Proposal Document
Fire Curtain
Date: 28.01.22
Version: 001
Contents
From studying the provided information, J&C Joel understand the requirement for the Fire
Curtain system. The proposal comprises the following in accordance with the provided
information.
The brail fire curtain system is the simplest and most cost-effective system of the two
described above.
This systems utilise Zetex fabric which is rated up to 30 minutes.
Zetex fabrics are woven from highly texturized continuous filament yarns and treated with a
proprietary vermiculite-based coating. The coating allows heat to dissipate evenly across the
surface of the fabric, significantly boosting its temperature rating and abrasion resistance.
1.2 Fire Curtain (brail option)
PRELIMINARIES
We will provide full design drawings (can be in SolidWorks and/or dwg, stp and ifc format as
well as PDF but BIM design not allowed for) including GA layouts and Shop Drawings, for
which we will require detailed As-Built construction drawings from the Main Contractor.
INSTALLATION
A team of two (2) experienced J&C Joel mechanical & electrical installation engineers will
lead teams during the installation period (estimated 3 weeks).
For the test-and-commission of the Control system, the appointed Control supplier will be on
site for a period of one (1) week to provide a satisfactory system and ensure all works
correctly.
LOGISTICS
Below is a list of exclusions as part of this bid proposal within the scope of works for the
Stage Machinery contract.
Materials:
- Secondary steelwork. J&C Joel will provide loading information and location requirement. It
is expected the design, supply and installation of secondary steelwork to be performed by
the Steelwork Contractor of which J&C Joel will liaise closely with.
- Electrical power & control cabling, containment, trunking and cable tray as required. J&C
Joel will provide sizing, cable types and routing advice. It is expected the design, supply and
installation of electrical cabling and containment to be performed by the Electrical Contractor
of which J&C Joel will liaise closely with.
Installation:
- Any cable installation or cabling works not included or described above is excluded.
- Any secondary steelwork works not included or described above is excluded.
- Access equipment excluded, this is expected to be provided by the Main Contractor.
- Forklift or any lifting equipment required during unloading excluded.
Logistics:
- Any and all import taxes, duties and clearance costs excluded
2 Quotation/BoQ
SUPPLEMENTARY COSTING SHEET
Status:
A-
B-
C-
SL SR
All dimensions in mm unless otherwise stated
Do not scale
Scale N/A Paper A1
Drawn by JRC Date 29/01/18
Rev
Drawing No 2298-GA-005 0
ID Task Task Name Duration Start Finish Jan '22 Feb '22 Mar '22 Apr '22 May '22 Jun '22 Jul '22
Mode 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09
1 Brail Fire Curtain 110 days Mon 31/01/22 Fri 01/07/22
2 Approval 5 days Mon 31/01/22 Fri 04/02/22
3 Approval 1 day Mon 31/01/22 Mon 31/01/22
4 Approval of Fabric 1 day Fri 04/02/22 Fri 04/02/22
5 Payment Date 50% 1 day Tue 01/02/22 Tue 01/02/22
6 Design 31 days Fri 04/02/22 Fri 18/03/22
7 Receive site As-Builts 1 day Fri 04/02/22 Fri 04/02/22
8 Design 4 wks Mon 07/02/22 Fri 04/03/22
9 Approval of drawings (Client) 1 wk Mon 07/03/22 Fri 11/03/22
10 Revisions of drawings 5 days Mon 14/03/22 Fri 18/03/22
11 Procurement & Manufacturing 95 days Mon 14/02/22 Fri 24/06/22
12 Mechanical Elements (Motors/Brakes) 8 wks Mon 14/02/22 Fri 08/04/22
13 Structural Elements (frame/guide, 4 wks Mon 14/03/22 Fri 08/04/22
smoke seals)
14 Zetex Plus Cloth 4 wks Mon 30/05/22 Fri 24/06/22
15 Logistics 60 days Mon 11/04/22 Fri 01/07/22
16 Mechanical Elements (sea freight) 6 wks Mon 11/04/22 Fri 20/05/22
17 Structural Elements (sea freight) 6 wks Mon 11/04/22 Fri 20/05/22
18 Zetex Plus Cloth (air freight) 1 wk Mon 27/06/22 Fri 01/07/22