According to the contract, CESMP, laws, sort out the license documents
1.1 License list related to the project execution
a 1. Construction License Belmiro yuyang
b 2. License for water extraction; Jonas/Site managers yuyang
3. License for the borrow pit (Vilanculos Send an email to subcontractors and site
c and Chibuto); Leonel yuyang managers to explain the requirements procedure
2 Organizational Management
2.1 Local staff recruitment HSE Team, Site Managers, Professional Engineers, Claims Engineers wangjianpo yaohong
2.2 CESMP phase II Deadline:Phase II is predicted to be resubmitted in 04/03/2022 Leonel yuyang 3/4/2022 Waiting for the memorando to be signed
Existing and new employees Training on project management A plan with the training for internal members has
2.5 Training for members internally requirements, CESPM, before starting on-site work. Samira/Mirela yaohong been issued
2.7 Manual of CESMP and Contract Quality and HSE management process;CESMP;Contract content Leonel yuyang 2/20/2022 3/10/2022
3 Construction
3.1 Matalane Substation
3.1.1 Bush Clearing
3.1.1.1 Prerequisite
a Mobilization Certificate of operator and machinery/mobilization plan
b Recruitment procedure GBV/Safety Induction/
c Method Statement of bush clearing Approved
d Risk Assessment
F HSE document ready it is available at the site
g Route of the road to be identified Ste
h Disposal of the vegetation of the surface to be confirmed by OE
soil
HSE issue around the school beside the
I road
j a corner problem of land acquisition
k water supply pipe along the road
3.1.3 Earthwork
3.1.3.1 Prerequisite
a the drawing approvalof earthwork 3/15/2022
Approval of Method Statement of
b Earthwork 3/15/2022
b Substation area thickness of first surface soil is 150mm-200mm;removal of trees and its 2/21/2022 3/20/2022
roots;Tranportation of soil and vegetation
thickness of first surface soil is 100-150mm;removal of trees and its
c Camps facility area roots;Tranportation of soil and vegetation 2/21/2022 3/5/2022
3.2.3 Earthwork
3.2.3.1 Prerequisite
a Approval of earthwork drawing 4/20/2022
b Approval of Method Statement of 4/20/2022
Earthwork
c Approval of risk assessment 2/20/2022
d Borrow pit license 3/20/2022
e Approval of access road drawing 4/20/2022
f Mobilization plan 3/20/2022
3.2.3.2 Execution of earthwork
a Removal of surface layer of soil 4/21/2022 5/20/2022
b Earthwork backfilling and compaction 5/10/2022 6/30/2022
Approval of method statement of power Approved by EDM/ material stuff has arrive at the site,just waiting for
b supply permit from OE 2/16/2022
c Approval of subcontractor and laboratory Check if a well permit is required locally 2/16/2022
fro Well drilling
Approval of Mobilization plan for camps
d facility Material supplier to be approved 2/20/2022