To date : 1/30/2022

Updated checklist on action items

ID Item PIC Status Percentage Days Start End Day left Results (Respond) Actions
Elbarkal OPEN 0 2 1/30/2022 2/1/2022 2
1 Protection quantities & tools cross check
Protection requirement zones and doors TEG Complete 100 4 1/30/2022 2/3/2022 0 Zone will be specified by Protection, no Notifying the main contractor and subcontractor
2
problems regarding doors verbally
3 Protection time schedule Elbarkal OPEN 0 2 1/30/2022 2/1/2022 2
4 Doors Status - meeting with Peter Mr Ameen OPEN 0 2 1/30/2022 2/1/2022 2
5 Sandwitch panels quantities check Elbarkal OPEN 0 2 1/30/2022 2/1/2022 2
Roof Ceiling for internal stair TEG OPEN 0 2 1/30/2022 2/1/2022 2 Arrange with subcontractor to install flat
6
panel and cladding the steel beam
7 Frontmatic conveyor system Mr Ameen OPEN 0 2 1/30/2022 2/1/2022 2
8 Scopes finalization TEG OPEN 0 2 1/30/2022 2/1/2022 2 Arrange for a meeting Eng Maysaa and Eng Ola
9 Updating Extra Work Schedule Elbarkal OPEN 0 3 1/30/2022 2/2/2022 3
10 Excavation schedule Elbarkal OPEN 0 2 1/30/2022 2/1/2022 2
Time schedule of AC sub-contractor (Block Eng Yasir OPEN 0 2 1/30/2022 2/1/2022 2
11
F)