Professional Documents
Culture Documents
1048/2 ط:اﻟﻣﺷروع
2020 ﺗطوﯾر ﺷﺑﻛﺔ اﻟطرق ﻟﻣﻌرض اﻛﺳﺑو
PROJECT: R1048/2
IMPROVEMENTS OF EXPO 2020 ROADS NETWORK
TENDER DOCUMENTS
EMPLOYER:
PROJECT R1048/2:
IMPROVEMENTS OF EXPO 2020
ROADS NETWORK
GENERAL INDEX
PROJECT R1048:
IMPROVEMENTS OF EXPO 2020
ROADS NETWORK
DUBAI SEWERAGE AND DRAINAGE
SPECIFICATIONS
CONTENTS
Page
2.0 EARTHWORKS
10.7 PLASTERWORK & OTHER WALL, FLOOR & CEILING FINISHES 10/8
10.7.1 Cement 10/8
10.7.2 Lime 10/8
10.7.3 Sand 10/8
10.7.4 Gypsum Plasters 10/8
10.7.5 Plaster Trims 10/8
10.7.6 Metal Lathing 10/8
10.7.7 Plasticisers 10/8
10.7.8 Bonding Agents 10/9
10.7.9 Storage 10/9
17.17 SITE TESTING AND COMMISSIONING OF ELECTRICAL AND MECHANICAL PLANT 17/15
21.1 SUBMITTALS
21.1.1 Materials and Equipment Schedule
21.1.2 No Objection Certificates
21.1.3 Shop Drawings and verification of Dimensions
21.1.4 Manufacturers Certifications
21.1.5 Recommendations of the Manufacturers
21.1.6 Spare Parts
21.1.7 Installations and Testing
21.1.8 Program / Progress Reports
21.1.9 Manufacturer’s Literature
21.1.10 Circuit Diagram
21.1.11 As Built Drawings and Operation & Maintenance Manual
21.1.13 Silence of Specification
21.1.14 System Explanations
21.1.15 Layout of Work
21.1.16 Clean Up
21.1.17 Warranty
21.1.18 Product Storage and Handling
21.1.19 Operation & Maintenance of the System
PROJECT R1048:
IMPROVEMENTS OF EXPO 2020
ROADS NETWORK
DUBAI SEWERAGE AND DRAINAGE
SPECIFICATIONS
PREFACE
All drainage and sewerage to be performed under this contract shall follow the specifications
given in Volume 2 – Part III and IV – Dubai Sewerage and Drainage Master Plan Standatd
specification. For all other works the contractor shall refer to the applicable specifications as
given in Volume 2 Part I and II.
Clause 1.2 of Dubai Sewerage and Drainage Master Plan Specifications shall not be applicable
to this Contract. The Contractor is referred to the requirements given in the General
Specifications with regard to the Site Office for the Engineer.
SECTION 1: -GENERAL
1.1.1 Preamble
1.1.2 Abbreviations
"ASTM" means the specification by the American Society for Testing and
Materials.
Where no units are quoted for a figure the relevant "System International"
(SI) unit should be assumed.
1.1.3 Datum
The Contractor shall make all the necessary arrangements for any land
required for working areas outside the right of way, including payment when
necessary, and the Employer does not accept any liability in connection with
such land. This includes land for compounds, temporary roads, detours,
diversions and stock piling materials.
Any soils and materials test results and information provided for the
Contractor with the Contract Documents at Tender stage are for his
information only. The Contractor shall be deemed to have studied this
information during the preparation of his Tender and to have carried out any
further tests as he may consider necessary. No claims for additional
payment will be considered from the Contractor on the grounds that the
information is insufficient, incorrect, or misleading.
The Employer and the Engineer accept no responsibility for any omissions
from or for correctness of the representation of existing features on the
Drawings.
The most recent edition of any standard shall always be adopted unless
otherwise stated in the Specification or directed by the Engineer.
The Contractor will be deemed to have carried out his own investigations at
the time of Tender to ascertain for himself the nature of the soil conditions
and in particular the groundwater levels that will be encountered.
1.2.1 General
The Contractor shall provide, maintain and keep clean temporary site offices
with all associated equipment and services for the exclusive use of the
Engineer's Representative and his staff, from commencement until
completion of the whole of the Works.
The offices shall have full partitions and room sizes shall be as shown in the
Schedule of Offices. All rooms shall have individual entrance doors.
The offices shall be air-conditioned with the exception of the Toilet, Shower
and Kitchen areas.
All rooms shall have glazed windows complete with fly screens and venetian
sun blinds.
The electrical installation shall provide for simultaneous use of all electrical
appliances.
The electrical supply shall be 220-250 volts, 50 Hz. The Contractor may
either arrange for a temporary power supply to the offices or alternatively
provide and maintain adequate diesel generator sets. All electricity bills shall
be paid by the Contractor.
The Contractor may either arrange for a temporary mains water supply or
alternatively provide tankered water supply. All water bills shall be paid by
the Contractor.
A minimum of two telephone lines with extensions shall be provided for the
offices along with a third line for an independent telefax facility as shown in
the Schedule of Fittings and the Contractor shall pay all installation and
rental charges, and call charges, if any, for UAE calls only.
Covered car parking areas of approved construction for ten (10) cars shall
be provided adjacent to the offices.
The Contractor shall submit any necessary drawings and calculations for the
construction of the offices for the Engineer's approval before commencing
construction and shall be responsible for ensuring that the offices are
structurally sound. The Engineer may request alterations at this stage. The
drawings shall be approved in writing by the Engineer before
installation/construction shall commence.
The offices shall be completed and all the equipment provided by the end of
the Mobilisation Period.
The Contractor shall provide all items listed in the following Schedule of
Offices and Schedule of Fittings. The Contractor shall obtain the Engineer’s
approval for all furniture and equipment proposed.
1 Resident Engineer 6m x 4m 1
2 Conference Room 8m x 4m 1
3 Assistant Resident Engineer / 4m x 4m 10
Civil Engineer / Landscape
Engineer / Materials Engineer /
Safety Engineer / Electro
Mechanical Engineer / Quantity
Surveyor/ Senior Quantity
Surveyor/ Senior structural
Engineer/ Structural Engineer
4 Materials Inspector 8m x 4m 1
5 Land Surveyor 8m x 4m 1
6 Inspectors Civil /Landscape 6m x 4m 2
7 Typist / Clerk / Filing 6m x 4m 1
8 Toilet 4m x 2m 4
9 Shower 2m x 2m 1
10 Kitchen / Store 4m x 2m 1
11 Store 4m x 2m 1
12 RTA Liaison Engineer 4m x 4m 1
13 Structural Inspectors 8m x 4m 1
1 2 3 4 5 6 7 8 9 10 11 12
* with email / internet connections. Computer shall be provided with Web Facilities for on-line
submission of test requests and on-line receiving of test reports.
2. The Contractor shall be responsible for the security of the building and its
contents at all times and shall employ watchmen for this purpose.
3. The Contractor shall supply the Consultant's staff with all safety clothing
and equipment that shall be necessary for site working such as safety
helmets, reflective waistcoats, etc.
4. The building shall be well constructed, burglar proof, mosquito proof and
weather proof and shall have sufficient doors and glass covered windows
for proper light and ventilation. Floors shall be covered with suitable,
approved flooring.
5. The Contractor shall retain on site for the exclusive use of the Engineer
all codes and standards referred to in the Specification.
7. Following the completion of the whole of the Works, the Contractor shall
remove the offices from the Site and reinstate the area to a natural
condition or as directed by the Engineer.
8. The building and all equipment, materials, fittings, etc., shall become the
property of the Contractor after the completion of the Works.
Within seven days of the date of the Letter of Acceptance issued by the
Employer the Contractor shall submit a plan or plans showing his proposed
locations for and details of:
The plan(s) shall be submitted to the Engineer in six (6) copies for approval.
Any reasonable changes or modifications suggested by the Engineer shall
be incorporated. All locations shall be subject to the approval of the
Employer.
Departures from the approved details shall not be permitted unless written
consent is obtained from the Engineer.
1.3.1 Materials
Materials delivered to the Site for the purpose of the Works, shall be
accompanied by a "Certificate of Guarantee" signed by the authorised
representative of the manufacturer, which will legally bind the manufacturer
to the product delivered.
Such Certification shall state that the materials specifications and test results
are in compliance with the specified requirement of the pertinent
designations of the most recent edition of ASTM, BS or any other approved
equivalent National Standard unless otherwise directed.
The Contractor shall stake-out the work as to lines and grade in accordance
with the Drawings and secure the approval of the Engineer's Representative
before constructing the work. The Engineer's Representative will, if he
deems it necessary revise the lines or grades and will require the Contractor
to adjust and to stake-out accordingly. The Contractor shall give the
Engineer's Representative not less than 24 hours notice of his intention to
set out or give levels for any parts of the Works, in order that arrangements
may be made for checking. The Contractor shall be responsible for
obtaining any setting-out data he may require from Dubai Municipality
Survey Section. The Contractor shall also be responsible for obtaining
Dubai Municipality Survey Section’s approval on right-of-way. Any costs
incurred in this shall be borne by the Contractor.
In the case of any variation from the approved works, the Contractor shall
give the Engineer three copies of cross-sections and profiles of the graphical
record or notes and computations of his stake-out as required by the
Engineer. At his option he may submit cross-mark on one copy with his
approval of the proposed lines of the work or his revisions thereof and return
it to the Contractor. The Contractor shall resubmit for approval any cross-
sections the Engineer may amend.
No permanent work shall be carried out without the consent in writing of the
Engineer's Representative. Full and complete notice, in writing, shall be
given 24 hours in advance of the time of the operation in order to make such
arrangements as deemed necessary for inspection.
1. The Contractor shall provide, erect and maintain such traffic signs, lamps
barriers and traffic control signals as may be necessitated by the
construction of the Works in accordance with Roads & Transport
Authority (RTA) and Dubai Traffic Police requirements. The Contractor
shall submit proposals for dealing with such situations to the Engineer,
RTA and Dubai Traffic Police for consent. Compliance with this Clause
shall not relieve the Contractor of any of his other obligations and
liabilities under the Contract.
3. The Contractor shall not commence any work which affects the public
highway until all traffic safety measures necessitated by the work are
fully operational.
4. The traffic diversion and signs, lamps, barriers and traffic control signals
shall be in accordance with the requirements of RTA (also refer to
Clause 11.5).
5. Traffic signs shall comply with the requirements of RTA. The flashing
rate for flashing lamps shall be within the range 120-150 flashes per
minute. The minimum luminous intensity of the lamps shall be 0.5
candela for steady lamps, 1.0 candela for ripple lamps at their peak, and
1.5 candela for flashing lamps at their peak.
6. The Contractor shall keep clean and legible at all times all traffic signs,
lamps, barriers and traffic control signals and he shall position,
re-position, cover or remove them as necessitated by the progress of the
Works.
The Contractor shall give three weeks notice to the owner/occupier before
entering private lands and the Contractor shall not enter on to those lands
until given permission by the Engineer.
The Contractor shall take great care and all reasonable precautions to
ensure that roads and thoroughfares used by him either for the construction
of the Works or for the transport of plant, labour and materials are kept clean
during of such construction or transport and in the event of their requiring
cleaning in the opinion of the Engineer the Contractor shall take all
necessary and immediate steps to clean them.
Each individual site of work must be clean during the work and must be
thoroughly cleaned up on completion.
If in the opinion of the Engineer the Contractor shall have failed to take
reasonable and prompt action to discharge his obligations in the matter of
site clearance or reinstatements, the Engineer will inform the Contractor in
writing of his opinion in which circumstances the Employer reserves the right
to carry out the reinstatement himself or to arrange for it to be carried out by
others or to make payments to the owners and occupiers in respect of such
matters for which the Contractor is responsible. All such costs incurred and
payments made will be deducted from any monies due or which shall
become due from the Employer to the Contractor.
Drains, pipes, cables and similar existing services encountered in the course
of the Works shall be guarded from injury or damage by the Contractor at his
own cost so that they may continue to function uninterruptedly to the
satisfaction of the owners thereof and the Contractor shall not store
materials or otherwise occupy any part of the site in any manner likely to
hinder the operations of such owners.
1. The Contractor shall protect and support, during the progress of the
Works, all pipe mains, cable wires and other apparatus which might be
endangered by his operations. The approximate positions and
alignments of known services are indicated on the Drawings, but no
guarantee of exact location can be given, and the Contractor must
communicate with the authorities and/or proprietors concerned to locate
them exactly, and he shall then prepare shop drawings 1/500 scale for
each Utility as directed by the Engineer. When approaching each
indicated position, the Contractor shall search, by safe methods which
will not endanger the service, to determine its precise position.
2. The Contractor shall make his own arrangement with the owners of the
services and with other persons interested, for any diversions, temporary
stoppages and reinstatements, and he shall allow in his programme for
all such arrangements.
4. The Contractor shall give notice, in writing, to the Engineer and to the
appropriate service company of all damages to existing services caused
by him or by any Sub-Contractor in the course of the Works. He shall be
held responsible for any such damage and shall immediately have such
damage made good at his own expense and shall relieve the Employer
of all claims in respect of any loss or interruption involved.
6. All existing sewers, culverts, water courses and drains of every kind and
condition that have been altered, extended or otherwise interfered with
either directly or indirectly by the work, or that may by leakage, silting,
stopping of free flow or otherwise interfere with or delay the execution of
the work, shall be made good, cleaned, placed in working order,
supported, maintained, and protected and the Contractor shall provide
everything necessary for efficiently dealing with, protecting, pumping or
removing, as the case may be, all water, sewage, or spoil there from.
If in the opinion of the Engineer it is necessary for the safety of the Works or
for any other reason, the Contractor shall, when so ordered, carry out the
Works, or any portion thereof continuously by day and night. The
Contractor will be reimbursed the agreed extra costs, provided the necessity
for the order is not a result of the Contractor's negligence.
Such approval, however, will not relieve the Contractor of his responsibility
for the adequacy of the staging. The cost of such staging is to be included in
the tendered rates and prices entered in the Bills of Quantities.
The Contractor shall carry out an investigation prior to submitting his Tender
as to the availability of water for the purpose of the Works and shall consult
and arrange with the appropriate authorities and consider all legal aspects.
The Contractor shall be entirely responsible for the supply of sufficient water
of the specified quality at all times throughout the Contract, and the costs
shall be deemed to be covered in the Contract rates and prices.
The Contractor, at his own expense, shall protect all works and materials
from injury by weather. All damage caused by adverse weather conditions,
whether by flooding or intense heat or any other weather conditions, shall be
rectified by the Contractor at his own expense. Abnormal weather conditions
shall not be considered any reason for a claim by the Contractor for
compensation for damage.
The Contractor shall at his own expense keep the works at all times well
drained and excavations whether above or below the normal water level of
the water table free from storm or percolating water which may accumulate
on the Site and which may interfere with progress of construction or has or is
likely to have deleterious effect on the work in progress or the use thereof,
by provision of temporary open drains and sub-soil drains, diversion of
ditches and other surface water channel or by pumping or other means as
required.
The Contractor shall provide and erect signboards as detailed in the BOQ, at
the Site and at the Offices of the Engineer and the Contractor. Normally
signboards will be required on all major road approaches to the Site.
The layout and lettering size and location of all signboards and their sitting
shall be subject to the approval of Roads & Transport Authority.
The signboards shall give, in English and Arabic, the name of the Project
and the names, Post Office Box numbers and contact telephone numbers of
the Employer, the Engineer and the Contractor. The boards shall be of
dimensions as shown on the drawings and shall be of durable construction
capable of withstanding the effects of the climate for at least the period of
the construction and the Defects Liability Period. The boards shall be
mounted on substantial frames.
1.3.16 Templates
When necessary the Contractor shall provide at his expense sufficient and
approved templates for the purpose of controlling the finished shape of
certain work. The templates will be in accordance with the Specifications and
Drawings where such are provided.
The Contractor shall also supply straight edges and lines when required to
control the work.
1. The Contractor shall provide and maintain for the use of the Engineer
such surveying and engineering instruments as the Engineer may
require for his duties as detailed in (Clause 1.3.18). The Contractor shall
provide the Engineer with all necessary assistance in checking the
setting out of the Works and interpreting any information used by the
Contractor for this purpose including the sole use of a minimum of three
(3) chainmen.
2. The Contractor shall provide the Engineer with all assistance, equipment
and material required to document and record progress of the Works.
5. The Contractor shall provide all unskilled labour and necessary tools as
directed by the Engineer.
6. If at any time before the commencement or during the progress of the
work it appears to the Contractor that for the proper execution of a
specified part of the Works, shop drawings are necessary, these
drawings shall be established by the Contractor and submitted to the
Engineers' Representative for approval. The Engineer's Representative
shall have authority to order at any time and the Contractor shall agree to
Such record Drawings produced by the Contractor shall include but not
be limited to the following information:
1.3.19 Laboratory
1.3.19.1 General
3. Dubai Municipality shall charge the Contractor for all testing and
re-testing. Also Dubai Municipality shall, at the discretion of the
Engineer, have the right to charge for additional material testing where
this additional testing is, in the view of the Engineer, caused by
negligence or insufficient testing prior to submission of materials on the
part of the Contractor. All charges for testing and/or re-testing will be at
Dubai Municipality standard rates current at the time of testing/re-
testing.
4. The testing of the Works by the Dubai Municipality does not absolves
the Contractor of his responsibility for the quality control of
workmanship and materials.
7. All sampling for such tests shall be carried out by the Consultant's
Inspectors and labelled as per the relevant standard sampling
requirements (as listed in Clause 1.3.20).
BS EN 12350
Slump test and compaction factor
ASTM C 1084
Minimum cement content of
hardened concrete as directed by
the Engineer.
Precast Flexural/Transverse strength and BS EN 12390
Concrete water absorption for each BS EN 1339
supplier of precast kerbs and
slabs (2 no. samples).
Subsequently on approval of a
source or supplier 2 samples will
be tested every 2000 linear metre
for kerbs and every 2000 m² for
slab tiles.
The Contractor shall be responsible for obtaining the Approval of the local
Authorities for the sources of materials and he shall have no right to claim for
any compensation if he is to pay for the material at its source.
In planning his programme the Contractor shall allow reasonable time for the
Engineer to confirm setting out details as the Works proceed in accordance
with the programme.
site work will be carried out and the location of plant and labour. The format
of the programme shall be agreed with the Engineer. The Contractor shall
also submit for the Engineer’s approval a daily record of manpower and
plant resources.
Weekly Report
The report shall include: the meteorological data; Contractor's plant and
labour returns; a brief summary of work completed.
Monthly Report
The report shall include: a description of the month's work; details of any
problems relating to the Works; quantities; records of test results; charts
illustrating progress in terms of work done against programmed work and the
financial status of the Contract including value of works completed, certified
and monies received; progress photographs.
The Contractor shall provide the Engineer on the last day of each month one
set of progress photographs, with dates imprinted on it, which shall comprise
the following:
- Ten colour prints (294 x 210 mm) of each of a maximum of twenty of the
negatives as selected by the Engineer.
The copyright of all photographs shall be vested in the Employer and the
negatives and prints shall be delivered to the Engineer within 4 days of
exposure.
During the execution of the Works the Contractor shall maintain flows in
pipelines and at pumping stations or alternatively provide adequate means
of diverting the flows or overpumping of the flows to the satisfaction of the
Engineer.
The Contractor should note that the Employer may decide to carry out
overpumping utilising his own plant and resources and the Contractor shall
make due allowance for the necessary coordination with the Employer with
respect to the Contract programme. Such arrangements will not relieve the
Contractor of his obligations for the maintenance of flows and the safety of
the Works, personnel and the general public.
No claim for delay or additional work arising from this requirement will be
considered by the Employer.
The Contractor shall give four weeks notice in writing to the Engineer of his
intention to commence work on any public road (which shall include un-
made rights-of-way).
The closure of public roads will not be permitted without the written
permission of the Roads & Transport Authority - Roads Department, the
Dubai Traffic Police and the Engineer. The Contractor shall submit five (5)
copies of his proposals for diverting traffic indicating positions of all signs,
cones, lights and anything else which may be necessary. The Contractor
shall comply with any Specification for traffic diversion, including surfacing
requirements, safety and control laid down by the Authorities in Dubai and
shall be responsible for continuous maintenance.
In the event of such permission being refused the Contractor shall have no
claim for any additional payment.
The Contractor’s work shall be so arranged that use of the roads affected by
the work shall be restored to the public with the minimum of delay. Laying of
the pipelines, backfilling, testing of the pipeline, temporary reinstatement and
clearance of the Site shall follow closely behind excavation and the Engineer
may limit the length of excavation when necessary.
Unless otherwise specified, the areas designated for clearing and grubbing
shall be cleared of all trees, stumps, bushes, roots, rubbish, debris, and
other objectionable matters.
Before removal of any trees or shrubs the Contractor shall obtain written
consent from Dubai Municipality Horticultural Section at least two weeks in
advance of the planned removal. The Engineer's approval of any removal of
trees and undergrowth must be obtained before commencement of work.
Trees and plants designated for preservation shall be protected from injury
or damage which could result from the Contractor's operations including
dewatering. The form of protection for vegetation within the site shall be of a
type and standard approved by the Dubai Municipality Horticultural Section.
For the full width to be cleared, all objectionable materials and any other
obstructions shall be grubbed from areas to be excavated, to the satisfaction
of the Engineer.
All tree trunks, stumps, bush, limbs, roots, vegetation, and other debris
removed in clearing and grubbing shall be either burned or removed to
approved location outside the right-of-way or otherwise disposed of so as to
leave the roadway and adjacent areas free from unsightly debris. Burning
shall be done at such time and in such manner as to prevent any damage to
areas adjoining the right-of-way.
2.2.1 General
The Contractor shall raze, remove and dispose of all structures and
obstructions as required including, but not limited to, the following: buildings,
sheds, walls, slabs, foundations, inlets, catch basins, culverts, headwalls,
trash racks, irrigation structures, standpipes, manholes, valves, ditch lining,
pipelines, tanks, pool lining, posts, poles, columns, signs, fences, gates,
planters, curbs, gutters, sidewalks, driveways, trees, stumps, shrubs and
plants.
2.3.1 General
The Contractor shall notify the Engineer a sufficient time in advance of the
beginning of excavation to allow pre-construction measurements and
records to be made of the undisturbed ground (refer to Clause 2.3.2). The
required excavation shall then be performed in reasonably close conformity
The Engineer may direct the Contractor to protect his excavation with
timbering where, in his opinion, such timbering is necessary to ensure the
safety of the workmen, adjoining structures and work generally. Any action
taken by the Engineer in this regard will in no way relieve the Contractor of
any responsibility or liability under the Contract.
No back throwing shall be allowed and all materials must be brought to the
surface and placed clear of the trench side.
The Contractor shall keep the trench excavation free from water at all times.
The Engineer reserves the right to direct the Contractor as to the lengths of
trench or portions of bulk excavations which shall remain open at any one
time.
The use of explosives for any purpose whatsoever during the Contract is
prohibited.
(1) Ground levels shall be agreed at suitable intervals with the Engineer's
Representative.
Where pipelines are to be laid in agricultural land the surface and subsoil
drainage shall be maintained whether natural or artificial. Before
commencing work the Contractor shall ascertain from the owner or occupier
of the land the location of any existing land drains or mole drains.
The sides and/or the bottom of excavations in excess of 1.2 metres shall be
adequately supported.
The Contractor shall provide the necessary support for excavations and shall
submit to the Engineer his proposals for the supporting of excavations by
trench sheeting or other approved means at least seven days prior to the
commencement of any excavation works. His proposals shall take into
account the nature of the ground to be excavated, the level of the water
table at the site and the proximity of buildings and roads.
If in the opinion of the Engineer the support proposed for the excavations by
the Contractor is insufficient then the Engineer will order the provision of
stronger support than that provided by the Contractor and in this event the
Contractor shall adopt the methods so ordered by the Engineer and shall
have no claim against the Employer for any costs incurred in adopting the
additional measures.
Timbering steel sheeting strutting and sheet piling for the support of
excavations where provided shall be fixed in accordance with BS 6031.
2.3.8 Dewatering
A high water table is expected and the Contractor must do all necessary
measures to ensure proper dry conditions are maintained at all times during
construction. The Contractor shall provide and maintain ample means and
devices (including spare units kept ready for immediate use in case of
breakdowns) with which to intercept and/or remove promptly and dispose
properly of all water entering trenches and other excavations. Such
excavations shall be kept dry until the structures, pipes, and appurtenances
to be built therein have been completed. In addition precautions shall be
taken to prevent floatation of partially built structures, completed structures
to be filled on commissioning of the Works and pipelines awaiting backfilling.
Method statements shall include proposals for disposal of the water arising
from dewatering systems.
All water pumped or drained from the work shall be disposed of in a suitable
manner without undue interference with other work, damage to pavements,
other surfaces, or property. Suitable temporary pipes, flumes, or channels
shall be provided for water that may flow along or across the site of the work.
No such water is to be disposed of into the existing sewer systems of the
town or otherwise without prior written approval of the Dubai Municipality
Drainage and Irrigation Department.
If permission is given to use new or existing pipes or culverts which are not
part of the live sewerage system, they shall be thoroughly cleaned of all silt
and any resulting damage made good after use.
During use the Contractor shall be responsible for the condition of the
pipeline, duct, etc., and any defect or failure shall be made good at the
Contractor's expense. Any delay to the Contractor's works caused by such
defect or failure shall be deemed as the Contractor's responsibility.
After use by the Contractor such pipeline, duct, etc., shall be handed back to
the Municipality in a condition not less than that at the commencement of
use. Any repairs or replacement required shall be at the Contractor's
expense.
All temporary works for control of water shall be sited clear of the Works,
except where temporary sub-drains under the Works are approved in which
case the pipes shall be laid with a 75 mm surround of gravel, and the top
surface of the surround shall be covered with tarred felt cloth or other
approved material.
Unless otherwise directed all temporary drains and sub-drains shall be finally
sealed with concrete at approved intervals and all temporary ditches, sumps,
wells, etc., shall be refilled and reinstated as specified elsewhere.
In the exceptional event that lagoons for the storage of groundwater are
permitted, they must be suitably protected with fencing and attended by day
and night to prevent access by the general public and will not be sited
adjacent to buildings. Approved means of preventing the formation of
mosquito larvae on the surface of the lagoons will be employed.
All necessary precautions shall be taken to prevent any groundwater from
entering mains to be used for the conveyance of potable water.
A. Temporary Underdrains
Where the nature of the Works necessitates, the Contractor shall dewater
the excavations by means of an efficient wellpoint drainage system which
will drain the soil and prevent saturated soil from flowing into the excavation.
The wellpoints shall be designed especially for this type of service. The
pumping unit shall be designed for use with the wellpoints, and shall be
capable of maintaining a high vacuum and of handling large volumes of air
and water at the same time.
2.3.9 Formation
The formation of excavations for pipelines shall be dry, even and free of
stones and other protrusions.
A. Safety
B. Description
The Contractor shall make excavations in such a manner and to such
minimum widths as will give adequate room for building the structures or
laying and jointing the piping; shall furnish and place all sheeting, bracing,
and supports; shall carry out all cofferdamming, pumping, and draining, and
shall render the bottom of the excavations firm and dry and acceptable in all
respects.
In no case, except with the approval of the Engineer, shall the earth be
plowed, scraped, or dug by machinery so near to the finished subgrade as to
result in the disturbance of material below said subgrade, the last of the
material to be excavated shall be removed by hand immediately before the
placing of the pipe, masonry, or other structure.
From areas within which excavations are to be made, loam and topsoil shall
be carefully removed and separately stored to be used again as directed, or
if the Contractor prefers not to separate surface materials, he shall furnish,
as directed, loam and topsoil at least equal in quantity and quality to that
excavated at no cost to the Works.
F. Bridging Trenches
The Contractor shall, at his own expense, provide suitable and safe bridges
and other crossings where required for the accommodation of travel, and to
provide access to private property during construction, and shall remove
said structures thereafter.
G. Road Signs
All existing road signs, street name plates and the like affected by the Works
are to be carefully taken down and stored. Signs to be re-erected shall be
cleaned, provided with new fixings where necessary and the posts
re-painted as required. Redundant signs shall be transported to the stores
or depots of relevant Authorities. Any sign, street name plate or the like
damaged by the Contractor during his operation shall be repaired or
replaced at the Contractor's cost.
Should the Contractor excavate to a depth greater than that required for the
construction of the foundations or pile caps, such excavation shall be filled
with Class C concrete at his own expense. Should the material forming the
bottom of any excavation, while acceptable at the time of excavation,
become puddled soft or loose during the progress of the Works, the
Contractor shall at his own expense, remove all such softened or loosened
material and replace with Class C concrete as directed by the Engineer's
Representative.
The width and depth of the trenches for electrical and telephone
cables/ducts shall be as specified in the relative drawings or as ordered by
the Engineer. Banks may be sloped or widened to facilitate placement of
cables, but not the extent that will cause interference with other utilities and
structures. No battering of trenches shall be allowed under existing
carriageways, unless otherwise agreed by the Engineer.
2.3.14 Excavated Material
All excavated material will remain the property of the Employer unless
designated as surplus to the Contract requirements in which case it will be
removed from site immediately. The Contractor shall dispose of such surplus
material as per Clause 2.3.16.
- Certain separate areas will be designated for the disposal of hard debris
such as building rubble, broken concrete, kerbing, road pavement and
the like. The Contractor shall use only these designated areas and shall
keep these disposal areas neat and tidy at all times.
2.3.17 Cofferdams
No timber or bracing which will extend into the concrete shall be left in
cofferdams or cribs.
Any pumping from the interior of any foundation enclosure shall be done in
such a manner as to preclude the possibility of any portion of the concrete
material being carried away. No pumping will be permitted during the placing
of concrete or for a period of at least 12 hours thereafter, unless it is done
from a suitable sump separated from the concrete work by a watertight wall.
Pumping to remove water from a sealed cofferdam shall not begin until the
seal has set sufficiently to withstand the hydrostatic pressure.
Cofferdams or cribs, including all sheeting and bracing, shall be removed by
the Contractor after the completion of the substructure. This removal work
shall be carried out in such a manner as not to disturb or mar the concrete.
2.4.1 General
Backfilling of trenches other than in roads and paved/ tiled areas shall
normally be carried out using selected excavated materials similar to the in-
situ materials in which the trench or structure is being constructed.
Material for backfilling may be selected from any part of the site and
methods of selection may include sieving to remove large particles or
methods of hand or machine sorting together with soil classification and soil
property testing.
Cohesive Soils
Cohesive soils shall be placed in layers not greater than 150 mm thick
(compacted thickness) and compacted such that throughout each layer
placed in-situ the dry density is not less than 95% of the maximum dry
density of the soil.
If site trials show that the specified compaction can be achieved with layers
greater than 150 mm compacted thickness approval may be given to backfill
in layers of greater thickness, but not exceeding 250 mm, providing the plant
utilised is that used for the trials.
The placement moisture of the soil shall be within the range 2% above to 2%
below the optimum moisture content of the soil.
Granular Soils
Granular soils shall be placed in layers not greater than 150 mm thick
(compacted thickness) and compacted such that throughout each layer
placed the dry density is not less than 95% of the maximum dry density as
determined by BS 1377: 1990: Part 4: cl 3.5 or 3.6 on the same soil at the
same moisture content.
If site trials show that the specified compaction can be achieved with layers
greater than 150 mm compacted thickness approval may be given to backfill
in layers of greater thickness, but not exceeding 250 mm, providing the plant
utilised is that used for the trials.
For free draining granular soils that have no clearly defined optimum
moisture content, compaction shall be carried out to achieve a relative
density of not less than 95%. During compaction the soil shall be made as
wet as practicable.
Testing of Backfill
Tests to determine the optimum dry density of the backfill material shall be
carried out as directed using BS 1377: 1990: Part 4: cl 3.5 or 3.6, the
frequency depending on consistency of material and test results.
Unless directed otherwise on site testing for density and moisture content of
in-situ soils shall be at the minimum rate of :-
(2) One test per backfill layer for every 30 linear metres of pipeline trench
backfill laid in one operation.
Where a land drain passes through an excavation the backfill shall first be
taken up to form a bed for replacement pipes. The severed drains shall then
be exposed at each side of the trench to allow for connection and laying of a
new drain across the excavation. This new drain shall be of similar pipes of
the same diameter as those in the existing drain. Before any further
backfilling is done the Contractor shall notify the owner or occupier to enable
him to inspect the reinstated land drain. The replacement drain shall be
surrounded with pipe bedding to a minimum thickness 150 mm before
further backfilling.
The material used for special backfill shall be obtained from designated and
approved sources.
Material shall not be placed against any concrete abutment, wing wall,
retaining wall, box culvert or similar structure until the concrete has been in
place at least 14 days, unless otherwise authorised.
Structural Filling
Structural filling shall be carried out using approved well graded natural
sands and gravel or special backfill in accordance with Clause 2.4.3.
Non-Structural Filling
The material and the procedure for Non-Structural filling shall be same as
outlined in Clause 2.4.2.
After the cables/ducts have been laid, the trench refilling shall commence
with approved fill in compacted layers not exceeding 200 mm thick, each
layer being well compacted by hand with iron rammers weighing not less
than 5 kg, until the trench has been filled to a height of 300 mm above the
top of the cable/duct.
The remainder of the trench shall then be refilled in compacted layers not
exceeding 200 mm in thickness, each layer being well compacted with
power rammers, vibrating plate compactors or other mechanical means of a
type to be approved until the ground is thoroughly consolidated up to the
required level for surface reinstatement. Each layer should be not less than
95% of its maximum dry density. Should the quantity of the excavated
materials be not sufficient, due to unsuitability or otherwise, for the process
of backfill and fill, the Contractor shall obtain the quantity required of such
backfill and fill from approved borrow pits and transport same to the site of
work at his own expense.
Trenches shall not be backfilled until all required tests are performed and
until the Engineer has verified that the cables, etc., have been installed in
accordance with the Specifications and Drawings.
Lumps and clods shall be broken up before use. Materials shall not be
dropped from a height and where directed water shall be added to assist in
adequate consolidation.
Where cover to cables/ducts is less than 400 mm, or where ordered by the
Engineer, protection in the form of concrete encasing shall be provided
according to an approved drawing or as ordered by the Engineer.
2.5.1 General
Where new pipes, mains, cables/ducts, etc., are to be laid alongside, over or
under the existing, the Contractor shall take care to interfere as little as
possible with the existing services and connections thereto and any damage
shall be repaired by the Contractor to the approval of the appropriate
Authority or by appropriate Authority at the cost of the Contractor.
The Contractor shall make all arrangements for protecting existing services
and for temporarily diverting them to maintain the services without
interruption.
Existing services, pipes, mains, ducts, etc., exposed in trenches for new
work shall be protected in accordance with the requirements of the relevant
Authority before trenches are refilled.
The Contractor shall lay cables, fittings, specials, etc., under hedges, fences,
walls, etc., as necessary.
Where hedges are damaged or destroyed the whole shall be restored and
reinstated with shrubs of the same kind as the hedge, planted in due season
in an approved manner and fenced on each side with post and rail stock
proof fences finished on top with one strand of galvanised barbed wire, or
otherwise protected as required by the owners or occupiers and the
Engineer.
Where fences or walls are damaged or destroyed the whole shall be
restored and reinstated with like materials to the satisfaction of the owners or
occupiers and the Engineer.
The grass shall be well watered four times a day and the Contractor will be
required to keep the grass cut short until the Defects Liability Certificate has
been issued.
Trenches and other excavations within road corridors may be opened in four
types of ground:-
The Dubai Municipality Horticulture Section will remove any trees, bushes
and plants from developed reservations that they wish to preserve prior to
the commencement of work by the Contractor. The Contractor must allow in
his rates for the removal and disposal of any remaining trees, bushes and
plants necessary for the execution of the Works and to keep sweet soil
separate in accordance with the current Local Order.
3.1 GENERAL
The prevailing standard for all concrete work shall be BS 8110 and such
amendments as shall be approved by the Engineer in accordance with the
CIRIA Guide to Concrete Construction in the Gulf Region.
3.2 MATERIALS
3.2.1 Cement
The complete range of chemical tests, test methods & specifications for
cement are as shown the following table:
3.2.1.1 General
Unless otherwise approved by the Engineer all cements shall comply with
the following requirements:
- The specific surface (fineness) shall not be greater than 375 m2/Kg and
not less than 280 m2/Kg when tested as described in BS EN196-6.
Sulphate resisting cement (SRC) shall comply with BS 4027: 1996, Class
42.5 N or ASTM C150 Type V. The heat of hydration shall not exceed 290
KJ/Kg at 7 days when tested in accordance with BS 4550: Part 3: Section
3.8.
Moderate sulphate resisting cement (MSRPC) shall comply with ASTM C150
Type II but containing not less than 4% and not more than 8% proportion by
weight of tricalcium aluminate. In either case the cement shall not contain
more than 2.7% proportion by weight of sulphur trioxide.
Fine aggregate for concrete shall consist of natural screened and washed
sand or crushed sand having hard and durable particles, or of other inert
materials with similar characteristics. It shall not contain harmful material
such as salts, clay lumps, tree roots, shale, iron pyrites, coal, mica, organic
matter or any deleterious matter which may attack the reinforcement, in such
a form or in sufficient quantity to affect adversely the strength and durability
of the concrete. If necessary, the aggregate shall be washed and sieved to
remove the deleterious substances. Beach sand shall not be permitted for
use in concrete mixes.
The fine aggregate shall comply in all respects with the requirements of BS
EN 12620 and shall also comply with Dubai Municipality Administrative
Order No. 143/91. In addition to the above, fine aggregate for concrete shall
meet the requirements in Table 3-1.
Fine aggregate of fine grading (BS EN 12620) shall not be used. Fine
aggregate shall conform to one of the gradings given in Table 3-2 (reproduced
from BS EN 933-1)
10 100 100
5 100 100
2.36 60 - 100 65 - 100
1.18 30 - 90 45 - 100
0.60 15 - 54 25 - 80
0.30 5 - 40 5 - 48
0.15 0 - 15 0 - 15
The coarse aggregate shall comply in all respect with the requirements of
BS EN 12620. The coarse aggregate shall also fulfill the requirements in
Table 3-3.
Type Permissible
Test Method
Limits
1. Flakiness Index BS 812: Part Max. 25
105.1
2. Elongation Index BS 812: Part Max. 25
105.2
3. Ten Percent Fines Value or BS 812: Part 111 Min. 100KN
Impact Value BS 812: Part 112 Max. 30%
4. Los Angeles Abrasion ASTM Max. 30%
C131/C535
5. Shell Content BS EN 933-7 Max. 10% by
weight
6. Magnesium Sulphate ASTM C88 Max. 12%
Soundness (5 Cycles)
7. Clay Lumps and Friable ASTM C142 Max. 1% by
Particles weight
8. Material Finer than 0.075 ASTM C117 Max. 1%
mm
9. Acid Soluble Chlorides (Cl) BS 812: Part 117
The coarse aggregate shall conform to the gradings given in Table 3-4 in
accordance with the nominal size of aggregate specified (reproduced from
BS 882).
3.2.5 Water
3.2.5.1 General
Water for washing aggregate and for mixing or curing of concrete shall be
fresh, clean and substantially free from oil, acids, alkali, sewage, deleterious
mineral or organic matter. Water shall comply in all respects with BS 3148. It
shall not contain impurities in sufficient amounts to cause discoloration of the
concrete.
All sources of water for use with cement shall be approved by the Engineer.
Sources of water shall be maintained at such depth and the water shall be
withdrawn in such a manner as to exclude silt, mud, grass and other foreign
matter. If at any time during construction the water from an approved source
becomes unsatisfactory, the Contractor will be required to provide
satisfactory water from some other source.
Water for washing aggregate and for mixing or curing of concrete shall be
tested in accordance with BS and ASTM standards and shall meet the
following requirements:
Maximum
Parameter Concentratio Test Method
n Limit
1. Chlorides as C1 250 mg/l ASTM D512
2. Sulphates as SO 3 350 mg/l ASTM D516
3. Alkali carbonates and
bicarbonates 500 mg/l ASTM D513
4. Total dissolved ions,
including 1, 2 & 3 above 2,000 mg/l BS 1377: Part 3
5. pH Min. 7/max. 9 ASTM D1293
The temperature of water for concrete should not be less than 5°C nor more
than 25°C. Water may be cooled to not less than 5°C by the gradual addition
of chilled water or ice but on mixing, no ice particles should be present in the
mix. Alternatively, flaked ice may be used. The ice to be used should be
crushed and should be the product of frozen water which complies with the
above requirements.
3.2.6 Admixtures
Where the use of admixture had been agreed by the Engineer, they shall
conform to the requirements of Type A, Type D, Type F or Type G as
specified in ASTM C494 and shall be used in strict accordance with the
manufacturer’s instructions. The Contractor shall be entirely responsible for
the use of any approved admixtures.
The cost of such admixtures shall be included in the cost of concrete and no
extra payment shall be made if they are used. The proportions of cement,
fine aggregate and water shall be determined by the Contractor before
concreting commences and submitted together with such test results as may
be required to the Engineer for approval and the Contractor shall not
commence concreting before such approval is given nor shall he alter or
vary in any way the proportion of mix unless he submits fresh test results
and mix proportions to the Engineer for approval.
The approval by the Engineer of such mix designs does not in any way
absolve the Contractor of any of the requirements of the Specifications.
The chloride and sulphate levels in the concrete mix shall comply with the
requirements of Table 3-7.
Chlorides as Sulphate as
Type of Concrete C1* SO 3 *
(According to (According to
BS 1881:Part BS 1881:Part
124)AMD 1:98 124)AMD 6:02
a. For reinforced concrete
if made with OPC/MSRPC 0.30% 3.70%
if made with SRPC 0.06% 3.70%
b. For mass concrete
if made with OPC/MSRPC 0.60% 3.70%
if made with SRPC 0.12% 3.70%
c. For prestressed concrete and 0.10% 3.70%
heat-cured reinforced
concrete
*Maximum limits of chloride and sulphate content as a percentage by weight
of cement in the mix.
The OPC and MSRPC cements can also contain chlorides, the relevant
standard BS EN 196-21 allows up to 0.1% C1. Therefore any chloride
content present in the cement has to be taken into account while computing
total C1 in the mix. In case the cement contains the maximum limit of 0.1%
Cl, then the aggregates, water and admixtures used for prestressed
concrete or heat-cured reinforced concrete should be absolutely free of
chlorides.
NOMINAL PROPORTIONS
G1 1 1
G2 1 2
G3 1 3
The amount of water (satisfying Clause 3.2.5) added shall just be sufficient
to make the mortar or grout workable consistent with its purpose.
Before any material from a particular source is used, the Contractor shall
obtain representative samples of fine and coarse aggregates and carry out
the necessary tests and analyses to show that the samples comply with the
Specification. During the progress of the Works, the grading and chemical
characteristics may be checked at frequent intervals. Sampling of
aggregates shall be carried out in accordance with BS 812: Part 101 and
Part 102.
The results of these tests shall be submitted to the Engineer and his
approval shall be obtained before any of the material is used in the Works.
Part of each sample will be required for concrete trial mixes and part shall be
retained for comparison with subsequent deliveries.
The concrete shall be mixed in a power driven machine of the batch type, no
hand mixing being allowed. The mixer shall be large enough to admit the
use of 1 cement bag or container or whole multiples of bags or containers at
a time. The mixing shall continue until there is a thorough distribution of the
materials and the mass is uniform in consistency and colour. The period of
mixing, judged from the time that all the ingredients including water are in
the mixing drum shall be as ordered by the Engineer's Representative but
shall not be less than 2 minutes or 20 revolutions of the drum whichever is
the longer. Should there be for any reason a stoppage of greater than 30
minutes, the drum or other containers of the mixer shall be thoroughly
washed and cleaned before mixing is resumed. On completion of the mixing
the concrete shall be discharged onto clean boards or into clean barrows.
The method of discharge from the mixer shall be such as to cause no
segregation whether partial or otherwise of the concrete materials.
Concrete which has commenced to set shall not be remixed either with or
without additional water and in no case shall such concrete be used in the
Works.
1. Sampling Cubes
Thereafter one sample shall be taken at random for each class of concrete
in accordance with Clause 4/31 of the Specification.
From each sample three cubes shall be made for testing at 28 days and
three for testing at 7 days for control purposes.
These samples shall be taken from every 100 batches, but at least once a
week during concreting operations, and shall coincide with sample taken for
test cubes.
If the any above criteria are not satisfied, the unit represented by the
sample is questionable and the following actions may be instructed as
appropriate:
If the range of individual cube strengths made from the same sample
exceed 15% of the mean, then the method of making, curing and testing
cubes shall be checked. In the event of a sample having a range
exceeding 20%, the result shall be unacceptable and the Engineer may
order any of following actions:
In the event cutting and testing of cores are required, the Contractors
shall cut cores from approved locations and test them to BS.
3.3.7.1 General
After the materials have been approved and at least 10 days before any
concrete is poured, the Contractor shall make preliminary sets of test cubes.
Each set of test cubes shall comprise of three cubes made from a single
sample of concrete taken from the point of final discharge of the wet
concrete. Each cube shall be made under the Engineer's Representative
supervision. Six cubes shall be made to test three at 7 days and three at 28
days after manufacture. Preliminary test cubes shall be made and tested for
all grades of concrete and for all proposed variations of quality, quantity or
origin of the aggregates and cement.
Should either the test cube crushed at 7 days or that crushed at 28 days fall
below the specified requirements and the failure is confirmed by the testing
of the third cube, the Contractor shall, on the Engineer's Representative's
instructions alter the mix design and/or the source of aggregates, cement or
water and/or the method of mixing including alteration of the type of mixer.
The compressive strength of the concrete cube at 7 days shall be equal to or
more than two thirds the required compressive strength at 28 days.
During the course of the construction of the Works, the Contractor shall
make test cubes as required by the Engineer's Representative. One set of
six cubes will normally be taken from each individual concrete member, e.g.
culvert invert, Irish crossings, but additional cubes shall be taken as directed
by the Engineer's Representative. Three cubes will be tested at 7 days and
three cubes at 28 days as the Engineer's Representative directs. Where the
strength of the concrete is shown to be below that specified, the Contractor
shall remove and replace at his own expense all concrete from the
concerned pour. The Engineer may require the Contractor to cut out
defective concrete from the Works at his own expense even though test
cubes made from that concrete have not failed.
The Contractor shall carry out slump test in accordance with BS 1881: Part
102 and/or compacting factor test in accordance with BS EN 12350-4 at
such frequency as the Engineer's Representative considers necessary to
ensure that the workability and consistency of the concrete is maintained in
accordance with the specified mix or accepted mix design and the trial mix.
But in any case workability tests shall be carried out at least once every two
hours during which concrete is being mixed.
During the mixing and casting of concrete the frequency of testing for control
purposes shall be as indicated in Table 3-8 or as directed by the Engineer's
Representative. No direct payment is made for testing. The price of this work
is to be included in the bid prices of concrete.
Concrete shall be taken from the place of mixing to the place of depositing
by approved methods which will prevent the segregation or loss of the
ingredients and which are sufficiently rapid to ensure that the concrete does
not commence to set before it is compacted in position. The concrete shall
be deposited as near as possible to its final position in the Works and shall
not be allowed to flow into position. Deposition of the concrete through
chutes shall not be permitted and neither shall the concrete be dropped
freely from a height exceeding 2.0 m. Pumping concrete through delivery
pipes may be permitted but only with the prior approval of the Engineer's
Representative.
The concrete shall be placed in its final positions as soon as possible after it
has been mixed, and in any case before the initial set has taken place. The
Contractor shall ensure that concrete which has already been placed in
position and commenced to set is not disturbed by the placing or compaction
of further concrete nearby. All concrete shall be carefully worked around and
between reinforcement and all other embedded fittings without such
Concrete shall not be placed when the shade air temperature exceeds
40° C or during periods of windblown dust or rain.
These measures are in addition to those specified for the curing of concrete.
3.5.1 Tamping
3.5.2 Vibrating
All concrete shall be protected from the harmful effects of sunshine, drying
winds, rain, flowing water, or other adverse effect. For at least 7 days after
placing, the concrete shall be prevented from drying out by being sprayed
with fresh clean water and covered with hessian, clean sand or other
approved material which shall be kept wet.
The concrete curing compound shall comply with the following requirements:
The Contractor shall ensure that all concrete is adequately protected against
inclement weather until properly set and shall if necessary provide additional
protection to that specified above.
carefully organized to ensure that the above mentioned interval shall not be
exceeded.
The sealing compound shall adhere firmly to the concrete in all weather
conditions. The sealing compound shall not flow either along or down the
joint during hot weather. The sealing compound shall be durable and shall
not weather beyond the forming of a thin surface skin.
Waterstop shall be extruded from high grade grey PVC Compound. Flat
Dumbell plain web waterstop shall be used for a Construction Joint while for
an Expansion Joint or a Contraction Joint, a centre bulb waterstop shall be
used. The width of the waterstop shall depend upon the concrete thickness,
the aggregate size and the position of reinforcement. In general, the
following shall be taken as a guide to select the width, w, of a waterstop:-
The Contractor shall not proceed with the surface finish or making good of
concrete surfaces until he has received the Engineer's Representative's
permission to do so and he shall not apply cement slurry or mortar or any
other coating to the concrete surfaces from which the shuttering has been
struck until the concrete has been inspected and approved by the Engineer's
Representative.
Throughout the progress of the concrete work the Contractor shall employ
and provide such supervision as is necessary to ensure
(a) the day to day control of the quality of the concrete and
(c) the carrying out of all testing as specified herein and any further testing
which the Engineer's Representative may require, and
(e) the preparation of reports and the keeping of such records as the
Engineer's Representative may require.
3.12 FINISHING OF CONCRETE
All concrete surfaces (except top faces of culvert decks) not requiring
shuttering shall be trowelled to a smooth dense surface with the minimum of
cement and fine particles being brought to the surface and shall be free from
irregularities. Top faces of culvert decks shall be carefully screeded and
tamped to the required shape and to a dense surface with the minimum
amount of cement and fine particles being brought to the surface and should
be free from irregularities greater than 3 mm in height or depth.
3.13.1 General
Formwork shall in every respect be adapted to the structure and the required
surface finish of the concrete. It shall include all temporary moulds for
forming the concrete to the required shape and finish and for the support of
such moulds. It shall be fixed in perfect alignment and securely ledged and
braced so as to be able to withstand, without displacement deflection or
movement of any kind, the weight of the construction and the movement of
persons materials and plant. Joints shall be close enough to prevent the
leakage of liquid and fine materials from the concrete.
The Engineer's Representative may at any time require the prior submission
for approval of the Contractor's proposals for design and construction of
formwork including supports. The formwork shall be constructed so as to
permit its removal without damage to the concrete.
Internal spacing blocks and construction ties shall be avoided as far as, in
the Engineer's Representative opinion, possible and practicable. Where it is
intended that the spacing blocks or construction ties shall be removed
whether before or after the concrete has set, the making good of the
concrete shall be subject to the Engineer's Representative's approval. The
removal of the blocks or ties must not jeopardise the stability of the
construction. If, with the approval of the Engineer's Representative, the
spacing blocks and construction ties are allowed to remain in the concrete
then they shall be of such material and of such quality that they do not
prejudice the strength of the work. Concrete spacing blocks shall be made of
concrete at least equal in quality to the main concrete. Metal ties shall be
positioned such that they do not come into contact with any of the
reinforcement or fittings and no part of the tie shall be permanently
embedded in the concrete nearer than 5 cm to the exterior surface of the
concrete.
Where timber is used for the soffits of slabs, the boards shall be placed and
laid perfectly true with close joints to prevent the percolation of liquid or fines
from the concrete. Tongue and groove planks shall be used if specified. All
requisite bearer and struts shall be adjusted in position and placed where
necessary on bearers as specified in the case of beam forms.
All concrete faces shall be left as struck with a fair face, true to line finish.
After careful inspection, all superfluous fines and similar projections shall be
carefully removed. No render or other applied finish shall be used to obtain a
fair face to the concrete. All concrete faces to be exposed in the finished
works shall be adequately protected against damage and surface staining
during the execution of the Works.
All formwork and reinforcement shall be clean and free from standing water
immediately before placing concrete.
The Contractor shall in all cases request the approval of the formwork by the
Engineer's Representative in sufficient time to allow an inspection to be
made and shall not commence concreting until such approval is obtained.
The period between the Contractor's request for approval and his intention
to commence concreting shall be not less than one clear normal working day
and the Engineer's Representative may require a longer period if, in his
opinion, the formwork is of such complexity as to require it.
Such approval shall not absolve the Contractor of his responsibilities under
the Contract.
All formworks shall be struck without jarring the concrete or subjecting the
same to sudden shock.
Before striking any formwork, the Contractor shall satisfy himself that the
concrete is sufficiently hardened to bear its own load and any other loads
that may be placed on it.
Subject to the above and the concrete test cube results, the minimum
periods for the removal of formwork generally are as follows:
(These times may be reduced only with the written approval of the Engineer)
No supports for the shuttering may be left in the finished concrete without
the written permission of the Engineer.
All concrete placed below ground level shall have a minimum protection to
its outside faces with a bituminous membrane as per Clause 9.2.1.2 of this
Specification.
The use of concrete delivered to the Site in a plastic condition and ready for
placing in its final position shall be permitted subject to the following
conditions:-
(a) The constituent materials and the concrete mix shall comply with the
requirements of this Specification.
(b) The concrete shall be produced in accordance with the standards laid
down in the current edition of the "Authorisation Scheme for Ready
Mixed Concrete", published by the British Ready Mixed Concrete
Association (B.R.M.C.A.), except that
(i) Para. 11.1 (i) of the above publication shall be replaced by item (d)
below.
(ii) Water shall be added to the mix under the control of the central
batching plant.
(iii) Dry batching with water added on site will not be permitted.
(d) The concrete shall be placed in its final position and left undisturbed
within 1-1/2 hours maximum of the time when the cement first comes
into contact with wetted aggregates, ie. the time when hydration of the
cement commences. If the temperature is less than 4°C or if the
temperature is above 21°C, this period shall be reduced to one hour.
(e) When truck mixed concrete is used, water shall be added under the
supervision, either at the Site or at the central batching plant as
agreed by the Engineer but in no circumstances shall water be
added in transit.
(f) Unless otherwise agreed by the Engineer, truck mixer units and their
mixing and discharge performance shall comply with the requirements
of BS 4251. Mixing shall continue for the number and rate of
revolutions recommended in accordance with Item 9 in appendix B of
BS 4251 or, in the absence of the manufacturer’s instructions, mixing
shall continue for not less than 100 revolutions at a rate of not less
than 7 revolutions per minute.
(g) The concrete supplier is required to certify that the C1 content in the
mix being delivered I within the limits specified in Clause 4/15.5. The
C1 and SO3 content shall be checked at frequent intervals.
3.14.2 Documentation
The Engineer shall receive copies of the delivery tickets for each batch of
concrete, and have access to a site record book maintained by the
Contractor in which the following information is recorded for each batch of
concrete delivered:-
3.15.1 General
Mild steel where specified or called for shall be either deformed or plain bars
complying with ASTM A615 structural grade or BS 4449 or any equivalent
National Standard as directed and approved by the Engineer.
Tying wire shall be No.16 gauge soft annealed iron wire or No. 18 gauge
stainless steel wire or the equivalent AASHTO specification for tying wire.
Welded wire fabric shall be used as reinforcement for concrete where shown
on the Drawings and as directed. Welded wire fabric shall conform to the
requirements of AASHTO M55 or to BS 4483.
Steel reinforcing shall be stored on timber packing clear of the ground. The
steel bars shall be free from sharp deformations, rolled-in silvers, deep
recesses or surface faults/blemishes which could result in inefficient or
inadequate coating. When fixed in the work and immediately prior to
concreting, steel reinforcing shall be entirely free from loose mill scale, loose
rust, oil, grease, paint, mould oil, and all other deleterious and extraneous
material. All hooks, bends, etc., unless otherwise shown on the Drawings
shall be to BS 4466.
Before ordering reinforcing steel, the Contractor shall prepare bar bending
schedules at his own cost and submit them to the Engineer for his approval.
Bar schedules shall show the weight of each bar, the total weight of each bar
size and the total weight of bars, and bending diagrams for bars in
accordance with BS EN ISO 4066. The length of each bar shall be
calculated in accordance with BS EN ISO 4066 except that the minimum
internal bending radius shall be four times the bar diameter.
The Contractor shall also provide and submit to the Engineer for approval
any working drawings additional to the Contract Drawings which may be
found necessary for the production of bar bending schedules or for the
completion of the Works.
Links, hoops, stirrups are generally to be bent round pins of the same
diameter as the bars they are to embrace. Where however, such bars are
less in diameter than twice the diameter of the link, the radius of the bend
shall be equal to the diameter of the link.
The number, size, form and position of all reinforcement shall, unless
otherwise directed or authorized by the Engineer, be strictly in accordance
with the Drawings. Nothing shall be allowed to interfere with the disposition
of the reinforcing bars. Bars generally must be of the required lengths.
Welding of the bars will not be permitted. Lapping of the bars other than the
lap splices shown on the Drawings should be avoided. The Engineer may
approve certain lappings under special conditions. All lappings should
comply strictly with the AASHTO specifications, namely Article 1.5.6. Clause
"c".
The steel reinforcement shall be firmly held in position by wire ties and
concrete blocks or other approved spacers designed to maintain the correct
clear cover of concrete over steel reinforcement. They shall be as small as
possible consistent with their purpose, and of a shape acceptable to the
Engineer. Minimum cover to reinforcement shall be 50 mm unless otherwise
detailed. The position of spacers and their method of use shall be approved
by the Engineer. The steel reinforcement shall be so connected as to form a
rigid cage.
All intersecting bars shall be bound together with No.16 gauge soft iron wire
with the ends of the wire turned into the main body of the concrete.
The Contractor shall in all cases request the approval of the Steelwork by
the Engineer's Representative in sufficient time to allow an inspection to be
made and shall not commence concreting until such approval is obtained.
The period between the Contractor's request for approval and his intention to
commence concreting shall not be less than one clear normal working day
and the Engineer's Representative may require a longer period if, in his
opinion, the reinforcement is of such complexity as to require it.
Such approval shall not absolve the Contractor of his responsibilities under
the Contract.
Precast concrete kerbs and edgings shall be hydraulically pressed and they
and precast concrete quadrants shall comply with the requirements of BS
EN 1339:2003 and to the dimensions and shapes shown on the Drawings
and/or as directed by the Engineer. They shall be Class B concrete with
sulphate resisting cement as indicated in Clause 3.2.7 of this Specification.
They shall be uniform in colour free from cracks, flaws or other defects with
well defined arises.
Joints between kerbstones shall be not less than 3 mm nor greater than 5
mm in width and shall be uniform from top to bottom. Joints shall be left
open.
Where precast kerbs of straight section are laid to form radii, joints should be
filled with non-shrinkage mortar, and expansion joints (using flexel or similar
joint filler) shall be provided at 3 m centres. For radii of 10 m or less
quadrants shall be used. Kerbs of a reduced size shall only be used for this
condition where approved by the Engineer.
All kerbstones shall be painted alternately black and white. The paint shall
be an approved concrete paint giving a nominal thickness 100 microns in
two applied coats.
In-Situ concrete edge strips shall be to the cross section shown on the
drawings and the class of concrete made with sulphate resisting cement
indicated thereon in accordance with Clause 3.2 of this Specification.
The edge strip shall be formed in as long lengths as possible and the form
work shall be set on the top surface of the sub-base, set to produce the line
and level in accordance with the requirements of this Specification. Care
must be taken to ensure that the top surface is carefully finished to achieve
these requirements and to provide the control of the wearing course.
Expansion joints will be provided with an approved joint filler at maximum 3
m centres as shown on the drawing and/or as directed by the Engineer. The
kerb shall be protected against covering or splashing by bitumen or cement.
Group A : Rigid pipes which do not depend on lateral support from the
bedding and trench sides for structural strength.
Concrete
Clayware
Asbestos Cement
Pitch Fibre
Grey Iron
Unless pipes are detailed with rigid joints or are specified differently all
pipelines shall be jointed with approved mechanical, flexible joints with
elastomeric joint rings. The whole joint assembly shall be compatible with
the pipe construction and with the specified performance of the completed
pipeline.
Angular Deflection
Pipe Material Pipe Diameter (mm)
(Degrees)
All materials up to 200 3
(except concrete Over 200 to 500 1.75
and clay pipes) Over 500 to 1350 1
Over 1350 0.5
Shear: Pipe materials which are listed in structural Group A shall be loaded
to 10 times DN (mm) in newtons in accordance with BS EN-512. Pipe
materials which are listed in structural Group B shall be subjected to a load
of 17.5 N/mm of pipe diameter in accordance with ASTM D-4161.
If the approved standard for a pipe material does not include a shear test for
the jointing system, this test shall be carried out in accordance with test
procedure of another appropriate pipe material standard.
Flanged pipes shall incorporate an annular gasket at the Joints and these
gaskets shall be manufactured to BS EN 1514 from ethylene propylene
rubber (EPDM) 3.0 mm thick and shall be dimensioned to full face of the
pipe flange and to suit the flange drillings. The hardness of the rubber
(IRHD) shall be to the manufacturer's recommendations to suit the pipe
material but for pipe materials in Group A shall be in the range 66 to 75.
All bolts, nuts and washers shall be of stainless steel grade 320S17 to BS
EN 10088-1 or DIN 17440:1.4571 and shall remain unpainted. PTFE
washers shall be fitted beneath stainless steel washers for both bolthead
and nut.
All elastomeric joint sealing rings and gaskets for flanged pipes shall be
supplied and transported in light proof packaging so as to prevent damage
due to ultra violet radiation. The Contractor shall provide suitable storage
facilities to prevent ultra violet exposure until use.
Asbestos cement pipes, joints and fittings shall be manufactured and tested
to ISO 160 or BS EN512 for all pipelines. Sulphate resisting cement with a
medium to low C3A content shall be used in the manufacture of asbestos
cement pipes, joints and fittings.
Asbestos cement pressure and gravity pipes and joints shall be Class 18
unless otherwise specified.
For gravity pipes the crushing strength shall be carried out on one percent of
the total number of pipes and joints. For pressure pipes the bursting test
shall be carried out on one percent of the number of pipes and fittings.
A jointing ring shall be provided at each end of the pipe this being rubber or
neoprene or a compound of both. Internal test pressure and the prevention
of infiltration of groundwater are to be the major design criteria of the joints.
The Engineer shall be given details of vacuum-type tests on the joints.
All bends and fittings required along the route of the pressure pipelines other
than those bends obtained by deflection of the pipe joints shall be of GRP
material. Bends and fittings shall be obtained from the same supplier as the
asbestos cement pipes and shall be compatible with the pipes and jointing
system used.
For identification purposes, all asbestos cement pipes and fittings laid for
drainage application shall be externally coated with a black bituminous paint.
Potable water pipelines in asbestos cement are uncoated.
The required limits for the above tests shall be as outlined in the standard or
advised by the Engineer.
uPVC pipes for gravity pipelines shall have a standard dimension ratio, D:t
(diameter to thickness), of between 35 and 45.
The Contractor shall advise the manufacturer of the climatic and transporting
conditions at the site of the works and shall seek his advice on the storage of
uPVC materials on site. Subject to the Engineer's approval this advice shall
be followed at all times.
Any pipes exhibiting cracks, notches or deep scratches or other damage will
be condemned and shall not be incorporated into the permanent work under
any circumstances.
Pipes for slotted land drains/slotted carrier drains shall be uPVC pipes. Prior
to perforation, the basic pipe shall be manufactured to BS 4660 and BS
5481, kite marked, and shall comply with the requirements of Clause 4.1.4 of
this specification relating to uPVC pipes for non-pressure application. The
slots shall be designed to give at least the minimum infiltration rates laid
down in BS 5911: Part 114. The final configuration of the slots shall be
subject to approval by the Engineer.
The slots shall be cleanly machine cut and be not less than 3 mm or greater
than 4 mm in width. The slots shall be in one 180° segment of the barrel in
one or more longitudinal rows, the slots in each row being spaced
equidistantly. Where more than one row of perforations are provided the
slots shall be staggered. No slots shall be nearer to the ends of the barrel
than the spacing between two adjacent slots. The spacing between slots in
any row may vary up to ± 20 mm.
4.1.6.1 General
GRP pipe and fittings shall be supplied with a rated pressure of 6 bar for
gravity pipes and shall be suitable for service temperatures up to 50oC.
1. The resin-rich inner liner shall have a minimum thickness of 1.5 mm,
consisting of ‘C’ glass veil backed with chopped strand
‘ECR/ADVANTEX’ glass all impregnated with vinylester resin.
sand content of the pipe material shall not exceed 50% in accordance with
the test type submitted for approval.
The resin shall be cured to reach a hardness not less than 90% of the resin
manufacturer's recommended hardness using a prescribed test.
The ellipticity of any pipe when measured resting freely on the ground shall
not be more than 2% of the mean diameter at any point. No pipe known to
have undergone a deflection greater than 7% shall be incorporated into the
Works.
Stiffness shall be minimum 5000 N/m2 for all pipes but for pipes to be used
in pumping stations and valve chambers the stiffness shall be minimum
10,000 N/m2 and pipes for use in microtunnelling or similar jacking
operations the stiffness shall be minimum 50,000 N/m2 unless enclosed in
concrete.
up to 700 100
700 to 1,000 120
1,000 to 1,600 160
1,600 to 2,400 250
2,400 to 4,000 300
Where GRP laminate is cut, exposed ends shall be sealed with a suitable
resin and approved prior to incorporation into the Works. Where such cutting
and sealing takes place at site the resins used and the methods of storage,
mixing, application and curing shall be strictly to the manufacturer's
recommendation. Before any such work takes place the manufacturer's
representative shall visit the site to demonstrate and give clear procedural
advice to the Contractor in the presence of the Engineer.
GRP pipe and fittings shall be smooth and both the internal and external
surfaces shall be clean and free from delaminations, cracks, bubbles,
pinholes, pits, blisters, foreign inclusions and resin-starved areas that due to
their nature, degree or extent detrimentally affect the strength and
serviceability of the pipe.
Unless authorized by the Engineer, repair will not be permitted on any pipes
with defects as listed below and such pipes shall not be incorporated into the
works:-
(4) Delaminations.
(7) More than 25% of the external area with protrusions of any sort.
(9) Pitting to more than 5% of the internal or 10% of the external surface
area and individual pits more than 1 mm diameter or 0.5 mm in depth.
(10) Wrinkles over than 3% of the surface area and individual wrinkles more
than 2 mm deep.
4.1.6.2 GRP Pipes and Fittings for Pumping Stations and Valve Chambers
The design of GRP pipe and fittings for pumping stations and valve
chambers shall incorporate all the requirements of these specifications
except for the following over-riding or supplemental stipulations.
GRP pipe and fittings inside pumping stations and chambers shall be
designed for use above ground with no thrust blocks and shall have
sufficient axial strength to resist end thrust, temperature and bending
stresses.
GRP pipe and fittings shall have a minimum pipe stiffness of 10,000
N/m2 and a minimum wall thickness of 10 mm.
The design working pressure for pipes and fittings shall be 10 bar and the
service temperature shall be 50°C. A minimum surge allowance of 40%
above the working pressure shall be included in the design of pipes and
fittings. Copies of the design calculations shall be submitted to the Engineer
for approval. The basis of design shall be checked by conducting 'type' tests
on representative sample(s) of manufactured materials, in accordance with
the requirements of BS EN 14364 or ASTM D-2992.
GRP pipe and fittings for pumping station and valve chamber pipework shall
have a suitably designed restrained joint capable of withstanding the design
operating pressure with no leaks and without the use of thrust blocks.
The acceptable jointing system shall be GRP flanges. GRP flanges shall be
machine filament wound using 'E' or 'ECR/ADVANTEX' glass fibre
reinforcements and vinylester or epoxy resin. Hand layed up flanges shall
not be permitted. Flanges shall be drilled to BS EN 1092 (metric units) type
PN 10.
The following tests shall be carried out on manufactured GRP pipe and
fittings at the intervals specified. Test methods shall be in accordance with
BS EN 14364 or ASTM equivalent. Witnessing of factory testing by the
Engineer's Representative will be required prior to delivery of the material.
Copies of the Manufacturer's test reports shall be submitted to the Engineer
after each consignment of pipe or fittings delivered to the site.
All GRP standard pipe and pipe used for fitting fabrication shall be factory
pressure tested to 20 bar for pressure pipes and 12 bar for non-pressure
pipes.
The following tests shall be conducted on all GRP pipe and fittings:
- Visual inspection
4.1.6.4 Installation
4.1.7.1 General
Polyethylene (PE) pipe, either high density polyethylene (HDPE) or high
performance polyethylene (HPPE) pipe shall be manufactured to conform to
the requirements of CP 312 Part 1 and 3, and BS 6437 or DIN 8075. Where
pipes are used for renovation work, pipes shall be of short lengths or short
length conforming to the requirements of the method selected and the
available working space in the manholes or drive shafts. Longer lengths may
be used for new installation where conventional open trench methods of
construction are employed.
The base3 polymer shall be polyethylene with a derived density greater than
930 kg/m when determined in accordance with the method required by BS
3412. The base polymer shall be blended with additives that are necessary for
the manufacture, storage and use of PE pipes for sewer lines, including
antioxidants, carbon black and UV stabilizers.
The material in pipe form shall have a thermal stability of at least 15 minutes
when tested in accordance with the isothermal method for differential
thermal analysis.
The ovality of pipes up to and including nominal size 250 mm shall not
exceed 0.02 the nominal size (mm). The ovality of pipes greater than
nominal size 250 mm shall not exceed 0.035 the nominal size (mm).
The ends of the pipe shall be cut, cleanly and squarely, to within the
following tolerances:
180 - 225 4 mm
250 - 315 5 mm
The calculated 24 hour and 50 year creep module shall be not less than the
values given below when tested in accordance with either the pipe ring in
tension or the three point bend method.
The jointing system for polyethylene pipes and fittings shall be in accordance
with the pipe manufacturer’s recommendations subject to approval by the
Engineer.
4.2.1 General
All pipes shall be handled and stored in compliance with the manufacturer's
recommendations subject to the following limitations :-
Pipes shall be transported, handled and stored with such packing and in
such a manner that damage does not occur and that contact is avoided with
sharp edges which may cause damage. During transit, pipes and fittings
shall be well secured and adequately supported along their length.
Pliable straps, slings or rope shall be used to lift pipes, and steel cables or
chains will not be used without written permission.
All pipes and fittings shall be thoroughly inspected on arrival at site after off-
loading and prior to installation for detection of any damages.
Suitably smooth and level storage areas shall be provided at or near the site
and made secure to prevent unauthorised access.
Up to 500 5
500 to 700 3
The end pipes in each row shall be strapped to the battens. Pipes shall not
rest on their sockets.
Pipes and fittings of plastic materials smaller than 300 mm diameter may be
handled manually and those equal or larger than 300 mm diameter shall be
lifted using a single fabric or large diameter rope sling. There shall be
enough slack in the sling to keep the hook at least 600 mm over the pipe.
Use of wire rope chains and forklifts shall not be permitted.
Where shaped battens are used, they shall be at least 100 mm wide and not
more than 1.5 meters apart. The end pipes in each row shall be strapped to
the battens. The pipe shall not be stacked any higher than five (5) layers.
The Contractor shall ensure that thermoplastic pipes do not come into
contact with bituminous or other hydrocarbon based materials.
Notes:
4) For uPVC pipes only rounded aggregates will be permitted but for all
other pipe materials crushed aggregates may also be used.
Stone for land drains shall be nominal single size 20 mm in accordance with
the following table or the manufacturer’s recommendations if different, and
placed as shown on the drawings. The stone shall also comply with the
general requirements of Clause 4.3.
Approximately one quarter of the material shall then be replaced into the
cylinder and compacted by tamping vigorously with a 40 mm diameter metal
rammer weighing about 1 kg until no further compaction can be obtained.
This operation shall then be repeated for each of the remaining quarters,
tamping the final surface as level as possible.
The distance from the top of the cylinder to the surface of final layer shall
then be measured and this value, divided by the height of the cylinder, shall
be taken as the Compaction Fraction.
4.4.1 General
Nominal trench widths for single pipelines shall be defined as 1.50 times the
diameter plus 500 mm, subject to a minimum trench width of 750 mm.
Nominal trench widths for two or more pipes in the same trench (laid in
parallel with similar invert levels) shall be defined as the sum of the internal
diameters plus 450 mm between the pipes, plus 750 mm.
Any excavation from the bottom of the trench to 300 mm above the level of
the crown of the pipe which exceeds the nominal widths defined above shall
be filled with concrete or the specified bedding materials as directed on site.
- Wide trenches shall be constructed to not less than the defined widths
for those categories of Group B flexible pipelines in granular bedding
defined below.
- If the value of E’s determined from the results of such tests is greater
than 2.5 MN/m2 then trench width is not critical. If less than 2.5 MN/m2
then trench widths shall be constructed to the widths defined in the
following table unless alternative means of increasing the passive
resistance of the trench sides are detailed or are proposed in method
statements where economic or environmental restrictions make wide
trenches undesirable.
Pipes and fittings shall be laid and jointed in accordance with all relevant
recommendations of the manufacturer. Any variations between the
manufacturer’s recommendations and this specification shall be highlighted
in the Contractor’s Method Statements and a ruling will be given with the
Engineer’s agreement.
Pipes and fittings shall be checked for soundness and be thoroughly cleaned
out immediately prior to laying and jointing.
The setting of the pipeline to the required levels and alignment shall be
carried out by approved procedure such as boning between sight rails or the
use of laser systems. Sight rails, if used, shall be at a suitable height
vertically above the line of pipes or immediately adjacent thereto, and there
shall, at no time, be less than three sight rails in position on each length of
pipelines under construction to any one gradient. Large diameter pipes,
1000 mm diameter or greater, shall be individually set to level and line by
instrument.
For pipelines laid in trenches and headings the permissible tolerances in line
and level unless otherwise specified shall be ± 3 mm in level and ± 12 mm
from centreline between manholes or access points. Also where a gravity
pipeline or sewer is shown as a straight line between manholes it will not be
accepted as having passed the final test unless a full circular light can be
sighted through the bore of the pipe for the length concerned.
For pipeline jointing systems incorporating flexible jointing rings pipes shall
be laid with a gap between the end of the spigot and the base of the socket,
or between spigots. This gap shall be not less than 6 mm or greater than
one third of the straight draw test dimension specified for the pipe joint or as
recommended by the pipe manufacturer, and it shall be achieved by
approved means, such as marking the outside of the pipe or using
removable metal or hardwood feelers.
The annular space between the pipe and the socket at a flexible joint shall
be sealed with an approved joint sealant to prevent the ingress of loose
material or concrete. Sealing shall be done on completion of a satisfactory
preliminary testing prior to concreting or backfilling, but not prior to the test.
For uPVC pipes solvent welded joints with parallel sockets shall not be
permitted unless made in the manufacturer's workshop.
Where flexible jointed pipes are laid to curves the angular displacement at
any joint as laid shall not exceed three quarters of the maximum
recommended by the manufacturer.
Flanged pipes shall incorporate an annular gasket at the joints. The gaskets
shall cover the full face of the flange and shall have holes cut in them
corresponding to the bolt holes in the flanges. However, in pipes fixed
vertically a plain ring covering the flange between the bolt circle and the bore
of the pipe may be used. Gaskets shall be manufactured as specified in
Clause 4.1.2.2.
When flanged joints are to be made the Contractor shall follow
manufacturer’s guidelines for the tightening of nuts and bolts.
The Contractor shall make sure that all joints are made strictly in accordance
with the manufacturer's instructions.
Where pipes are to be laid with a concrete cradle or surround they shall be
supported initially above the trench bottom on concrete setting blocks. The
blocks shall either be laid accurately to level and covered with damp-proof
sheeting beneath the pipe barrel or shall be provided with two hardwood
wedges each to an approved pattern to enable the pipe level to be adjusted.
The blocks and wedges shall be of sufficient size and strength to prevent
settlement of the pipes during laying and at least two concrete blocks shall
be provided for each pipe.
The length of pipeline laid in any one operation before concreting the
pipeline shall be that which in the opinion of the Engineer permits accurate
laying of the pipeline and concreting in an efficient and proper manner.
Concrete cradles to pipes of all diameters and surrounds to pipes of one etre
diameter or less shall be poured in a single lift. Concrete surrounds to pipes
over one metre diameter shall normally be poured in two lifts, with a
horizontal joint not more than 100 mm below the crown of the pipe.
Concrete cradles and surrounds shall be interrupted over their full cross
sectional area at each pipe joint, by shaped expansion joint filler. The
thickness of filler shall be 18 mm for pipe diameter less than 450, 36 mm for
pipe diameter 450 to 1200 and 54 mm for pipe diameters greater than 1200.
In spigot and socket pipelines the joints in the bed shall be at the face of
each socket.
In all flexible joints the annulus of the pipe socket shall be sealed with an
approved sealant to prevent the concrete from entering the pipe joint.
150 mm (minimum 100 mm under sockets) for pipes not exceeding 300 mm
internal diameter.
The time interval between placing bedding material on the trench formation
and commencing pipelaying shall be as short as is practicable.
The bedding material shall extend to the full width of the trench and shall be
compacted in layers not exceeding 200 mm. The bedding material shall be
carefully compacted using a plate vibrator or other approved equivalent
mechanical method. Sufficient passes of a plate vibrator or other approved
mechanical method are required to achieve positive deflection of flexible
pipes to ensure that final deflections are within the specified limits. Hand
tamping or punning will only be permitted where insufficient space is
available to allow the use of mechanical plant.
Where the formation of the trench is of silt or soft clay and is below the
natural water table a 75 mm blinding layer of sand shall be substituted for
the specified bedding material directly above formation and carefully
compacted if directed on site.
material shall be introduced at both sides of the pipe and compacted until it
has been brought up to at least 150 mm above the crown of the pipe.
The methods of selecting excavated materials may include sieving either in
bulk or above the trench.
The granular material shall be carefully laid and compacted at the sides of
pipes according to one of the following methods for alternative types of
compaction plant as agreed with or directed by the Engineer.
The use of power rammers will not be permitted over any pipe until the depth
of fill above the crown of the pipe is at least 300 mm.
The backfill requirements for trenches around structures shall be the same
as that for pipeline except that compaction by mechanical means shall
commence from the formation level (to the specified densities).
4.4.8.1 General
For all pipes the horizontal and vertical deflections shall be measured at
each end at points 100 mm and 1.5 m away from the joint and at 3.0 m
intervals thereafter, or as directed by the Engineer. For pipe lengths of less
than 3.0 m these deflections shall be measured at each end at a point 100
mm away from the joint and at the mid-point.
For pipes of 600 mm diameter and greater the device shall be in the form of
a telescopic spring loaded rod graduated for each diameter to show
percentage deflections.
The Contractor shall tabulate the results of the measurements and copies
shall be submitted to the Engineer immediately after each set of
measurements has been taken.
1. After the pipe surround material has been placed and compacted to 300
mm above the pipe crown.
Pipes exhibiting any negative deflection in the vertical in (1) above and/or
pipes exhibiting a deflection in excess of 2% in (2) above or 4% in (3) above
shall be exposed and the surround replaced and recompacted. Should any
deflection exceed 7% that pipe shall be replaced. Any pipe removed for this
reason shall be taken from site and not incorporated in the permanent
works.
All pipes exposed for recompaction and pipes replaced for any reason shall
subsequently be subject to the three deflection checks listed above.
Deflection checks shall also be carried out on adjacent pipes for 50 m either
side of the recompacted or removed pipes.
If any of these tests indicate that the deflection may exceed the permitted
values the pipe or pipes shall be replaced. Any pipe removed for this reason
shall be taken from site and not incorporated in the permanent works.
All pipes replaced for any reason shall subsequently be subject to deflection
checks as described above. Deflection checks shall also be carried out on
adjacent pipes for 20 m either side of the removed pipes.
Where pipes are laid on a granular bed or with a granular backfill, a stank,
i.e. an impermeable barrier, shall be provided across the full width of the
trench and for the complete depth of the bedding at intervals not exceeding
50 m, and generally mid-way between manholes or chambers.
Either a 300 mm long plug of fine grained clayey soil or a 300 mm long plug
of a mixture of sand and bitumen consolidated in an approved manner.
Or a layer of thick polyethylene cut to fit around the pipe across the full width
of the trench and laid on the granular bedding material at its natural repose
angle.
All methods must form an impermeable barrier. Bitumen shall not be used
for thermoplastic pipes.
Where details are not shown on the drawings the Contractor shall prepare
proposals for thrust and anchor blocks including calculations and submit
them to the Engineer's Representative for approval. Such approval shall not
relieve the Contractor of his responsibility for the adequacy of his proposals.
Special details shall be shown on the drawings or instructed at site where
environmental or ground conditions dictate.
Distance between
Pipe Diameter Maximum distance
first and second joint(mm)
(mm) to first joint (mm)
Min. Max.
Up to 300 150 450 2.5 * dia.
300 to 1000 300 1.5 * dia. 2.5 * dia.
Above 1000 450 1.5 * dia. 2.5 * dia.
These joints will be required at surrounds and anchor blocks unless directed
otherwise on site.
Between the structure and the first joint any disturbed ground below the pipe
will be removed and replaced with Class B concrete in the form of a cradle,
all to the direction of the Engineer. The cradle shall not extend beyond the
first joint.
Beyond the first flexible joint within the excavated working space of the
structure the concrete fill shall be brought up 300 mm below the pipe invert
only. Specified bedding materials will then be used.
Within the excavated working space for the structure disturbed ground below
the pipe will be removed and replaced with Class B concrete to within 300
mm of the underside of the pipe. Specified bedding materials will then be
used to support the pipe.
The width of the concrete backfill shall not be less than the nominal trench
widths except for any permanent shuttering against temporary trench
supports to facilitate removal of such trench supports after concreting.
The neoprene will normally extend through the width of a wall to a dry
chamber or structure but will be limited to 150 mm or 100 mm is exposed to
liquid (groundwater or liquid inside the structure) a sealant groove shall be
formed if detailed and filled with an appropriate, approved, joint sealant.
Care shall be taken to ensure that the rubber strip is not displaced during
concreting.
4.4.12.1 Pipelines
All buried valves, couplings, flange adaptors, and other metal components
shall be encased to guard against corrosion. Other pipe joints, valves and
similar items on both buried and exposed pipelines shall be encased where
specified or shown on the drawings.
The item to be encased shall first be cleaned and its original surface
treatment made good. The surface shall be dry before encasing is carried
out, which shall not be done before the pipeline has been tested.
Before wrapping with tape the item to be encased shall be enclosed with an
approved mastic or inert putty-like filler which shall be moulded by hand so
as to provide a smooth surface for the tape. The tape shall be tightly spirally
wrapped with 25 mm overlaps so as to enclose the whole of the item and a
minimum of 150 mm of pipe length on each side. The enclosure shall be
firmly pressed out to prevent air being trapped under the wrapping.
In addition at all air valve chambers, the Contractor shall erect indicator
signs on posts, to an approved design, at locations described to him by the
Engineer.
All slotted pipes and pipes laid beneath the permanent groundwater level the
granular bedding material shall be laid on and enclosed within a geotextile
filter fabric.
Filter fabric used for subsurface drainage works shall consist of long-chain
synthetic polymer fibers composed of at least 85 percent by mass
polyoiefins, polyesters, or polyamids. They shall be formed into a network
such that the filaments or yarns retain dimensional stability relative to each
other, including selvedges.
Min.
Property Test Method
Requirements
Grab Strength (N) ASTM D 4632 800
Puncture Strength (N) ASTM D 4833 355
Burst Strength (Kpa) ASTM D 3786 2000
Trapezoid Tear (N) ASTM D 4533 220
Permeability (M/S) ASTM D 4491 10-4
Apparent Opening Size (Mm) ASTM D 4751 0.6
Ultraviolet Degradation
ASTM D 4355 70 @ 150 H
(Percent Retained Strength)
Where filter fabric is used to enclose granular or stone pipe surrounds, the
fabric will be placed on the prepared trench formation and carefully
supported during pipe laying operations. When the pipe has been laid
complete with surround to the correct level the filter fabric shall be closed
over the top of the surround by forming a 'lap' of minimum width 500 mm. All
membrane joints shall be overlapped a minimum of 500 mm.
Care shall be taken not to puncture or damage the membrane in any way
during installation or during backfilling of the trench. Fabric damaged or
displaced before or during installation or during placement of overlaying
aggregate material shall be replaced or repaired to the satisfaction of the
Engineer at the Contractor's expense.
Service protection tapes shall be installed above all sewage, drainage and
irrigation pipelines and pressure mains constructed or exposed under this
contract excluding individual service connections.
For pipelines with the top of the pipe barrel more than 900 mm below
finished surface level the tape shall be placed over the centreline of the
pipeline at 600 mm below finished surface level during backfilling and
compaction operations. For pipelines with less than 900 mm cover to the
top of the pipe barrel the tape shall be placed over the centreline of the pipe
at 300 mm above the top of the pipe barrel during backfilling, compaction
and reinstatement operations.
The tape shall be continuous over pipelines and at joints between tapes from
separate rolls the joint shall be lapped a minimum of one metre.
The tapes shall be flexible with a minimum width of 150 mm and thickness of
150 microns and shall be subject to the Engineer's approval.
Site tests to confirm detectability of the warning tapes after installation and
backfill shall be performed when ordered by the Engineer.
Text in Arabic and English indicating the protected services lying below the
tape shall be permanent ink bonded to resist prolonged chemical attack by
corrosive acids and alkalis with the message repeated at a maximum
interval of two metres. Tapes shall be colour coded as follows, with black
text as indicated. The sign and styles of the text shall be approved by the
Engineer.
Sewers : Yellow
Drains : Yellow
(2) The layout and design of the pipework shall be such as to facilitate its
erection and the dismantling of any section for maintenance of
associated plant by inclusion of approved mechanical coupling or
flange adaptors.
(4) Adequate supporting and anchoring arrangements for all pipes shall be
included which may take the form of straps, stays, tie bars or concrete
cradles. All pipe hangers and supports inside pumping stations and
valve chambers or other structures shall be of 320S17 stainless steel.
All fixing bolts shall be stainless steel grade 320S17.
(5) GRP pipes shall be provided with puddle flanges where they pass
through the walls of underground or water retaining structures.
(6) Small bore pipework for sump pumps, vents, etc., may be an approved
plastic material.
(7) All pipes connected to pressure vessels, pumps, etc., shall have
flanged connections.
(8) All pipes shall be checked for alignment and mating of flanges and
connections before secured. Pipes shall not be sprung into position.
4.6.1 General
The inverts shall conform accurately to the size of the adjoining pipes. Side
inverts shall be curved and main inverts (where direction changes) shall be
laid out in smooth curves of the longest possible radius which is tangential,
within the manhole, to the centerlines of adjoining pipelines all as indicated
on the drawings and instructed by the Engineer.
The ductile iron frames, grates and covers shall be to the Dubai Municipality
standard frame, grate and cover as indicated on the drawings and
hereinafter specified in Clause 4.7.
All benching and channel shall be formed with Class A concrete unless
shown otherwise in the drawing. 7 mm minimum GRP laminate shall be
applied to benching and channel.
Manhole walls shall be plain Class A concrete formed to the shape and
thickness shown on the drawings by the use of sound formwork material to
give a fair faced finish.
shown on the drawing and the external (buried) surfaces shall be protected
in accordance with Clause 9.2.1.2 (1) either with water-proof membrane with
protection board or with a brush-applied bituminous emulsion as indicated in
the drawing.
Pipes entering and leaving manholes, chambers and special structures shall
be laid soffit to soffit unless otherwise shown on the drawings. Details of
pipelines entering and leaving manholes, chambers, etc., shall be as
specified for pipes protruding from structures in accordance with
Clause 4.4.11.
Gullies shall comprise the gully grating and frame and the polypropylene
gully pot, all as shown on the drawing.
The gully pots shall be supplied with a fibre glass sand bucket with lifting
handle, as detailed in the drawing. The sand bucket shall have perforations
in its upper part and small holes 3 mm in diameter in its bottom part. The
total area of perforations shall not be less than 20,000 sq. mm and the
minimum diameter of each hole shall be 50 mm. The depth of the bucket
shall not be less than 750 mm.
The connecting pipe between the gully pot and the drain/manhole shall be
160 mm dia. uPVC.
The connection into the drain pipe shall be made by means of an oblique
junction which may be of uPVC.
4.6.3.1 General
The Contractor shall furnish all ductile iron frames, grates, and covers
conforming to the details shown on the drawings, and as specified in Clause
4.7 to RTA/DM Standards.
The Contractor shall submit for approval detailed shop and working drawings
of all castings before fabrication. Such drawings shall be obtained from the
supplier(s) he chooses to select from the approved list of RTA/DM (see
Clause 4.7.1).
If required by the Engineer, the Contractor shall obtain from the supplier/
manufacturer a guarantee that replacement component parts will be
available for a minimum period of 10 years from the issue date of the
Completion Certificate.
All covers, frames and grates shall be delivered to Dubai with a transit
protective packaging or wrapping. Any damage occuring to the approved
coating system shall be made good prior to installation.
One set of prising and lifting keys of approved design shall be supplied by
the Contractor with each twenty manhole covers and frames supplied.
All access covers and frames shall be of heavy duty construction complying
with BS EN124 and the requirements of the RTA/DM Standards (Clause
4.7). With the exception of those for sewerage manholes, access covers and
frames shall be sand tight with seatings designed to be non-rocking unless
detailed otherwise.
Both sides of covers and frames shall be protected with an approved epoxy
coating system appropriate to the Dubai environment (refer to Clause 19.4).
The coating system may be applied at the place of manufacture or in Dubai
under controlled application conditions approved by the Engineer.
Covers for sewerage manholes and chambers shall also be provided with a
reinforced plastic sealing plate. The design of cover, frame and sealing plate
shall be such that no load can be transferred from the cover to the sealing
plate.
(1) Sewerage
Where ventilated covers are detailed the total area of ventilation shall not be
less than 5 % of the minimum clear opening area and the covers shall be
provided with suitable protective sand traps which shall seat in the access
cover frame.
Table 4-9. Standards for Covers and Gratings for Storm/Land Drainage
PUMPING
REQUIREMENT IN OUT FLUSHED UPSTAND STN.
ROAD OF KERB KERB ACCESS
ROAD COVER
Double Double
Shape Semi- Semi- Square -
Circular Circular Rectangula
r
Size of clear 600 dia. 600 width weir dpt 600 x 750
opening dia. Nom.450 165 600 x 900
Standard BS EN BS EN BS EN BS EN BS EN124
124 124 124 124
Ventilation No No - - No
Construction Solid Solid - - Concrete
Infill
Sealing Plate Yes Yes - - -
Inscriptions Storm Storm Storm Storm Storm
Tightness Yes Yes - - -
Rocking No No No - No
Locking No No No - No
Interchangeability Yes Yes Yes Yes Yes
HOUSE PUMPING
REQUIREMENT MANHOLE CONNECTION STN.
CHAMBER ACCESS
COVER
IN ROAD OUT OF ROAD
Size of clear 600 x 600 600 x 600 600 x 600 600 x 750
opening 600 x 900
Ventilation No No No No
Construction Solid Solid Solid Concrete
Infill
Sealing Plate Yes Yes Yes -
Inscriptions Sewerage Sewerage -
Sewerage
1. ELKINGTON
2. PASSAVANT
3. STANTON
4. SELFOCK
5. GLYNWED BRICKHOUSE
5.1 MATERIALS
All concrete Bricks & Blocks shall conform to RTA/DM Local Order No.
44/1990.
They shall be free from cracks, uniform in size, true to shape, free from
deleterious matter, clean, hard, impervious with smooth faces in appearance
similar to normal Class B concrete and with well defined arises.
Bricks and blocks shall not be incorporated into the Works until they have
matured under suitable conditions for 28 days.
5.1.2 Bricks
Engineering bricks and special purpose bricks such as radial bricks, weir
bricks, copings and bull nosed bricks shall have an average compressive
strength of at least 69 N/mm2 and an average absorption not exceeding 4.5
percent by weight measured by a standard boiling or vacuum method.
Bricks for arches and circular work of 1.5 metres and less in diameter shall
be purpose made radial bricks.
Lime for cement-lime and lime-sand mortar shall be the hydrated type to the
approved standard.
5.2 CONSTRUCTION
5.2.1 General
During hot and dry weather bricks and blocks shall be wetted as necessary
and the tops of walls shall be wetted before a course is laid
All faces of brickwork or blockwork will be kept clean and no rubbing down of
exposed faces will be permitted.
Vertical faces of all bricks shall be well buttered before being laid and the
whole well grouted at each course.
All blocks shall be laid on even full beds of mortar; vertical faces of all blocks
shall be well buttered before being laid and the whole well grouted at each
course.
The overall dimensions of four blocks laid in mortar shall not exceed by more
than 25 mm the overall dimensions of the same blocks laid dry.
When concrete is to be faced with brickwork, header bricks shall be built into
every fourth course and at intervals of 2 bricks horizontally so as to project
1/2 brick into the concrete. Headers in successive courses shall be
staggered.
5.2.3 Blockwork
All blockwork shall be built level, plumb and true to line with all perpends in
line vertically. Blockwork shall be built in stretcher bond and alternate
courses shall be bonded in at all junctions. All blockwork shall be set in
gauged mortar as described to the lengths, heights and thicknesses shown
on the drawings. Fair and fair-faced work shall be kept perfectly clean and
no rubbing down of blockwork will be allowed. Blockwork to be plastered
shall have joints struck off flush and left rough.
Mortar for precast concrete units, brickwork and blockwork shall be gauged
in the proportions of one part of cement to three parts of sand. Lime shall
only be added if specifically ordered.
Ingredients shall be measured in proper boxes and shall be turned over and
thoroughly mixed on a wooden platform.
Cement lime (gauged) mortar shall consist of one part Portland Cement, one
part of lime and six parts of sand by volume (1:1:6). All materials shall be
accurately gauged using gauge boxes and shall be thoroughly mechanically
mixed. Mortar that has begun to set shall not be revived or re-used.
Cement mortar rendering shall consist of two or more coats; the undercoat
shall be 13 mm thickness and scored to form a key for the final coat which
shall be not less than 6 mm in thickness. The finished coat shall be worked
with proper metal floats, and the face left with an even and polished surface.
The mortar for the undercoat of the rendering shall be gauged in the propor-
tion of one part of cement to three parts of sand, and the finished coat shall
be in the proportion of one part of cement to two parts of sand.
The Contractor shall ensure during and after construction that the pipes
remain clean and free of all silt, mortar, debris and other obstructions, and if
required by the Engineer, the pipelines shall be cleaned out using approved
methods and equipment which do not damage the internal lining of the
pipes and manholes. When work is not in progress the open ends of the
pipeline shall be securely plugged with an approved watertight plug or
stopper to prevent the ingress of deleterious matter into pipelines.
After backfilling pipe trenches and completing chambers, hatch boxes, etc.,
and before the trench surfaces are reinstated, the interior of pipelines shall
be cleaned of silt and debris by approved methods for inspection by the
Engineer's Representative as follows:-
6.2.1 General
The Contractor shall make his own arrangements for the supply of water
used for testing and cleaning of pipelines which shall be obtained from a
source approved by the Engineer. All water required for testing and
cleaning shall be provided by the Contractor at his cost.
permission be given for the discharge of such fluids into the existing
sewerage system.
If lagoons for the storage of such fluids are permitted, they must be suitably
protected with fencing and attended by day and night to prevent access by
the general public and will not be sited adjacent to buildings. Approved
means of preventing the formation of mosquito larvae on the surface of the
lagoons will be employed.
For both gravity and pressure pipelines only testing of new, renovated, or
replaced sections of pipelines and fittings will be required under the
Contract, in accordance with this Specification, unless detailed otherwise.
Such testing will be carried out before making final connections to the
existing network. However where tees or other fittings are inserted into
existing pipelines and where lengths of pipeline are replaced no backfilling
will be allowed at the tees or fittings or at the joints between new and
existing pipework until the pipeline has been returned to service and a
visual inspection of all such fittings and joints made at the network
pressure.
Should any inspection be unsatisfactory or any test fail the Contractor shall
replace defective pipes, leaking joints or otherwise re-execute defective
work as instructed following which cleaning and testing will be repeated
until the Engineer's Representative certifies the pipeline to be satisfactory.
Preliminary and final air and water tests will not normally be applied to
pipelines greater than 600 mm (nom.) internal diameter and acceptance of
these pipelines will be dependent on satisfactory visual inspection of the
pipes and joints.
1. The Contractor shall plug all pipe outlets with suitable plugs, and brace
each plug securely where needed.
After backfilling the length of pipeline under test, it shall be given the
following final test:
1. All branches and open ends shall be closed with suitable stoppers,
secured with longitudinal braces before testing commences.
2. Water shall be filled from the lowest point and air allowed to escape. No
entrapped air shall remain in the pipeline while testing.
4. After that, the test pressure shall be maintained for 60 minutes and
water added shall be measured.
Where in the opinion of the Engineer's Representative the above test is not
sufficiently indicative of water tightness by reason of high ground water
levels the test will not be applied. Acceptance of the pipelines will then
The Engineer may require any length of pipe suspected of being damaged
to be retested by the water test at any time during the contract period.
Infiltration Test
All pressure pipelines of 675 mm or more internal diameter shall have each
joint individually tested by means of an approved joint testing apparatus.
Each test shall be restricted to pipes of one class. Pipelines shall be tested
in sections not exceeding 500 metres or between valve positions. In
addition the whole pipeline shall be tested upon completion. Particular care
must be taken to isolate air valves, etc., not to apply higher pressure than
specified at any point on the pipelines and to ensure that the pipelines are
adequately anchored before any test is carried out.
As soon as a length of pressure pipe has been laid and before backfilling,
when applicable and when ordered it shall be subjected to the following
preliminary test:
1. The Contractor shall plug all pipe outlets with suitable plugs, and brace
each plug securely where needed.
5. The test will not be satisfactory if the air pressure falls to less than 275
mm during a period of 5 minutes without further pumping of air.
Pressure pipelines shall be given the following final test using water after
they have been backfilled, cleaned and inspected:
1. All the joints of the pipeline shall be left open for the purpose of
inspection for leakage if any, where practicable or instructed by the
Engineer.
3. Water shall be filled slowly (to prevent possible water hammer) from the
lowest points and air allowed to escape through an air vent fixed for the
purpose at the highest points of the pipeline section under test. No
entrapped air shall remain in the pipeline while testing.
8. Pipeline shall be deemed to have passed the test if all the following
conditions are satisfied:
c. The loss of the pressure during the test period does not exceed
70KN per square metre.
This shall be carried out before any backfilling and before the application of
any external concrete protection has taken place. Any damages revealed
as a result of such tests shall be made good to the satisfaction of the
Engineer.
9.1 MATERIALS
9.1.1 Corrosive Environments
(1) The climatic conditions prevailing in the project area with particular
emphasis on temperature variations, high surface temperatures and
high humidities.
(4) Hydrogen sulfide and other gases emanating from sewage, septic
sewage and sewage sludges.
(5) Saline groundwater with high chloride or sulphate contents both below
the water table and in soil zones above the water table where capillary
action and the presence of oxygen may cause extremely severe
conditions.
9.1.2 Paint
The Contractor shall only be allowed to use paints which are delivered to the
site in sealed cans or drums bearing the name of the manufacturer and
properly labeled.
Tints and shades of final coats shall be advised by the Engineer or his
Representative.
PVC sheet materials to be used for lining concrete structures and pipelines
internally shall be manufactured from polyvinyl chloride, plasticisers and
pigments to make permanently flexible sheets.
The PVC sheet shall have a minimum thickness of 1.5 mm and shall be
formed by extrusion to have on one side locking keys or ribs of either ‘T’ or
diamond section at centers not greater than 75 mm. It shall be capable of
forming a continuous 100% effective seal with the use of welding strips or
other approved method and shall be supplied with all materials and tools for
making the joints.
The tensile strength of the material shall be not less than 17000 kN/m2.
All weld strips, patches and other sheets used in the permanent fixing of the
ribbed sheet shall be of a material having the same composition as the
ribbed sheet.
(1) The work size, which is defined as the internal diameter as specified by
the manufacturer, shall be declared and shall not differ from the normal
diameter by more than ± 1%.
(5) The deviation from straightness of the bore of the liner shall not exceed
20 mm.
Although the liners are not designed to be structural, they shall have a
sufficient stiffness to withstand :-
Prior to grouting of the manhole liner at least 24 hours shall be allowed for
temperature equalization between the manhole structure and the reinforced
plastic liner.
The manufacturer shall provide shop drawings of the proposed top slab
liners prior to manufacture for approval.
The manufacturer shall stipulate the maximum deflection of the slab liner
permitted without causing surface cracking to the gel coat. The Contractor
must take care not to exceed this limit, and any surface cracking that occurs
will be repaired.
(3) Bisphenol polyester resin with heavy duty glass cloth inclusion.
The mortar shall be manually applied to all internal surfaces and left at least
15 minutes.
Firstly the surface of the manhole walls and the surface of the cover slab
soft, benching and channel (concrete) shall be coated with isophthalic resin.
Three layers of 600 gm/m2 glass chopped strand mat shall then be applied
and impregnated with isophthalic resin to provide an approximate thickness
of 5 mm.
Next one layer of 600 gm/m2 and one layer of 300 gm/m2 glass chopped
strand mat shall be applied and impregnated with vinylester resin.
Following this two layers of glass veil shall be applied and impregnated with
vinylester resin.
Finally a coating of vinylester resin with paraffin wax shall be applied to
provide a total minimum thickness of 7 mm.
Bisphenol Polyester Resin with Heavy Duty Glass Cloth Inclusion System
All cleaned surfaces shall be primed with a polyester based primer to seal
the surface and aid the application of the lining.
The base coat of resin reinforced with filler shall be trowel applied to
approximately 1.5 mm thick. The reinforcing cloth shall be consolidated into
the first trowel coat with particular attention being paid to ensure that the
cloth is fully wetted out. This application shall be allowed to cure overnight
before applying the top coat of resin. This resin reinforced with the same
filler shall be troweled on and dressed with a rolling aid.
The epoxy mortar system shall be a trowellable, two component epoxy resin
system consisting of a prefilled base and unfilled reactor which when mixed
shall produce a high strength, impermeable and chemically resistant mortar.
The epoxy mortar system shall have excellent chemical resistance to sodium
chloride and sulphuric acid (shall pass the relevant chemical resistence test),
and shall have high impact resistance. Typical properties are given in the
following table:
When placed on a concrete substrate the epoxy mortar system shall have
an adhesive strength of not less than the internal cohesive strength of
concrete.
To achieve the necessary adhesion to the substrate an epoxy primer
compatible for use with the mortar and the substrate shall be applied.
The epoxy mortar, or the primer where required, shall be suitable for
application onto a substrate with a moisture content of 4% or less as
measured by the "wet-check" Moisture Meter or other instruments approved
by the Engineer.
The pot-life of the mixed mortar shall not be less than one hour at the
temperature at the place of application at the time of mixing. The Engineer
may restrict application to such time as the ambient temperature is
sufficiently low for the specified pot-life to be ensured.
There shall be strict control of surface cleanliness between primer and epoxy
mortar and between coats of the same. Vacuum removal of dust and sand
shall be employed and water soluble contamination shall be removed as
specified above. Where dirt or dust has become trapped in the primed
surface it shall be removed with suitable abrasive paper. The surface being
primed shall be free of visible moisture throughout these operations.
The mortar manufacturer shall stipulate primer and epoxy re-coat intervals
for all curing temperatures likely to be encountered and these shall be
adopted with a maximum tolerance of +4 hours. Where this is exceeded the
surfaces to be re-coated shall be suitably abraded to remove gloss.
Bituminous emulsion shall be to the approved standard and shall not contain
less than 53 % of bitumen.
9.2.1 General
The permissible rate of permeation of all protection systems shall not exceed
0.0027 per inches (ASTM, 1 per inch = 1 gramme of water per hour per
square foot (0.0929 m2) per mil (0.0254 mm) of thickness for a 1 inch (25.4
mm) difference in Hg vapour pressure on each side of a membrane.
The membrane shall be tropical grade, cross laminated to have high tear
strength; and puncture and impact resistance and shall be chemically
resistant for protection against aggressive soils and contaminated
groundwater.
2
Tape Strength ASTM D638 Long 4.2 N/mm2
Trans 4.8 N/mm2
During the backfilling operation around all tanked structures, the waterproof
membrane shall be protected from damage by the use of an approved
protection board. The board shall be manufactured from graded and
selected kork granules bound with modified bitumen and encased between
two layers of tough asphalt paper. The board shall be light weight and
capable of providing protection against abrasive backfilling. The board may
be stored outside, but shall be kept flat on original pallets.
The surface shall first be wire brushed and all dust and loose scale removed.
Three coats of bituminous rubber emulsion paint shall then be applied. The
second coat shall not be the same colour as either the 1st or 3rd.
Water Proofing Membrance the following test shall be checked with Dubai
Centeral Laboratory;
The surface shall first be wire brushed and all dust and loose scale removed
(refer to Clause 19.4 for schedule of surface preparations). An epoxy resin
or other primer/sealer (for concrete and allied substrates) shall then be
applied followed by coats of high build epoxy airless spray or other coatings
to give a minimum dry film thickness (dft) of 300 microns. Freedom from
pinholes shall be established by use of a spark tester. The approved paint
system must have adequate flexibility to suit the thermal movements of the
concrete without cracking whilst maintaining an effective bond.
The PVC sheet lining shall be fixed such that the keys or ribs are cast into
the concrete surface. The lining shall be capable of taking up the same
profile as the concrete substrate as indicated on the Drawings.
The manufacturer shall visit the site to demonstrate to the Contractor in the
presence of the Engineer's Representative the methods of handling and
lifting, including formation of the joints between the chamber liner.
The Contractor is reminded that these liners are not designed to withstand
pressure exerted by the concrete during construction.
Where the Contractor is required for any reason to cut reinforced plastic
liners, he shall seal the exposed ends with an approved resin before
incorporating the cut reinforced plastic in the work. No cut reinforced plastic
shall be used until the resin has cured.
9.3.1 General
The Contractor shall provide the labor, materials and equipment necessary
to install and test the odor control facilities as shown on the Contract
Drawings and as specified herein. The odor control units shall be either of
the activated carbon filter types or of the natural soil filter bed types as
indicated in the Drawings.
The activated carbon odor control filter shall be furnished and installed in
accordance with Clause 20.3. The air blowers for the odor control unit shall
be as specified in Clause 20.3.
9.3.4 Natural Soil Odor Control Filter
9.3.4.1 Materials
The HDPE liner shall be furnished and installed in accordance with Clauses
19.3.4 and 19.2.13 and as shown on the Contract Drawings.
Washed Stone
Stone for the air plenum shall be washed, rounded, uncrushed, well graded
in size from 20 mm to 25 mm and consisting of clean, and durable particles
free from dirt, vegetation or other objectionable matter and free from an
excess of soft, thin elongated, laminated or disintegrated pieces. The
Contractor shall submit a sample of the stone to the Engineer for approval
prior to placement.
Wood Chips
Soil Filter
The soil filter shall be a mixture of approved natural sand or sandy loam and
treated compost. The compacted soil/compost mix shall have a 50 percent
porosity. The compost shall be a product of thermophilic aerobic
stabilization. It shall be adequately stabilized, so as to be completely free of
any odors. The compost shall be friable, pass through a 13 mm mesh
screen, and be free of stones, stocks and all objectionable debris. Compost
shall have a pH of 5.5 to 8.0 and no less than 25 percent volatile solids. The
compost source is subject to the review of the Engineer. All compost shall be
"cured" to the point that it is no longer self heating.
9.3.4.2 Installation
The Contractor shall place the stone, wood chips, soil and compost in layers
of uniform thickness as indicated on the Contract Drawing(s) or as directed
by the Engineer. The stone, wood ships, soil and compost shall be placed so
as not to damage the aeration piping. Damaged piping is to be replaced by
the Contractor at no additional cost to the owner.
9.3.4.3 Monitoring
The Contractor shall perform the following selected soil and atmospheric
analyses at the direction of the Engineer, but not more than once per week
with the exception of soil moisture and pH, for the length of the natural soil
filter maintenance period. The results of the analyses shall be recorded and
presented to the Engineer at the end of each month. Soil samples must be
taken so as not to disrupt the even distribution of air through the odor control
filter.
Atmospheric Hydrogen Sulfide
9.3.4.4 Maintenance
The Contractor shall test the porosity of the compacted soil/compost mixture
before placement and provide the results of the test to the Engineer.
10.1 CONCRETE
10.1.1 Tolerance
Floor and roof slabs shall be level to a point within ± 5 mm of the level
shown on the drawings. Columns and beams shall have no irregularities
exceeding 3 mm in a 3m length. The position of the face of columns, beams
and walls at any point shall be within 5 mm of its position derived from the
drawings.
All exposed concrete beams, columns and slab surface described as fair-
faced shall be Type f.f. as follows: -
Type f.f. shall be an as struck finish entirely free from honeycombing, stains,
pins, clippings, lining joint marks, nail and screw marks, raised grain marks,
air holes and surface defects and shall be uniform in colour tone and surface
texture with clean true faces and arises.
The Contractor shall submit to the Engineer for his approval prior to
concreting his proposals for the sequence of placing concrete and the
position of horizontal and vertical construction joints.
Small pre-cast items such as lintels, sills and padstones shall be built in as
the work proceeds and have a fair-faced Type f.f. finish where exposed to
view and hacked surfaces where plastered.
Cast-in fixings shall be securely fixed to formwork ready for casting and shall
be true to line in the positions shown on the drawings.
All Bricks & Blocks Works shall conform to RTA/DM Local Order No.
44/1990.
Wall ties shall be 18/8 stainless steel vertical twist type 200 mm long.
Wall ties shall be built in the mortar beds as the work proceeds and shall be
spaced at a maximum of 900 mm horizontally and 450 mm vertically and
shall be staggered. Each door and window opening shall have wall ties at
each joint at 225 mm centres vertically.
As described for Joinery Fixing Accessories. Door and window frame ties
shall be fixed as described under Joinery Work.
10.2.4 Mastic
Mastic for pointing door and window frames shall be one part gun-grade
polysulphide mastic to accepted standards and approved by the Engineer.
Mastic seals to windows or door frames shall be neatly gun applied to clean,
solid and dry backgrounds in one operation. The mastic shall be a triangular
seal across the whole joint and any surplus shall be cleaned off when set.
10.2.7 Pointing
All pointing shall be done as the work proceeds and shall be flush with face
of blockwork.
10.3 ROOFING
Roof screed shall be laid to fall over the concrete roof slab and have a
minimum thickness of 35 mm and maximum thickness of 75 mm. The screed
shall be thoroughly mixed 1:4 cement/sharp sand mix with very little water
added. The screed shall be laid and compacted and shall be levelled off and
finished with a steel trowel. Precautions must be taken to prevent rapid or
excessive drying out.
Primer for concrete shall be suitable for use with the waterproofing
membrane and shall be applied in accordance with the manufacturer's
instructions.
Surfaces to receive the membrane shall be smooth, dry and free from dust.
The membrane shall be laid on a primed surface and in accordance with the
manufacturer's recommendations.
The fascia cladding shall be of single skin construction formed from profiled
aluminium sheeting with matching aluminium profiled flashings. The
Contractor shall provide working drawings and manufacturer’s literature for
approval before ordering the same.
10.4 JOINERY
10.4.1 Timber-General
Timber for joinery shall be air dried and the moisture content be allowed to
reduce until it reaches a level in equilibrium with local conditions. It will be
deemed to have reached equilibrium when the moisture content is 12% +
2%.
Timber shall be 3 mm less per wrought or finished face than the sawn size.
10.4.3 Hardwood
Adhesives for exterior use shall be synthetic resin types, weather and
boil-proof, complying with the approved standard. Adhesives for interior use
shall be synthetic resin types, moisture resistant and moderately weather
resistant, complying with the approved standard.
Door frame and lining fixing cramps shall be of 25 mm wide x 14 swg thick x
250 mm girth stainless steel, one end turned up 50 mm and twice drilled and
the end fishtailed for building-in.
Dowels for fixing door frames shall be 10 mm dia. x 100 mm long stainless
steel.
Timber preservative shall be water repellent and protect the timber from all
wood destroying fungi and insects particularly termites. The preservative
shall be applied in accordance with the manufacturer's instructions including
treatment to all ends, notches and joints in treated timber out on site.
10.4.6 Ironmongery
10.4.7 Workmanship
Where the term 'framing or framed' is used it shall mean all halvings,
dovetails, tenons and hardwood pins and the best known means of putting
this work together.
10.4.8 Storage
All joinery shall be protected from the weather during transit and shall be
stored under cover, clear of the ground in clean, dry ventilated conditions so
as to maintain the specified moisture content.
All framework shall be put together loosely and stored as described and
shall not be wedged and glued together until required for fixing.
External door frames shall be built-in as work proceeds with fixing cramps as
described. The fixing cramps shall be screwed to the back of the frames at
450 mm maximum centres with two sheradised screws 25 mm long. The
fishtail ends shall be built-in to the brickwork or blockwork mortar joints as
the work proceeds.
10.4.10 Doors
External doors shall be hung on one and a half pairs of hinges unless
otherwise detailed, to give a maximum tolerance all round of 2 mm.
10.5 METALWORK
10.5.1 Aluminium
Aluminium alloy sections for aluminium shall be type H59 TF box sections.
10.5.4 Ironmongery
Rates for supplying and fixing ironmongery shall include for all boring,
cutting, mortising, sinking, making good, replacing damaged screws, oiling,
adjusting, leaving in good working order and mastering all locks.
Screws shall be of suitable gauge and material for the purpose and shall
match the item to be fixed.
10.6 PLUMBING
Copper tubes shall be half hard copper tube of accepted standard approved
by the Engineer.
uPVC pressure pipes and fittings for water supply shall be of an accepted
standard approved by the Engineer.
10.6.4 Workmanship
10.6.5 Pipework
Copper tube shall be fixed clear of walls and ceilings with two piece copper
spacing clips or with proprietary plastic pipe clips. Clips shall be at 1.20m
horizontally and 1.50m vertically for 15mm diameter pipes and at 1.80m and
2.40m respectively for 22mm and 28mm diameter pipes. Capillary joints
shall be neatly made with all surplus solder removed.
Screw threads on compression joints shall be wrapped with PTFE tape prior
to tightening.
uPVC waste pipes for sinks and urinals shall be fixed and jointed in
accordance with the manufacturer's instructions. Fixing clips shall be at
0.50m horizontally and 1.20 m vertically and joints shall be by 'O' rings, seals
or solvent cement. Care shall be taken to allow for expansion in accordance
with manufacturer's instructions.
10.6.8 Sleeves
uPVC sleeves shall be provided through walls and ceilings for pipes and
shall be internally 3 mm minimum larger than the pipes.
10.6.9 Testing
Soil and waste pipes shall be air tested for leaks to a pressure of 38 mm
water gauge, constant for three minutes.
Rainwater pipes shall be tested for leaks as above and gutters shall be
tested by filling with water to overflow level.
GRP cold water storage tanks shall be placed on 2 nos. galvanised mild
steel brackets bolted to the wall.
10.7.1 Cement
10.7.2 Lime
10.7.3 Sand
Sand for plasterwork with gypsum plasters shall be suitable for use with the
brand of gypsum plaster used. Sand for rendering, internally and externally,
and floor screeds shall comply with Clause 5.1.3.
Metal angle beads and plaster stops for plasterwork and plasterboard shall
be manufactured from galvanised mild steel.
10.7.7 Plasticizers
Plasticizers shall be an approved vinyl resin type and used in the manner
and proportions recommended by the manufacturer.
10.7.9 Storage
Vitrified and fully vitrified floor tiles shall be as detailed on the drawings.
Floor tiling shall be laid with a proprietary tile adhesive (approved by the
Engineer) either directly onto a clean, dry and level concrete sub-floor, or on
a cement/sand screed laid over the sub-floor. The sub-floor surface shall be
scabbled to remove all surface laitance prior to tiling or screeding. The
screed shall be mixed semi-dry by hand or in a pan mixer and shall be a 1:4
cement/sharp sand mix with just enough water to enable it to hold together
when squeezed in the hand. The sub-floor shall be kept damp for 24 hours
and the screed shall be laid and well compacted to a thickness of 56mm and
brought to the required levels using a draw float. The finished floor screed
shall be kept damp for a period of 7 days prior to commencement of tiling.
The tile adhesive shall be spread evenly by steel trowel to a thickness of
3mm onto which the clean, dry tiles shall be laid to give a 3mm minimum
joint width. The tiles shall be grouted with a proprietary and approved tile
grout within a minimum period of 24 hours after laying.
Coloured wall tiles shall be 152 x 152 x 5.5mm thick glazed tiles approved
by the Engineer.
Tiles shall be fixed with proprietary tile adhesive (approved by the Engineer).
The tiles are to be bedded strictly in accordance with the manufacturer's
instructions with 10mm joints between tiles.
At least 24 hours after fixing tiles are to be jointed using approved mortar.
Tile adhesive for floor and wall tiling shall be as recommended by the Tile
Manufacturer and used in accordance with the adhesive manufacturer's
instructions.
Expansion joints in floor and wall tiling shall be 6.5 mm wide Polyethylene
backing strip with 6.5 mm wide approved silicone sealant, gun applied on the
face in accordance with the manufacturer's instructions.
10.7.16 Backgrounds
All backgrounds shall be clean, dry, free from efflorescence, paint, oil and
dust and adequately prepared to provide a good key. All loose, flaking and
unsound material shall be completely removed and all mortar joints shall be
raked out, if required, to a minimum depth of 10 mm. Concrete surfaces shall
be well wetted five minutes prior to plastering or rendering.
10.7.18 Hacking
Dubbing out of all areas to receive plaster or render shall be in the same mix
as the subsequent coat, not exceeding 10 mm thickness in one application,
and shall be allowed to harden.
All internal finishes shall not commence until the building is watertight,
including glazing, and reasonably dried out.
The render shall be two coat work comprising a stipple coat as described
previously and a finishing coat giving a maximum thickness of 12 mm. The
mix shall be in the proportion 1:1:6 cement/lime/sand. The render shall be
kept damp for a minimum of three days. All window and door openings must
be closed to prevent through draughts causing rapid drying out.
10.7.23 Stucco
A PVA copolymer based putty for concrete and plaster shall be applied, in
accordance with the manufacturer's instructions, to the surface of the
internal render after curing has taken place. The stucco shall only be applied
in sufficient thickness to seal the surface of the render and remove minor
surface irregularities to give a smooth surface ready to receive the
decorative finish.
External render shall be applied to concrete, concrete blocks and clay bricks
as follows :-
The render shall be three coat work comprising a stipple coat as described
previously, an undercoat and a finish coat giving a maximum thickness of 16
mm. The mixes shall be in the proportions shown on the schedule of mixes.
The undercoat shall be level, true and of sufficient thickness to prevent the
background joints showing through and shall be kept damp for three days
before applying the final coat.
A key for the final coat shall be provided by combing the undercoat prior to
setting with wavy lines 20 mm apart and 5 mm deep. The final coat shall be
6 mm minimum thickness and worked to a level and smooth finish with a
wooden float with clean, true and level arises. The whole shall be protected
from rapid drying out in hot, dry and windy weather.
10.8 GLAZING
10.8.1 Glass
Glass for glazing shall be the best of its respective kind and free from
blemishes and imperfections. Glass shall be as shown on the drawings.
10.9.1 Painting-General
All primers, oil bound undercoats and finishes, emulsions and polyurethane
interior varnishes shall be used in strict accordance with the manufacturer's
recommendations and shall be obtained from an approved manufacturer.
Only fresh paint delivered to site in original sealed containers shall be used.
Each container shall be labelled with the manufacturer's name, contents,
colour, quantity, batch number and date and instruction on method of
application.
10.9.3 Workmanship
All painting shall be carefully executed with clean brushes and in the best
manner and applied strictly in accordance with the manufacturer's
instructions.
All paints, stains and varnishes shall be well stirred before use and thinned
only in accordance with the manufacturer's recommendations.
Painting of exterior work shall not be carried out in wet, dusty or foggy
weather and interior work shall not proceed in dusty conditions.
Plaster shall be clean and dry and free from loose material. Holes and
cracks shall be cut back and solidly filled, allowed to dry and rubbed down
smooth.
Mild steel shall be blast cleaned and primed with two coats of primer within
four hours of cleaning.
Galvanised mild steel shall be degreased with white spirit and primed with
two coats of primer.
Interior primed softwood and all primed mild steel shall be painted with two
undercoats and one gloss or semi-matt finish coat of oil-based paint to give
a smooth, even and solid finish, all as instructed. Each coat shall dry
overnight before applying further coats.
The paint finish to internal walls shall be PVA copolymer matt emulsion paint
or as detailed on the drawings.
10.9.8 Ironmongery
All fixed ironmongery except hinges shall be removed before painting and
refixed on completion.
12.1 GENERAL
The Contractor shall be responsible for the safety of personnel and the
public during the contract period and compliance with safety requirements
stated herein shall not relieve the Contractor of his responsibility or liability
under the Contract.
If at any time safety requirements are not being met by the Contractor, the
Engineer shall have the right to instruct the Contractor on the necessary
safety provisions and the Contractor shall comply with such instructions
forthwith.
The Contractor shall notify the Engineer immediately of any accident that
occurs whether on or off site in which the Contractor is directly involved
which results in any injury to any person whether directly concerned with the
site or whether a third party. Such initial notification may be verbal and shall
be followed by a written comprehensive report within 24 hours of the
accident.
The Contractor shall make himself familiar with the condition of the site
before tendering in order to assess the nature of safety problems he is likely
to encounter and the safety requirements.
The Contractor shall appoint a Safety Officer who shall be responsible for all
aspects of safety. He shall be conversant with and experienced in all general
civil engineering construction and sewer safety techniques and emergency
procedures, and shall be on site at all times operatives are working. He shall
enforce and supervise the safety procedures at all places of works and make
sure that adequate safety equipment, required under Clause 12.5, is
available in good working condition and at all places of works at the time
works are on-going.
All personnel working on, visiting or inspecting any part of the Works shall be
provided with and be required to wear appropriate protective clothing or
apparatus.
Every hoist, lift, sling, chain, rope, pulley block and any other lifting tackle,
used in the Works shall be thoroughly examined by a competent person at
least once every 6 months and shall be test loaded to 150% of the safe
working load and shall then be tagged with the safe working load and the
date of successful testing by an authorised testing authority.
All parts and working gear whether fixed or movable, including the anchoring
and fixing appliances of every crane and lifting machine shall be of good
construction, sound material, adequate strength and shall be properly
maintained. All parts and gear shall be examined at least once every twelve
months.
12.6.1 General
Special care shall be taken to protect all employees when using power tools
or materials which will produce a fine dust and in particular all asbestos
based products. The operator should stand upwind of the operation and
wear an approved respirator and goggles. Wherever possible overalls
should be worn and should consist of 60% polyester fibre and 40% cotton.
The Contractor shall adopt the safety procedures as proposed by him as per
Clause 12.4 for entry into a manhole or other confined space. However, the
following safety procedures are outlined as a guide only. The Contractor
shall, where appropriate, use these procedures in addition to his proposed
procedures while entering into a manhole or a confined space. Also included
are additional information on safety procedures for manhole entry in
Appendix 3 contained in Part 3 of 3 of these Specifications for his guidance
and use where appropriate.
When any person is in a confined space, the atmosphere at the work place
and at the base of the access manhole or pit shall be continuously monitored
by a Monitoring Device to detect oxygen deficiency, flammable gas and toxic
gases. The monitoring equipment shall be designed to be lowered into the
work place or access manhole and shall not depend on a sample draw tube
from the surface. The monitoring equipment shall be the first piece of
equipment to be lowered into the place of work and shall be the last piece of
equipment removed.
The Contractor shall provide, maintain and calibrate the approved monitoring
equipment in accordance with the manufacturer's instructions. The
Contractor shall provide adequate numbers of monitoring devices to fully
cover all proposed work places and open manholes or access pits with
adequate spare devices, parts and batteries as needed to ensure complete
monitoring of all sites of work at all times throughout the construction period.
No entry into a confined space shall be allowed until the monitoring devices
have been properly placed at the work place or access site and the readings
indicate that the atmosphere is safe. Operatives are to be fully trained in the
use of the monitoring equipment and in the necessary response to alarm
conditions.
the manhole covers or through open access pits. Positive ventilation shall be
provided at all times when a person is in a confined space, even if the
atmosphere monitoring equipment indicates that the atmosphere is safe for
access.
Each person entering a confined space shall wear a harness at all times.
The harness shall be designed such that it will enable an unconscious
person to be lifted to the surface in a vertical posture.
Every work place where persons are entering a confined space, shall be
provided with facilities for washing.
12.6.8 Communication
12.6.9 Lighting
Prior to initiating any work at a site, the Contractor shall prepare, for the
approval of the Engineer, a plan for the diversion and control of traffic
around the work site. The approved traffic control plan shall be submitted to
the Roads and Transport Authority (RTA) - Roads Department and Dubai
Traffic Police for review. Work at the Site may not commence until the traffic
control plan has been approved by the RTA and Dubai Traffic Police.
The traffic control plan shall include a street plan of the work site showing all
traffic lanes and building access drives that will be affected by the work. The
proposed system of traffic diversions and the manner of control shall be
clearly illustrated, including the location and types of traffic cones, warning
signs and warning lights to be used. The plan should indicate the
anticipated schedule of works for which traffic must be diverted. Road
diversions and road signs shall conform to Clause 1.3.4.
The traffic control plan shall take into consideration the requirements of the
work crew for access to the work site, for positioning and parking of vehicles
needed for the work and for the temporary storage of equipment and
materials.
16.1 GENERAL
The Contractor shall furnish all labour, tools, materials and equipment
required to design and complete the installation of pipelines using
micro-tunnelling or pipe jacking methods as and where indicated on the
Drawings and as specified, including surveying, instrumentation and
dewatering. The Contractor may also elect to use micro-tunnelling
methods to install those pipelines where the installation method has been
left to the option of the Contractor.
The Contractor shall decide the excavated dimensions of the drive and
reception shafts at the locations shown on the Drawings and as required
for the micro-tunnelling method selected. Minimum shaft dimensions shall
be used at all locations.
The Contractor's design shall include for all ground stabilization measures
either in advance or during micro-tunnelling operations.
The settlements arising from the construction of the works shall be limited
to the following:
The proximity of buildings is such that the driving of steel sheet piles to
shafts is not permissible, nor is any construction noise greater than 70 dB.
All constructional plant forming part of the micro-tunnelling system is to be
electrically driven, either by mains supply or on-site generation.
The pipes and joints proposed for use in micro-tunnelling item(s) shall, as
a minimum, comply with the appropriate standards set for pipes and joints
(refer to sub-section 4.1) used in conventional (open-trench) pipeline
construction in all respects including materials of manufacture, tolerances,
minimum strengths, etc. In particular, the pipes and joints must comply
with the details of Clause 4.1.6 for use in micro-tunnelling or similar jacking
operations. The Contractor shall satisfy the Engineer that the proposed
pipes and joints shall adequately withstand the temporary loads applied
during installation.
If the Contractor elects to propose GRP pipes with concrete surround for
micro-tunnelling, he shall submit along with his Tender, comprehensive
material standards and complete specifications for these pipes for review
and consideration of the Engineer. He shall also provide evidence of
successful use of such materials elsewhere in a similar construction
method and in areas of similar soil conditions including the highly saline
nature of the groundwater as in Dubai.
16.2.1 General
The Contractor shall set out the works and establish the laser guidance
system for the micro-tunnelling machine using survey stations given on the
Drawings or indicated by the Engineer on site. Any temporary control points
are to be recorded and notified to the Engineer for checking.
The laser guidance system for the micro-tunnelling machine shall be such
that the machines position can be continuously monitored. Any deviations
from line or level shall be recorded as each new pipe is inserted.
Boreholes shall be sunk adjacent to all proposed shaft locations. Due to the
variability of soil, rock and groundwater conditions, boreholes should also be
sunk at intermediate locations. It is recommended that boreholes be sunk at
a maximum intermediate spacing between shafts of 50 meters. In any case,
it shall be the responsibility of the Contractor to adequately familiarize
himself with the ground conditions along the pipeline routes and to assure
himself that the selected construction method is appropriate and safe. This
data is also vital to the proper selection of cutting head for the tunnelling
machine.
The boreholes shall be sunk at least 2.0 meters below the level of the
proposed works or at least 50 percent deeper than the proposed works,
whichever is deeper and shall be sited at least 2 metres off the proposed
tunnel line to avoid creating areas of weakened ground.
The boring logs, results of the laboratory tests and a discussion of the
results as they pertain to the selection of micro-tunnelling method and the
selection of cutting head shall be compiled in a "Soils Investigation Report"
and submitted to the Engineer prior to commencing micro-tunnelling work on
any section.
- Optical survey for layout and verification of all instrument locations and
elevations.
The geotechnical firm shall read and record data in accordance with the
schedule below and report data from the geotechnical instrumentation within
24 hours to the Engineer during the course of the work for eeeeo-tunnelling
or shaft excavations.
Monitoring Schedule
He shall provide settlement points on the road surface and within existing
structures. Settlement points in the vicinity of the shafts will be agreed with
or at the direction of the Engineer.
The geotechnical firm shall install settlement anchors and reference head in
drill hole in accordance with manufacturer’s instructions. Anchors shall be
grouted in place with cement/bentonite grout mix. Proportions by weight
shall be 1 part of cement to 3 parts of bentonite to 3 parts of water, (1:3:3).
The Contractor (or his specialist sub-contractor as per Clause 16.3.4) shall
install inclinometer casings at locations as directed by or agreed with the
Engineer. The geotechnical firm shall supervise installation and testing of all
devices and provide qualified personnel for the proper operation and
maintenance of the installation and shall take field measurements for lateral
deformation both perpendicular and parallel to adjacent structure.
The geotechnical firm shall reference all instrument locations and elevations
to existing benchmarks and line monumentation. He shall establish
elevations on all instrument reference points to a minimum accuracy of 0.01
foot.
16.4 DEWATERING
The Contractor shall supply all equipment, tools, materials and labour for
dewatering and control of groundwater using dewatering systems consisting
of well points and/or deep wells. The system shall include any system
required to recharge the groundwater so that adjacent structures are not
affected with any additional piezometers and observation wells.
Once dewatering has begun, it shall continue 24 hours per day for extent of
time shaft excavations are open. Water levels shall be maintained at least
16.4.1 Submittals
The position of drive and reception shafts should be checked on site by the
Contractor to ensure that the design has provided sufficient working space
which will cause the least disruption to the flow of traffic.
16.7 EQUIPMENT
The equipment utilized to perform this work shall be designed and provided
so as to carry out the micro-tunnelling work efficiently. It shall be able to
handle the ranges of ground conditions indicated by the boreholes and
groundwater level information, with excess capacity. The equipment shall be
able to maintain stability of the tunnel when taking into account the soil and
hydrostatic loads as well as any surcharges imposed by vehicular traffic.
16.8 EXECUTION
Prior to the start of work on any pipe section, assemble all material,
equipment and tools necessary to conduct tunnelling work continuously until
that section is completed.
The sewer lines are located such that manmade obstructions should not be
encountered. However, the Contractor should have contingency methods
available to remove natural or manmade obstructions should they be
encountered including the facility to withdraw the micro-tunnelling machine
along the line of the tunnel drive if obstructions or changes in ground
conditions are encountered within 30 metres, to allow a different micro-
tunnelling machine to be used.
The tunnel shall be excavated to a size such that the overbreak is kept to a
minimum. The overbreak occuring shall be filled with a suitable slurry to
keep ground movements within the tolerances given in Clause 16.1. Slurry
pressure or mechanical earth pressure shall be maintained to ensure a
positive pressure on the working face at all times.
At all times when the tunnel is being advanced, a field supervisor with
extensive experience in the operation of the equipment being used shall be
present.
The setting of the laser and target and the alignment of the tunnel relative to
the laser beam shall be continuously monitored (refer to Clause 16.2.2) to
ensure compliance with the horizontal and vertical tolerances as specified in
Clause 16.6.
16.9 TESTING
16.10 SAFETY
The Contractor is responsible for the safety of all personnel as well as for
the safety of the public during the performance of the work and is
responsible for maintaining safe conditions in and around the work area.
This is specified in more detail in Section 12.
Particular care shall be taken to ensure that all components are suitable for
the corrosive climatic and environmental conditions prevailing in Dubai.
As well as complying with the specified procedures for approval the following
documentation shall be supplied and procedures followed for all items of
electrical and mechanical plant in the Contract.
(c) Any additional drawings of particular items, called for by the Engineer.
If the drawings are not approved one copy will be returned to the Contractor
marked to indicate the alterations required.
Upon final approval one copy will be marked Approved and returned.
During the course of the Works the Contractor shall maintain a detailed
record of all changes in order to facilitate accurate preparation of “As Built
Record” drawings and to ensure that these drawings are in all respects true
record of the installation.
The final record drawings shall be prepared by the Contractor and shall
show the complete Works including the sizes and routes of all ducts,
pipework and cables. The scales used shall be such that all details are
legible when reduced for inclusion in the Operation and Maintenance
manuals. All drawings shall show scale bars as appropriate.
The drawings shall clearly show the names of the plant manufacturers,
giving model and type numbers, and all details of plant and machinery duty
ratings, sizes, current settings, fuse ratings, etc. of all items of plant including
electrical distribution cabling and wiring installations.
The Contractor shall provide three prints of all drawings and schedules
correctly modified as final record drawings. These shall be submitted to the
Engineer for approval before the issue of a Taking Over Certificate and shall
be a complete record of the Mechanical and Electrical installation.
If the drawings are not approved, one copy shall be returned to the
Contractor with marked indications of the alterations required.
Upon final approval, one copy of the drawings or document shall be stamped
“Approved” and returned to the Contractor.
One set of the approved record drawings on paper shall be included in each
of the Operation and Maintenance manuals. These may be full size drawings
folded and inserted into clear plastic sleeves bound directly into the
document. Reduced size drawings shall be legible in all respects, and the
actual reduced scale clearly marked on the drawings.
Before plant is delivered the Contractor shall provide for the use of the
Employer and the Engineer:-
(b) Two copies of Draft Instructions for the Operation of the Plant which
shall describe the installation as a whole and shall give step by step
procedures for every operation in the running of the Plant. All
necessary drawings and sketches shall be included.
(c) Two copies of Draft Instructions for the Maintenance of the Plant.
These instructions shall include charts showing lubrication, checking,
testing and replacement procedures to ensure trouble free operation.
The Contractor shall obtain the Draft Instructions from the suppliers, check
them for accuracy and shall bind each Instruction Book in Uniform bindings,
the cover of which shall be finished with a black and greaseproof material
and the title printed on the front and the spine including the word ‘Draft’.
Before the Taking-Over Certificate is issued the Contractor shall provide for
the use of the Employer and the Engineer:-
(a) Three copies of Approved Instructions for the Operation of the Plant
which shall describe installation as a whole and shall give step by step
procedures for every operation in the running of the Plant. Copies of
the as built record drawings and sketches shall be bound in the
document.
(c) 1 No. copy on magnetic disc & tape on digital drawings in AutoCAD
release 13, Intergraph or DXF file as appropriate and two hard copies
of the following As Built Record drawings¤ for approval :-
(a) Drawings showing the internal construction of the major items, with
parts list and reference numbers for ordering spares.
When (a), (b), (c), (d), (e) and (f) have been approved by the Engineer, the
Contractor shall provide two prints of each drawing or detail on thick paper
for the use of the Purchases, and one 35 mm photographic negative of each
drawing or detail mounted in a card frame 187 mm x 83 mm for the use of
the Engineer.
(1) The Plant shall be new, of sound workmanship and of robust design.
(2) The general electrical and mechanical design of the Plant and
particularly that of the bearings, contacts, and other wearing parts,
shall be governed by the need for long period of service without
frequent maintenance and attention being necessary.
(3) Unless otherwise specified, all items of Plant shall be rated for
continuous service at the specified duties under the prevailing
atmospheric and operational conditions on site.
(5) All items of Plant for which spare parts may be required shall have
attached to them untarnishable serial numbers and basic information
as to rating, etc. in sufficient detail to allow the unit or assembly to be
identified in correspondence and when ordering parts.
(7) Provision shall be made for taking up wear in all bearings and other
wearing parts or for easy replacement if adjustment is not practicable.
(8) If any moving parts show, in the opinion of the Engineer, signs of
undue wear or unsuitability for the purpose for which they were
installed, they shall be deemed to be defective materials, workmanship
or design and shall be replaced.
(9) Suitable packers and/or shims shall be fitted for ease of adjustment
and re-alignment of all machinery units. Particular attention shall be
given to combined sets.
(10) Where fitted bolts, spigots or other means for precise location are not
employed in the assembly of the Plant, locating dowels shall be fitted,
on completion of erection, to the satisfaction of the Engineer.
(2) The positions of all greasing and oiling points shall be arranged so as
to be readily accessible for routine servicing. Where necessary to
achieve this, suitable extension pipes shall be fitted.
(4) Where continual grease or oil feeding is required the capacity of the
reservoir shall be sufficient for not less than seven days continuous
services.
The Contractor shall supply the initial charges of oil, grease electrolyte and
similar materials necessary for the correct setting to work and operation of
the Plant.
17.6 SPARES
(1) Spares shall be readily interchangeable with the parts they replace,
and shall comply with the specification.
(3) Spares shall be packed and protected for storage to the appropriate
standard. Electrical equipment shall be sealed in polythene or similar
bags with a liberal supply of desiccant. Other items shall be protected
so as to avoid corrosion and spoilage for a minimum of twelve months
after handover to the Client. Machined surfaces of all mechanical
components shall be further protected by the application of a protective
coating which may be easily removed at the time of installation. Each
package shall have attached to it an untarnishable metal plate giving
information for identification. This shall include the maker’s name and
reference description as shown on the marked-up drawings supplied.
(5) The Contractor shall provide the detailed agreed schedule in duplicate
of the spares supplied one copy to be retained by the Engineer after
checking the goods.
(1) A schedule is included to cover all special tools necessary for the
proper maintenance of the Plant. The Engineer will notify the
Contractor which tools shall be included in the Contract. These tools
shall not be used for the purpose of erecting the works.
(2) The Engineer may require to inspect the tools and packaging before
dispatch and the Contractor shall hold them at his works and not allow
them to be sent by suppliers direct to site.
Spares and tools shall only be dispatched to site after instructions for their
reception have been applied for and obtained from the Engineer.
The Contractor shall provide a lockable metal tool box to contain two sets of
tools as required by (1) above together with two sets of steel combination
spanners to fit every nut/bolt size on the plant including the holding down
bolts and unions, plus other tools of a special nature necessary for general
maintenance.
The Contractor shall provide a detailed schedule in duplicate of the tools and
lubricants supplied one copy to be retained by the Engineer after checking
the goods.
(1) All Plant shall be adequately protected and packed in accordance with
the approved standard. In addition the Plant shall be so protected as
to be safe from spoilage and corrosion until installation or in the case of
spare parts for a period not less than 12 months from its date of
handover to the Client.
(2) Items of plant which are finished painted at the manufacturer’s works
such as switchboards, shall be suitably encased in wood (such as
hardboard secured by screws to a wood framework) for their protection
before dispatch.
(5) The Contractor shall make good to the satisfaction of the Engineer any
deterioration of the protective coatings, paintwork, etc., which may
occur during transportation.
(2) Each starter shall be provided with an individual fuse for the control
circuit deriving its control supply from the live and neutral in its
associated cubicle unless otherwise specified. Indicating lamps shall
be controlled by separate auxiliary contacts.
(5) Each pump level float switch shall be separately provided with its own
low voltage supply transformer to avoid all pumps being cut out should
one transformer fail.
The Contractor shall provide qualified engineer(s) to instruct and train the
Employer’s staff in the operation and maintenance of the plant.
After the equipment has been installed, tested, adjusted and placed in the
satisfactory operation the Contractor shall provide the services of the
manufacture's representatives to instruct the Employer's operating personnel
in the use and maintenance of the equipment. An instruction and training
programme shall be conducted for up to 6 operators designated by the
Employer. The Contractor shall give the Employer at least two month's
written notice of the proposed instruction and training programme.
The Contractor shall be responsible for the maintenance of the plant for one
year from the date of Taking Over and shall supply at his own cost all spares
required during this period.
Eleven months after the Plant has been in operation, a visit to site shall be
made by an experienced fitter, of the Contractor or the Manufacturer, who
shall service all the Plant. The service shall comprise tracing and correction
of all faults and replacement of any item of plant found to be defective which
the Engineer considers to be the Contractor’s liability.
17.14.1 Introduction
l) System curves.
i) General
ii) Contents
iii) highlight any particular complex or critical tasks over the above
normal requirements.
iv) measurements and guidance on limits of acceptable wear for all
items subject to wear.
h) Fault finding and correction. This shall provide a guide to first line
checks that can be undertaken in the event of plant failure without
the need for reference to the detailed instructions. A detailed guide
of more complex checks shall be provided in Section (g).
i) Inventory of installed plant. A schedule of this shall be
provided.
j) Drawings list. A list of the ‘As-Built’ drawings shall be provided.
k) ‘As Built drawings’. Approved copies of all "As-Built" drawings
shall be included for the following:-
i) process and instrumentation diagram
ii) site layout showing main works operational features
iii) equipment and machinery layout
iv) mechanical and electrical details
i)
The above are to be supplied to the satisfaction of the
Engineer. The Contractor shall provide the Engineer black and
white prints of each on thick paper and one ISO size A2 (594 x
420) negative of each. All drawings shall be prepared on a
CAD system and printed on ISO standard sized paper A1
unless specifically requested otherwise. Each drawing shall be
marked with the Engineers Consultant's, Contractor's and
manufacturers names and references, drawing number, title,
scales, date of completion and a full description and date of all
amendments, and shall be certified 'As-built'. The project title
shall be included in a box at the bottom right had corner of each
drawing.
17.15 WORKS TESTING AND INSPECTION OF MANUFACTURED ITEMS
All manufactured items for incorporation in the Works shall be offered for
inspection, examination and witness testing and shall be supported by
certificates to demonstrate compliance with this specification and with the
approved manufacturing and testing standards specifications.
The Contractor shall give to the Engineer and the Inspecting Engineer
reasonable notice, which shall normally be of two weeks, of the date and
place at which plant will be ready for prescribed testing.
If the tests are beyond the resource of the manufacturer he shall make
arrangements for these to be carried out elsewhere. Any variation of this
requirement shall be agreed and confirmation in writing shall be obtained
from the Engineer.
The Contractor shall supply four unpriced copies of all sub-orders for
manufactured items. Two copies of each of these sub-orders shall be
forwarded to the Engineer and two to the appointed Inspecting Engineer at
the time the sub-orders are placed. The sub-order shall indicate the Works
for which the item is required, state in detail the inspection and test
requirements, give sufficient information for ready identification and shall
state that these items will be subject to witness testing and inspection.
Four copies of all test certificates and, where relevant, curves shall be
supplied to the Inspecting Engineer within two weeks of completion of any
witnessed tests.
Where witness tests are not required or instructions to waive witness tests
have been issued, the test certificates and curves shall be forwarded to the
Inspecting Engineer within two weeks of the date of testing.
The Contractor shall be entirely responsible for complying with the above
testing and inspection requirements, including the provision of test
certificates, curves and any other information required by the Engineer and
shall ensure that due care is taken by himself and his Sub-Contractors or
suppliers before presenting the Plant for inspection or test. If unauthorised
delivery has taken place the Contractor may be required to arrange for the
Plant to be returned to the manufacturer for inspection and/or witness testing
by the Inspecting Engineer.
All apparatus, instruments and connections required for the tests shall have
been tested for accuracy within the preceding 12 months.
Any equipment used in the testing of the Plant shall in all respects comply
with the appropriate safety regulations and/or requirements regarding
electrical apparatus for the safety of the Plant and the men working therein.
The Contractor shall carry out tests as stated in the approved standard;
performance tests and such other tests as are necessary, in the opinion of
the Engineer, the Engineer’s Representative or his Inspecting Engineer, to
determine that the Plant complies with the Specification either under test
conditions in the manufacturer’s works, on site or elsewhere or in the
ordinary working.
Where pumps are included in the Contract, at least one unit of each size
shall be tested with the suction rigged to conform to site conditions.
All cast metal components designed for the retention of liquids, e.g. pump
casings, gear boxes, engine crank cases, etc., shall be checked for
soundness after machining etc., but before assembly or painting by treating
with paraffin or similar method.
Testing shall be done & Certification shall be issued by the Inspection &
Certification Section of the DCL.
Motors of 15kW and above shall be witness tested for performance to the
approved standard.
Type test certificates shall be provided and shall include the following
information for all motors :-
After initial witness testing each motor shall be combined with its driven units
and witness tested to demonstrate satisfactory performance, correctness of
assembly and ease of re-assembly at site. The assembled units shall be
adequately marked and dowelled.
(4) Lubricating and fuel lines, sumps, tanks, etc., shall be adequately
flushed to remove any foreign matter before being put to use.
The Contractor shall not proceed from one stage to the next without
the Engineer's approval.
All installation shall be safe to use. Temporary access, covers etc., will
only be permitted if approved by the Engineer.
All cleaning work shall be completed.
Clean water shall be used to fill tanks, wells piping and systems that
contain water, sewage or sludge in normal operation. Where
Tests shall show that all component units operate with the quantities,
efficiency, repeatability, and accuracy specified.
System validation tests shall not commence until tests have been
satisfactorily completed.
OR DAE Pumpen AS
Tolderlundsveg 3
DK - 5100
Odense C
Denmark
OR Groupe Schneider
P. O. Box 43103
Abu Dhabi
UAE
Binghalib Engineering
P.O. Box 6969
Sharjah
United Arab Emirates
OR Siemens Aktiengesellschaft
Werrer-von-Siemens-Strasse 50
Power Engineering Group
E5 Division
D8520 Erlangen
Federal Republic of Germany
The Contractor shall be responsible for liaising with the suppliers, obtaining,
checking for accuracy and issuing all drawings and other documents and for
co-ordination of supply and installation.
17.19 CLIMATE
All plant and materials used shall be suitable for the climatic conditions
described below.
The climate in Dubai is relatively mild from November to May, and hot from
May to October with high relative humidity.
The prevailing wind directions are from the North and West. Strong winds
are common with maximum velocities exceeding 160 km/hr and sand storms
occur in the summer months.
The electricity supply available from the Dubai Electricity & Water Authority -
Electricity Division network is 3 phase 220/380 volts, 50 Hz 4 wire.
The minimum derating for all electrical equipment including cables shall be
in accordance with the relevant Electrical Standards appertaining to the
climatic conditions referred to in Clause 17.19.
17.22 TROPICALISATION
17.22.1 General
In choosing materials and their finishes due regard shall be given to the
conditions under which equipment is to work. Tropical duty materials shall
be used wherever possible.
17.22.2 Metals
Ferrous metals shall be prepared and coated in accordance with the painting
specification. Small iron and steel parts (other than stainless steel) of all
instruments and electrical equipment the cores of electromagnets and the
metal parts of relays and mechanisms shall be treated in an approved
manner to prevent rusting.
Cores etc. which are built up of laminations or cannot for any other reason
be anti-rust treated shall have all exposed parts cleaned and heavily
enamelled or lacquered.
When it is necessary to use dissimilar metals in contact these shall be
selected such that the electro-chemical potential difference is not greater
than 250 mV and if practicable the two metals shall be insulated from each
The use of iron and steel shall be avoided in instruments and electrical
relays wherever possible. Steel screws when used shall be zinc, cadmium
or chromium plated or when plating is not possible owing to tolerance
limitations shall be of corrosion resisting steel. Springs shall be of bronze or
non-rusting material. Pivots for which non-ferrous material is unsuitable shall
be of an approved rustless steel where possible.
17.22.4 Wood
The use of wood shall be avoided as far as possible. When used it shall be
of an approved type to resist termite attack and fungal decay.
The Contractor shall comply with any safety precautions called for by the
Engineer such as a "Permit to Work" system for access to designated high
risk areas including wet wells, sumps, valve chambers sewers and buildings
in addition to Electrical Danger Areas.
The wet wells of pumping stations and raw sewage open channels to a
height of one metre above coping level shall be classified as Zone 2; in
accordance with BS EN 60079:1997.
The Contractor shall furnish a progress report for the ME&I Works at the end
of each month utilising software generated CPM planning and reporting
methods The Contractor shall in his report state the details with dates of the
submission, approval, manufacture, works testing, shipment, installation, site
testing & commissioning of the proposed equipment.
All equipment furnished under this specification shall be new, and wherever
possible, shall be a standard product of an approved or experienced
manufacturer, assembled from standard components readily available in the
market.
After approval of the mechanical and electrical drawings the Contractor shall
prepare and submit to the Engineer revised drawings showing any
necessary revisions to the proposed building and civil structures. The
location, size and details of box-outs and fixings for mechanical and
electrical and other equipment shall be shown on the revised drawings and
the Contractor shall be responsible for providing in the civil structures the
correct location and size of the box-outs and fixings shown on the approved
mechanical and electrical drawings. The Contractor shall prepare at his own
cost the necessary revised civil drawings and detailed structural and other
design calculations and submit them to the Engineer for approval. The
Contractor shall not be entitled to an extension of time for completion for any
delays from the preparation of such revised drawings. The Contract price
shall not be increased as a result of any changes in the civil structure from
that designated unless such changes are the result of variation properly
ordered by the Engineer.
17.29 GUARANTEE
The Contractor shall provide a guarantee for the maintenance period for all
equipment in accordance with the General Conditions of Contract. In
17.30 CO-ORDINATION
The Contractor shall take all measurements for his work at the installation
site, verify all dimensions and conditions at the place of installation verify the
sub-contractor's drawings and be responsible for the proposed installation,
of the equipment within the available space specified and shown on the
Drawings. Proposed deviations from the Drawings and Specification shall
be submitted to the Engineer in writing giving full details and reasons for the
requests. The Engineer’s approval must be obtained for any modification of
the original works.
v) recording intervals.
All applicable data such as, but not limited to, water and other liquid
levels, flows, pressures, head differentials, duration of runs, instrument
readings, voltage settings, drive speeds, motor running currents, torque,
voltages and related information, as applicable, and in accordance with
approved test procedures shall be recorded at the start and finish of
each operational demonstration and at 30 minute intervals during system
validation tests, unless other intervals are specified.
The Site Reliability Trials shall be carried out as follows under the control of
the Contractor's staff and the supervision of the Engineer. The purpose of
these trials shall be as follows:-
(i) To confirm the results of the Works Tests.
The Site Trials shall be carried out under the control of the Contractor's staff
and the supervision of the Engineer. The Contractor shall provide all of the
necessary labour and instrumentation to conduct the test.
Failure of one of the elements during the test run shall invalidate the test run,
and test runs shall be repeated until a continuous uninterrupted test run of all
equipment has been obtained.
(ii) A record of all limit switches, overloads, relay and protective settings
etc. shall be tabulated to show the "as-built" condition of each
applicable part of FBA’s and other electrical switchgear and include a
discrimination chart.
(iii) All cables shall have an insulation test to confirm the integrity of the
insulation. A tabulated record of results shall be made. Every cable
shall be subject to the following tests after installation:-
Tests shall also be performed to prove earth loop impedance for all
circuits. Calculations shall be produced in accordance with the IEE
regulations to support the relevance of the impedance measured.
(v) The control centres, control panels and instrumentation shall be
statically tested with motors disconnected to confirm the correct
sequence and functional operation.
(vi) Each pump shall be operated individually over the range from closed
valve to maximum emergency top water level on a re-circulation basis
using fresh water. During this test the following parameters will be
recorded:-
The hydraulic tests shall also be applied to the above ground pipework
at Site after erection. The Contractor shall provide the necessary
equipment including any temporary blank flanges which may be
required to isolate equipment.
(vii) All cranes shall be tested at works with a load 25% in excess of the
rated load.
The tests shall be repeated at site when erection is complete using test
weights to be provided under the Contract.
Certificates shall be provided for both tests and these shall include
details of centre span deflections recorded during the test procedure.
After all the deficiencies apparent during the site reliability trials have
been rectified to the Engineer's satisfaction, apart from necessary
retesting, the following test shall be carried out:-
18.1.1 Construction
Switch and control boards shall be factory built assemblies (FBA) and be
constructed and certified by an approved short-circuit testing authority. They
shall normally be of steel, flush fronted cubicle type, and of rigid
construction, the sheet steel being not less than 2 mm. Each FBA shall be
multi-cubicle or multi-box type form 4 with a separate compartment for the
busbars and for each functional unit or group. The protective conductor
shall not be exposed. Unless otherwise detailed they shall be self standing
and have front access. Each enclosure shall be suitably protected to an
approved International Standard against dust, damp & vermin . Removable
back and other plates, where fitted shall be provided with suitable gaskets or
inserts.
Steel used for the construction of boards shall be zinc sprayed or equally
protected. Bolts, nuts, washers, etc. shall be of stainless steel. Small fixing
screws and other similar items shall be of non-ferrous metal. Screws, bolts
etc. on the face of boards shall be of stainless steel. Painting shall be to
final coat of stove enameled grey gloss finish for external surfaces, unless
otherwise detailed, and stove enameled white gloss finish for internal
surfaces. Each coat to be individually stoved on. All paints shall be applied
to the directions of the paint manufacturer. Surfaces of boards which will be
in contact with or close to structures shall, in addition, be coated with
bituminous paint or equal.
Boards shall be properly earth bonded and provided with a tinned and
sleeved copper earthing bar of minimum size 300 mm2 running the full length
of the board and supplied with terminals of adequate size for connection to
the station earthing system.
18.1.3 Terminals
All internal connections, terminals, and metal supports for equipment and
cables shall be included.
Cables, unless otherwise detailed, shall enter through the underside of the
board via approved cable glands secured to a blank steel glanding plate.
Space shall be provided to accommodate cable glands of appropriate size
for incoming and outgoing circuits. Direct termination on equipment such as
distribution board fuses or miniature circuit breakers is not acceptable.
Undrilled non-ferrous gland plates bolted into position shall be provided
where single core cables are terminated.
Termination blocks shall not be more than 400 mm from the gland plates.
They shall be referenced, readily accessible, of adequate size and suitable
for accommodating surge diverters.
18.1.4 Busbars
Bus bars and connections shall be identified by phase colour marking and
adequately supported by suitable insulators the whole to be mechanically
and electrically designed to withstand the full fault capacity as specified
herein.
Lamps shall be well ventilated and the design shall permit removal of lamp
glass and bulbs from the front of the unit.
All pilot lamp bulbs shall be of the same voltage regardless of transformer
primary voltage.
Each motor starter shall be provided with its own MCCB or fused switch,
which shall be suitable for padlocking in the "off" position.
18.1.9 Control Circuit Protection
Separate short circuit protection devices shall be provided for each circuit
and shall be clearly marked to show the circuit that is protected.
Socket outlets where detailed, shall be of low voltage not exceeding 220 V
fed from a suitable double wound and fused transformer with earth leakage
protection. They shall be 3 pin 16 ampere flush socket outlets with flaps.
18.1.12 Metering
When provision for the Dubai Electricity Water Authority (Electric Division)
metering equipment is specified the Contractor shall obtain details of the
equipment and shall submit drawings of the arrangements to be provided
for approval. The approved arrangements shall be incorporated and
annotated in the drawings submitted to the Engineer. When the KWH meter
is supplied by the Control Panel Manufacturer, the meter shall be forwarded
to the Dubai Electricity Water Authority (Electric Division) for calibration tests
prior to installation. The calibration certificates shall be included with the
documentation.
18.1.13 Labeling
Labels shall be colourless transparent plastic material not less than 3mm
thick with beveled edges to half the thickness. Each shall be reverse
engraved in Arabic and English the engraving being filled white and the
reverse side painted blue unless otherwise detailed. Main labels shall be
provided as detailed and subsidiary labels be provided for each item on the
face of the board, stating what it indicates or controls. Any item which is not
isolated at the board shall, in addition, be provided with a warning label
"Danger Live Terminals Isolate Before Maintenance" with flash and voltage
in red letters on white background in Arabic and English. A drawing giving
label sizes and a list of inscriptions shall be submitted to the Engineer for
approval before manufacture. All labels shall be fixed before taking-over
tests are carried out.
All external labels shall be affixed with chrome plated nuts and bolts with
slotted holes to allow for expansion of the label. All internal labels shall be
engraved multi-layered plastic to an approved design affixed with chrome
plated nuts and bolts or a permanent adhesive.
18.1.14 Spares
The spare parts list for the FBA’S shall be as approved by the RTA/DM.
A complete spare set of all fuses and indicating lamp bulbs in each cubicle
shall be provided suitably marked and clipped in readily accessible positions,
preferably inside the door; in each cubicle.
Each panel shall have provision for standby generator incoming supply as
an alternative to the main supply as follows:-
(a) For a load of 125 Amps or less, a suitably rated three position change
over switch with indicator lights shall be provided.
One No. 3 phase, weatherproof neutral and earth, 5 pole male socket for
the connection of a standby power generator supply shall be flush
mounted on the L.H. bottom section of the panel. Where the panel is
located inside of a weather proof kiosk. A lockable door shall be provided
to afford direct access to the socket. Each socket shall be complete with
a female plug for the termination of the generator supply cable. The
socket shall incorporate a mechanically interlocked mechanism to
ensure that the plug is fully/correctly inserted into the socket prior to
switching on the supply. The fitting shall be rated at 125 A, 600 V and
shall be compatible with the existing fittings. Each socket shall be
complete with a secured cover which may be placed in position when the
plug is removed, and as detailed on the single line diagram.
(b) For a load higher than 125 Amps appropriate termination and change
over arrangements shall be provided, and as detailed on the single line
diagram.
Panels for use in locations exposed to the weather shall be installed within
Fibre Glass Kiosks.
(b) Each push button shall operate through a suitable shroud covering the
whole of the button and forming a barrier between the button and the
interior. All operating spindles on isolators, etc. shall enter their
enclosures through packed glands or similar, to exclude moisture.
A generator plug and socket enclosure shall also be provided on the L.H.S.
of the kiosk. The enclosure shall be fitted inside the kiosk, mounted flush
with appropriate opening and lockable doors.
Joints of main or control wiring between the components are not permitted.
All control panel wiring, motor starters, control gear and the like shall be
carried out in a neat and systematic manner with cables supported clear of
the panels and other surfaces at all points to obtain free circulation of air.
Claw washers shall be used to terminate all small wiring. Insulating bushes
shall be provided where necessary to prevent chafing of wiring. Neoprene
will not be used with PVC wiring. All panel wiring shall be in PVC sheathed
cable or fire-resisting cable of approved type.
All control panel wiring, motor starters, control gear and the like shall be
carried out in a neat and systematic manner with cables supported clear of
the panels and other surfaces at all points to obtain free circulation of air.
Claw washers shall be used to terminate all small wiring. Insulating bushes
shall be provided where necessary to prevent chafing of wiring.
All circuits above 200 Volts shall be wired in 450 / 750 Volt grade cable but
circuits at 200 Volt and below in 300 / 500 Volt grade cable. The conductors
shall be of copper and shall have a minimum cross sectional area of 1 mm2.
All wire ends shall be tinned before termination and all terminals shall be
protected by PVC sleeves or flame retarded cold shrink or heat shrinkable
tubing. All wires shall be fitted with numbered ferrules of approved type at
each termination.
Crimped lugs shall be fitted to all wires and cables for termination.
18.1.19 Thermal Overload Relays
cable boxes complete with glands of suitable size for the accommodation of
the incoming and outgoing cables entering from below.
Facilities shall be provided for testing the circuit breaker operation when in
the isolated and withdrawn position. Auxiliary jumper connections if
necessary shall be included.
The incoming circuit breakers should be fitted with over current tripping and
earth fault relays with auxiliary relay for instantaneous remote trip and
indication.
All incoming circuit breakers shall be fitted with a voltmeter with a selector
switch to read voltage of the line and line to neutral.
Ammeters shall be fitted on the bus bar side voltmeters on the line side of
the incoming circuit breaker trips.
The LV circuit breaker shall trip every time its associated HV circuit breaker
trips.
All components of the switchgear including bus bars and cable boxes shall
be capable of withstanding the tests outlined in the approved International
Standards.
(2) Unless otherwise called for in the detailed specification the following
standards sizes shall be employed throughout :-
60, 100, 150, 200, 300, 400, 500, 600 and 800 A.
(3) The switch action shall be parallel, giving a simultaneous make and
break action on all contacts.
(4) Moving contacts shall be provided with suitable fillets between phases
with fixed contacts fully shrouded.
18.5 FUSES
Fuses for systems of up to and including 1,000 Volt pressure, shall be of the
HRC cartridge type to approved International Standards.
(1) Selector switches shall be of robust design and construction and rotary
in operation. Bezels shall be of non-metallic rust-proof type.
18.10 EARTHING
All switchboards and control boards shall be provided with a proper system
of earthing, suitable for connection to all protective conductors and metallic
sheathing of all associated cables, so as to be effectively connected to the
general mass of earth at the sub-station from which the installation is
supplied, in accordance with approved regulations and codes of practice as
required by the supply authority and to the approval of the Engineer.
18.11 AC MOTORS
(9) Moving parts of the motor shall be provided with guards and where
appropriate hinged doors shall be provided for easy access to
commutator and brush gear.
(12) Each motor shall be provided with a suitable external earthing terminal.
(13) Each motor shall have a rating plate with the following information:-
18.12.1 General
The starter cubicles as required are to form part of the FBA and as such
circuit connections protection devices and the like shall comply with the
approved International Standards appertaining to the FBA’s . The cubicles
shall be easily accessible for maintenance purposes and shall be damp-
proof and dust-proof. The motor starter shall comply with an approved
International Standard and shall be suitable to carry the full load current of
its rated duty at its most severe load conditions. All starters shall be capable
of at least 20 starts per hour at 100% full load torque. Motor starters shall be
dust-proof. Motors up to and including 11 kW shall be started direct on line.
Motors above 11 kW shall be started in accordance with applicable clauses
detailed herein.
iv. For slip ring rotor resistance starting there shall be provided
magnetically operated starting, accelerating and running contactors
operating under mechanical or pneumatic timing devices.
v. Contactors shall be selected for AC4 duty.
vi. For Solid State Reduced voltage Starting there shall be provided a
micro-processor based electronic logic module and a 3 pole, 6
thyristor (SCR) full wave power section together with the following
features:-
Protection Against:
overcurrent unbalance
single phase
earth fault
relay settings
% of FLC that the motor is taking
continuous monitoring of thermal capacity of motor
thermal capacity used during start of motor
if tripped, how much time before restart to take place
stall or short circuit trip
earth fault trip
starting
j) 1 Set of power factor correction capacitors with fuses for all corrected
drives.
The following equipment shall be mounted on the door of the starter cubicle:-
l) 1 No. ammeter fitted with suppressed scale to read motor running and
starting current.
o) 1 No. Blue pilot lamp to show automatic operation has been selected.
iv) 1 No. Triple pole H.V. vacuum contactor which shall comply with
requirements of an approved International Standard and be designed
to minimise the mean currents chopped and transient over voltages to
those which could occur with an equivalent air contactor. Continuous
vacuum monitoring facilities shall be provided and interlocked with the
contactor coil.
18.12.4.1 General
Where slip ring rotor resistance motor starters are employed the rotor
resistance shall be of the metal grid type and shall limit the starting current to
that specified for the size of drive.
Rotor resistance shall be mounted in floor standing units, panel top units or
integral panel units.
Both the exterior and interior of the cubicle shall be stove enameled to in
Grey to an approved International Standard. Warning notices to indicate
electrical hazard within shall be fixed to all access panels.
Each cubicle shall be equipped with a heater which shall be continuously
"on" while the associated resistance bank is de-energised.
The cubicles shall be provided with adequate ventilation louvres and access
to the resistance units shall be by means of a lockable, hinged front door.
Cable connections to the main control panel shall be via suitable cable
glands to maintain the integrity of the control panel enclosure.
The rotor resistance may be mounted within a cubicle within the control
panel itself provided that:-
(b) The resistance cubicle is provided with suitable cable gland entries to
maintain the integrity of the control panel enclosure.
(e) 1 No. TP wound magnetic overload relay fully adjustable but set at the
actual current setting required to trip under a stalled motor condition
within the maximum time that the motor characteristic permits this
condition to exist.
(1) M.C.C.B's shall withstand the system short circuit current of not less
than 30 KA.
(3) The rated voltage insulation shall not be less than 600 V AC and the
rated operation voltage shall not be less than 380 V AC.
(4) The rated operational current for uninterrupted duty shall meet loading
requirements.
(8) Volt free contacts shall be provided for ON/OFF indication, contacts
shall be wired to case mounted terminals.
The control unit shall be suitable for operation on 220 V AC supply and in
the ambient conditions prevailing in Dubai. It shall contain a built -in battery
with a minimum life of 2 years. Stored data shall be protected from being
lost in the event of a power failure. The unit shall record the time taken to
empty the sump and calculate the idle time to continuously adapt the
operation of the pump(s) to the station inflow to achieve the most
economical operation. The current sensors for use in conjunction with the
(6) The emergency stop (low level) float shall be in circuit for both manual
and auto modes of operation and shall stop all the pumps.
(7) A high level in the pump shall be indicated in the panel through a float
switch and a continuously rated flasher light mounted on top of the
kiosk marked 'HIGH LEVEL IN SUMP'.
(8) Reset button to erase all stored operating data from the memory.
The objectives and key features of the telemetry system will be as follows:
(2) To provide operational data for both normal and fault conditions
including the initiation of alarms in order to minimise the frequency of
visits and to provide a prompt response to faults.
Sufficient space shall be provided in the control panel for the telemetry
system. The Contractor will be provided with outline requirements for the
system and will be required to then offer detailed proposals and
specifications for the plant and equipment to be supplied.
The specifications, plant and equipment etc. shall be subject to the approval
of both the Employer and the Engineer.
The battery and charger shall be housed in a single sheet steel floor
mounted ventilated cabinet with batteries housed in the lower part of the
cubicle.
The unit shall be complete with a self adjusting constant potential trickle
charger suitable for operating from a 220V single phase AC supply. The
charger shall be rated to continuously energise relay coils and lamps as
applicable. The charger shall be designed to maintain a constant voltage
within 3% irrespective of mains voltage or frequency variation. Booster
charge facilities shall be included.
The unit shall be fitted with the following:-
1 No. Supply ON indicating lamp
1 No. ON/OFF switch
1 No. Charger ammeter
1 No. OFF/FLOAT/BOOST switch
1 No. Charger failure alarm relay and lamp
1 Set of cable terminals and fuses.
All battery cells shall be either nickel iron or nickel cadmium structure with an
alkaline electrolyte and be provided with a suitable drip tray to protect the
cabinet from corrosion caused by accidental spillage of the battery medium.
Batteries shall be 30V or 110V DC and of suitable ampere hour capacity to
operate the closing and tripping coils motor of the circuit breakers. Dual duty
batteries (i.e. for engine starting and for tripping circuit breakers) will not be
acceptable.
18.17 TRANSFORMERS
18.17.1 Standards
18.17.2 Windings
The high voltage windings shall be provided with tapping at +5%, +2.5%, -
2.5%, -5% with constant flux voltage variation as defined in an approved
International Standard.
The tap changing selector shall be located below the oil level inside the tank
and the selector operating rod shall extend outside the tank.
18.17.3 Construction
The transformer tanks shall be constructed from high grade steel with
electrically welded seams. The structure of the tank shall enable it to be
handled whilst filled with oil and shall be pressure tested to 70 kN/m2.
Tank shall be fitted with skids and four removable rollers and lifting eyes
suitable for the mass of the transformer and oil.
The tanks shall be provided with external cooling tubes to provide natural
cooling under the climatic conditions.
All terminals shall be brought out through oil tight insulating glands into
respective disconnecting terminal chambers to facilitate cable testing.
The design and construction of the transformer core winding and tank shall
ensure that the noise level at full load is kept to the minimum consistent with
economic design. The tank shall be reinforced or braced where necessary
to reduce the noise level.
All windings, winding terminals and connections shall be fully immersed in oil
under all operating conditions and materials shall be suitable for this duty
and not be subject to deterioration from contact with oil.
18.17.4 Fittings
(a) Thermometer pockets, one for oil and one for winding temperature.
(b) 200 mm diameter dial type oil and winding temperature indicators each
fitting with 2 No. sets of adjustable contacts for alarm and trip
functions.
(c) Rating and diagram plate complying with an approved International
Standard and of a durable and non-corrodable material.
(h) Marshalling box for overtemperature, pressure alarm and trip contacts.
18.18.1 General
Particular regard shall be paid to the ease of access to all instruments. Serial
number/calibration plates shall be visible when the instrument is in its
cabinet.
18.18.5 Indicators
Level indicators shall be scaled vertically, alarm levels being indicated by red
areas.
Motor current ammeters shall have red lines or adjustable movable pointers
to indicate motor full load current.
Digital flow indicators shall be three figure electronic digital display type.
Precaution shall be taken to ensure that fluctuation in the signal, however
caused, does not render the last figure to unstable and unreadable during
normal running when updating of readings at three second intervals.
18.18.7 Integrators
All chart recorders for use in control and instrument panels, desks, consoles,
etc., shall comply with the following unless specified elsewhere.
Have a linear scale not less than 100 mm long with clear graduations and
markings.
Have the units of the measured variable and any multiplying factor clearly
marked on the scale plate.
Be designed so that the chart may be withdrawn from the front and replaced
without interrupting the indicating section.
Have a plug-in chassis which may be withdrawn from the front leaving the
housing in position, without interrupting its signal.
Have a minimum chart speed of 20mm per hour and a minimum chart
duration of 4 weeks.
Have charts with printed calibration of 0-100% and 24 hr. time marks.
Match all other meters and instruments (including indicating meters, meter
relays, integrators etc.) on the same panel, and on similar panels in the
same room, as regards style, finish and appearance.
The Contractor shall ensure that all meters intended for installation on
inclined surfaces are suitable for that application, and that when so mounted
the accuracy will be maintained over the whole range.
Sufficient charts shall be provided for two year operation at the time of
take-over.
18.18.9 Transmitters
Transmitters shall be manufactured from materials suitable for use with the
process medium and for the site ambient conditions and this shall be
approved by the Engineer.
The power consumption shall not exceed 16 watts per 100 mm of diameter.
The output shall be 4-20 mA and the system accuracy shall be within 0.75%
of the flow rate. Test Certificates shall be provided.
The equipment shall be guaranteed suitable for the ambient and process
liquid temperatures and the atmospheric environment.
Each flow-meter primary element shall be supplied with a Teflon liner and
electrodes of material best suited to the particular process fluid.
Primary units shall be as follows:-
Incorporate electrodes to detect when the pipe is not full. The detectors
output shall control circuits within the converter to short out the analogue
signal and initiate an indication of the "pipe not full" condition.
a. Complete with amplifier (converter), drive unit (if applicable) and all
cable for connecting between the components. Where this equipment is
exposed to the environment it shall be housed in a GRP enclosure.
All materials in contact with the process liquid shall be approved for use in
the specified application.
All items of equipment attached to the pipe and/or pipe insert shall be of non-
corrosive material, designed to withstand continuous submergence to a
pressure of 3m head and guaranteed suitable for the temperature and
process pressures, including maximum possible surge pressures.
The transmitter shall process the signals from the acoustic transducers and
shall:-
The complete system shall operate with a minimum accuracy of ±1.5% of full
scale deflection over the full ambient temperature range. A test certificate
shall be provided for each set of equipment.
The sensor shall be suitable for mounting in the open, or within an enclosed
tank, and shall be totally enclosed and hoseproof with environmental
protection appropriate for the installed location.
The control units shall incorporate facilities for adjusting independently both
zero and span, and shall have an output of 4-20 mA proportional to level.
The overall accuracy of the level measurements shall be within ±1.0% of the
instrument span.
The connection between the sensor and control unit shall be via a single
length of commercially available screened cable, and the equipment shall
operate with up to 150 metres of such cable. Cable connections / joints will
not be permitted above the processing liquor.
The Contractor shall ensure that all equipment is suitable for the application,
particularly with regard to the blocking distance and transmitted beam angle
/ cone.
The sensor shall be hermetically sealed and suitable for mounting in sewage.
It shall be readily removable.
The control units shall incorporate facilities for adjusting independently both
zero and span, and shall have an output of 4-20 mA proportional to level.
The overall accuracy of the level measurements shall be within ±1.0% of the
instrument span. The connection between the sensor and control unit shall be
via a single length of commercially available screened cable, and the
equipment shall operate with up to 150 metres of such cable. Cable
connections / joints will not be permitted above the process liquor.
The Contractor shall provide and install all the necessary fittings, sub-
distribution boards, contactors, etc. for the complete small power and lighting
installations as follows:-
General
Low voltage supplies required for illumination and power supplies etc. shall be
as follows:-
All handlamps shall be 25V and the socket outlets colour coded violet.
Installation
Small Power Installations shall be provided so that the following facilities are
available in each area.
a) Motor Room
b) Control Rooms
As motor room.
f) Accommodation
General
The lighting shall be located in easily accessible positions for the purpose of
maintenance. If this is not possible the Contractor shall advise the method
for undertaking maintenance and if this requires special equipment such as
scaffolding, hoists or access tower, this shall be provided by the Contractor
at no extra cost.
The Contractor shall submit his proposed scheme together with details of the
fittings he proposes to use and his calculations of illumination levels for the
Engineer’s approval.
a) Motor Room
b) Dry Well
350 lux using energy efficient watt anti-corrosive fluorescent fitting with
polycarbonate diffuser;
c) Control Rooms
400 lux using energy efficient fluorescent fittings with easy clean antiglare
diffusers.
d) Wet Well
e) External Lighting
Over each external entrance door there shall be installed 1 No. 250 watt
high pressure sodium floodlights controlled by an external weather-proof
switch.
g) Miscellaneous
Accommodation
Each room to contain sufficient 100 Watt light fittings with opaque white
glass to achieve the illumination level defined in an approved International
Standard as appropriate for the intended use of the room.
Dry Well - 1 No. unit at each stairway landing plus 1 No. unit at pump level.
1 No. Gripper Type handlamp with wire cage and 25 V, 40 watt B.C. rough
service lamp complete with 30 metres of 3 core tough rubber sheathed cable
and plug suitable for low voltage socket outlets;
Generally for all small power and lighting installations the following Clauses
shall apply:-
18.23.1 Wiring
Wiring shall be carried out in PVC cable enclosed in conduit. The minimum
copper conductor size used shall not be less than 1.5mm2. The use of
junction boxes between fittings shall be kept to a minimum and where
practicable all connections shall be made at the fitting. Where used junction
boxes shall be rectangular pattern and where possible their position shall be
hidden from immediate view but not made inaccessible. Circuit wiring shall
not be connected directly onto the terminals of lighting fittings but shall be
made off in point boxes consisting of a standard box containing porcelain
shrouded pinch screw connectors to which connections shall be made to the
light fitting by heat resistant flexible cables.
All distribution boards shall be of the totally enclosed metal clad pattern (500
V rating) manufactured in accordance with an approved International
Standard.
The enclosure shall be made from zinc coated mild steel formed to a clean
line and complete with a lockable hinged cover with gasket. Removable
plates with conduit knockouts shall be provided at top and bottom.
All distribution boards shall be complete with a Residual Current Circuit
Breaker. The circuit breaker shall be rated and have the same number of
phases as the circuit from which it is fed.
Doors shall be fitted with gaskets and shall be easily removable to preserve
the finish and simplify installation. Each distribution board shall be arranged
for top and bottom cable entry and shall be provided with an ample cable
termination plate and chamber to enable cables to be neatly glanded with
tails grouped and terminated onto appropriate internal termination's.
Distribution boards shall be wall or floor mounted and shall when specified
incorporate on-load isolators which shall be front of panel operated with
ON/OFF indicator and capable of being padlocked in the OFF position.
Distribution boards shall incorporate HBC cartridge fuses or combinations of
single pole and neutral and triple pole miniature pole circuit breakers
(MCB's) as specified.
All distribution boards shall have a fusing factor of 1.5 to afford "close"
overcurrent protection to circuits.
All neutral bars shall have a separate terminal for each fuseway within the
distribution boards.
The termination of the circuit cables at distribution boards shall be neat and
slack left at each fusebank or neutral bar to enable the complete assembly
to be removed for inspection without disconnection. Neutral conductors shall
be connected to the bar in the same order as the phase conductor to the
fuseway.
Socket outlets shall be connected to a ring circuit with each 30 amp circuit
feeding a maximum floor space of 50m2. All socket outlets shall be
switched and of the shuttered type. They shall accept 13 amp. square plugs
and comply with an approved International Standard. They shall be selected
from one of the following types.
(b) Flush mounted socket outlets shall be of the grid switch pattern with
matt chrome heat cured powder lacquer finish covers.
18.23.4 Switches
b) Flush mounted switches shall be of the grid switch pattern with matt
chrome heat cured powder lacquer finish covers.
Special care shall be taken to ensure that all switches are securely
fixed truly vertical and that flush mounted switches are flush with the
wall finish so that the overlapping cover plates seat onto the rims of the
boxes.
Lampholders for flexible pendants, batten or wall mounting shall be of the all
insulated skirted pattern with cord grips. All lampholders shall be of the
bayonet cap pattern.
The point box suspensions and other parts of the lighting fittings shall be
erected at times to suit the building programme for decoration. The
glassware, diffusers, shades, lamps and tubes shall not be fitted until all
building work is complete.
All fittings shall be left clean inside and outside ready for use. All fluorescent
fittings shall be suitable for instant start.
The Contractor shall supply and install all lamps for the entire lighting
installation and shall replace all burned out lamps up to the time that the
Employer takes final acceptance of the works.
18.24 CABLES
18.24.1 General
The Contractor shall ensure that each cable is of sufficient rating for its
normal and fault conditions. To assess the rating and cross section required
for each cable the following factors shall be considered:-
The Contractor shall submit details of the cable sizes for the Engineer's
approval before ordering.
The Contractor shall be responsible for measuring the length of cable
required.
Each cable shall be supplied in a suitable length, continuous through its run.
Through joints will not be permitted without the written permission of the
Engineer.
The earthing conductor shall be of adequate cross sectional area and shall
either be one core of a multicore cable or a separately run single core cable.
The use of conduit, water or other service pipes in any part of the earth
continuity conductor is strictly prohibited.
The Contractor shall supply and install all necessary cable glands and
sealing boxes required to complete the installation.
The cores of each cable shall be taken direct to the terminals of the
equipment to be connected. Cable ends shall be sealed in suitable
chambers bolted to terminal boxes.
The general routing of cables is indicated on the Drawings but the final
routes shall be agreed with the Engineer before any work in connection with
the cable installation is commenced. All cables shall be installed in strict
accordance with the requirements of this Specification.
Cables with a conductor size of less than 1.5mm2 section shall not be used
in the installation.
All cables used shall bear the manufacturer's original guarantee and all
cables shall be delivered to Site in their original wrappings. The Contractor
shall obtain the permission of the Engineer before removing wrappings and
commencing installation.
The Contractor shall ensure that the installation is installed so that no more
than one phase will occur at switch lighting or power outlets where these
outlets are less than 2.5m apart unless guarded by a wall partition or other
barrier. If this is impracticable the Contractor shall obtain the advice of the
Engineer before proceeding.
A minimum tail length of 250mm shall be left on all cables at outlet positions
for connection of the apparatus fed by the outlet.
PVC insulated and sheathed galvanised steel wire armour cable with an
overall PVC sheath (PVCSWA PVC) shall conform to an approved
International Standard. They shall be of approved manufacture of 600V or
1000V grade with copper conductors.
All such cables shall be terminated with mechanical glands in accordance
with an International Standard and shall be of a type to provide adequate
mechanical support by locking on the armour, with outer seal, shroud and
earthtag.
PVC insulated and sheathed galvanised steel wire armour cable with an
overall PVC sheath (PVC SWA PVC) shall conform to an approved
International Standard. They shall be of 600V/1000V grade with copper
conductors from an approved manufacturer.
XLPE insulated and PVC sheathed galvanised steel wire armour cable with
an overall PVC sheath (XLPE PVC SWA PVC) shall conform to an approved
International Standard. They shall be of 600/1000V grade with copper
conductors from an approved manufacturer.
The cable used shall not be less than 1.5mm2 cross-sectional area.
For fire alarms and associated uses they shall be coloured orange
18.25.1 General
Minimum
internal radius
of bend (times
Insulation Finish Overall overall
diameter diameter* of
cable)
Rubber or PVC(Circular Not exceeding 10
or circular stranded Unarmoured mm 3(2)+
copper or aluminium Exceeding 10 mm,
conductors) but not exceeding 25
mm 4(3)+
Exceeding 25 mm 6
Armoured Any 6
PVC or XLPE (SAC Armoured or 8
or shaped copper Unarmoured Any
conductors)
Copper sheath 6
with or without
Mineral PVC covering Any
* For flat cables, the factor is to be applied to the major axis.
+ The figures in parentheses relate to single core circular conductors of
stranded construction installed in conduit or trunking.
Spacing of clips, saddles and cleats shall be such to prevent sagging of the
cables at all times during their installed life.
The Contractor shall prepare drawings showing his precise requirements for
cable trenchwork detailing the width and depth of trenches and indicating the
road crossing cable ducts required. These drawings shall be prepared in
consultation with the Engineer and be approved before issue.
The sanding and laying of cables shall satisfy the following requirements:-
(a) Cables shall be laid at a depth of 750mm for LV and 1000mm for H.V
cables. The depth shall be assessed from finished ground level unless
otherwise directed by the Engineer.
Generally LV and H.V cables should not be run in the same trench but
should be laid staggered. However where necessary to pass through
ducts it may be necessary to lay one above another and H.V cables
should be laid first and sanded before laying the LV cables.
(b) Before laying cables the Contractor should inspect the trenchwork to
ensure that the bottom of each trench is firm and of smooth contour
and free from broken stones or rock.
(c) 75mm of riddled sand shall be placed in the trench to form a bedding
for the cables.
(1) They shall be laid using rollers not more than 3 m apart and where
drawn round corners skid plates and additional rollers shall be used.
(e) Before sanding and backfilling all laid cables shall be inspected by the
Engineer.
(f) After cables have been laid they shall be covered with a further 75mm
of riddled sand which shall be well tamped around the cables.
Mechanical punners shall not be used for this work.
(g) The Contractor shall supply cable cover tiles. These shall be of the
precast concrete type complying with an approved International
Standard and engraved "Electricity".
(h) After sanding cable covers shall be placed in position to overlap the
cables by a minimum of 50mm either side of the cables.
(j) A second inspection following sanding and tiling shall be made by the
Engineer before backfilling.
(k) The Contractor shall carry out backfilling and be responsible for
ensuring that tiles are not disturbed and that no large rocks or stones
are dropped on tiles or included in the backfill material.
(l) After backfilling the Contractor shall reinstate to finished ground level.
(m) The Contractor shall supply and lay in position the necessary cable
route marker posts at a maximum of 10 metres apart and at any
change in direction of cable route.
Where cables enter or leave buildings the ducts shall be sealed at the points
of entry into the building. The Contractor shall include for caulking with an
approved compound, followed by not less than 40mm of bitumen compound
or a weak sand/cement mixture as directed by the Engineer. Care must be
taken to ensure that the PVC sheathing of cables is not damaged during
caulking due to excessive temperature if heated bituminous compound is
employed.
All cable shall be delivered on robust cable drums with cable ends treated to
form an effective seal. When a cable is cut from a drum the cable end left
on the drum shall be immediately sealed in an approved manner to prevent
the ingress of moisture.
Each and every cable shall be permanently identified at each end by its
cable number. Cable markers shall comprise oval markers with semi-rigid
black PVC carrier strip and shall be fixed axially by means of two PVC
covered aluminium strips with buckles. Cable markers shall also be installed
at entry and exist points of buried ducts, exits from buildings and in such
other positions as are necessary to identify and trace the route of any cable.
All power shall be connected to main switchboards and other items of plant
so that the correct phase sequence colour coding are preserved throughout
the system. All such cables shall be identified with phase colours for 3 and 4
wire systems and blue and brown for single phase. On rotating plant, where
to achieve the required direction of rotation it is necessary to connect the
phase cores to the appropriately identified terminals, special core ferrules
shall be fitted to identify each core with the terminal to which it is finally
connected.
All conduit systems and their component materials shall comply with an
approved International Standard.
Conduit shall be neatly run on the surface or buried. Ways shall be provided
for additional conduits at all distribution boards. The size of conduit shall be
as detailed for a particular position or as determined by the number of cables
to be drawn in. In no case shall conduit less than 20mm diameter be used.
Sunken and concealed conduit systems shall support fittings independently
of any false ceiling.
All horizontal runs shall be supported at no more than 900mm. Vertical runs
shall be supported at no more 1200mm. Where directional changes occur
support shall be provided at no more than 150mm either side of the bend.
a. PVC - a bending spring of the correct size shall be used in all cases.
The heat source shall be provided by a hot air torch. When the conduit
is in a pliable state it shall be bent around a suitable former and held in
position until the conduit has set. No other method will be approved.
Particular care must be taken to ensure that no water is allowed to enter the
conduit at any time and all conduits shall be arranged with adequate
ventilation and drainage where necessary or as directed by the Engineer.
No single conduit serving phase socket outlets lighting points and switches
shall contain more than one phase.
Wiring shall be carried out on the looping-in system and no joints other than
at looping-in points will be allowed.
Each flexible connection shall include not less than 400 mm length of flexible
conduit and a separate earth conductor shall be run within the conduit
connected to the earth terminals in the equipment and the fixed conduit run.
The flexible conduit shall not be used as an earth continuity conductor.
Each length of trunking shall be fitted with easily removable covers attached
to the trunking by an efficient fixing.
The trunking system shall be complete with purpose made angle and set
accessories designed to afford easy installation of and to avoid tight right
angle bends in the circuit cables installed in the trunking. All trunking
accessories shall be complete with removable covers. No site made mitred
joints will be allowed.
Where cable trunking is installed in vertical runs efficient circuit cable clamps
are to be installed at not greater than 500mm intervals.
The Contractor shall ensure that the size of the trunking is adequate for the
number of cables passing through it but as a minimum the size should be
50mm x 50mm. All bends tees and intersections shall be of the gusset type
and manufactured by the maker of the trunking and to similar standard.
The cable tray shall be complete with approved type fixings while cleats shall
be of the aluminium or nylon pattern. Cables which shall be attached to
cable tray or structure by saddles or cleats respectively shall be spaced to
ensure compliance with an approved International Standard. The spacing of
supports shall be 1200mm in all cases where cables are supported by cable
tray and 750mm where supported from tray or by cleats. All cables shall be
saddled or cleated in position as they are installed along the route. All cable
tray changes in direction or level shall be made via sets and adequately
sized angles to provide a support to the cables. The cable runs on trays
shall be fixed to the tray by purpose made approved fixing clamps. Cable
trap brackets shall be of galvanised steel. Site manufactured bends and
junctions will not be permitted.
18.26 EARTHING
Where the cable sheath and armour is used as the earth path return then it
shall be established that the impedance is sufficiently low to carry the fault
current and disconnect the equipment. If not a separate copper earth
conductor shall be installed.
The earth tapes shall be protected against corrosion and be complete with
test links. Earth tapes shall be held in position by saddles screw fixed to the
substrate.
Where rigid or flexible conduit and/or trunking is incorporated into the Works
a separate internal earth conductor shall be run which shall be securely
bonded to the terminating apparatus by means of a special earth terminal.
Earth rods shall be copper or steel cored with a metallic bonded copper
outer surface.
Actuators shall be suitable for use with a nominal 380 volt 3 phase 50 Hz
power supply and shall incorporate a motor, integral reversing contactor
starter, local control facilities and terminals for remote control and indication
connections.
Handwheels shall be clearly marked with the words "OPEN" and "CLOSE"
and arrows in the appropriate directions. The rims of handwheels shall
have a smooth finish.
The actuator shall be fitted with a drive bushing which is easily detachable
for machining to suit the valve stem or gearbox input shaft. Bushings shall
be fitted in the base of the actuator to enable standard length valve stems to
be used.
Actuators shall be provided with open and close torque and/or position limit
switches as required by the type of valve or penstock plus two additional
limit switches at each end of travel for remote indication and interlocking. A
mechanical latch shall be provided to prevent the open torque switch tripping
while the initial unsealing hammer blow is applied. Two additional sets of
limit switches consisting of 3 switches per set shall be provided. Each set
shall be independently adjustable to any valve or penstock position. Switch
contact ratings on inductive circuits shall be 5 amp. AC up to 440V, 50 watts
DC up to 250V.
The reversing contactor starter and local controls shall be integral with the
valve actuator and housed to prevent breathing and condensation build-up.
The starter shall be suitable for 60 starts per hour and shall comprise
mechanically and electrically interlocked reversing contactors of approximate
rating to the motor size with coils fed from a 120V control transformer of
40VA minimum rating. The common connection of the contactor coils at the
transformer shall be grounded so that the contactors drop out on the event
of leakage to earth. The primary winding shall be separated from the
secondary by a grounded screen and shall be protected by two easily
replaceable cartridge fuses. Secondary windings shall also be protected by
cartridge fuses.
Local controls shall comprise push-button switch for Open, Close and Stop,
and a Local/Off/Remote selector switch padlockable in any one of three
positions:-
(b) Plug-in interposing relays with dust covers for Open/Close/Stop control
from a specified remote DC supply.
The actuator starters shall be integrally housed with the actuator in robustly
constructed totally enclosed weatherproof housings. The motor starters
shall be capable of starting the motors under the most severe conditions.
All telemetry, micro-processor and PLC equipment shall comply with this
Clause, and the relevant clauses in Section 17 to 20.
The equipment shall accept status inputs from site and panel mounted volt
free contacts and 4-20 mA analogue signals from site and panel mounted
transmitters. Analogue inputs shall be scanned into a 10 bit binary analogue
to digital converter with buffered inputs.
Status outputs shall be suitably rated for switching filament indicator lamps,
connecting into alarm systems, operating hardwire control circuits or other
switching functions in accordance with the requirements of the application
Clauses.
The power supply unit shall be suitable for operation on a supply having a
voltage variation ±6% and a frequency variation of ±2%. The power unit
shall have an isolated output and incorporate protection against voltage
spikes on the mains supply, over-voltage and short circuit.
Each system unit shall include spare installed capacity of not less than 15%
of each type of input and out put module, together with a minimum of 20%
spare system logic capacity.
All systems and equipment shall include diagnostic and automatic self test
routines with volt-free contacts to initiate an alarm in the event of
malfunction.
In all cases the facility shall be provided for modifying the program, altering
set points and adjusting time settings while the equipment is "on line". There
shall be a permanently connected means of accessing set points and timer
settings.
All equipment associated with an operator interface shall utilise a high level,
engineer orientated language to permit programming, editing and similar
functions by engineers and operators.
ii) PLC’s
19.1 FINISH
All covers flanges and joints shall be properly faced, bored, fitted, fixed,
hollowed moulded or chamfered as the case may be according to the best
approved practice. All working parts of the plant and other apparatus shall in
like manner be well and accurately fitted, finished, fixed and adjusted.
19.2 MATERIALS
All materials incorporated in the Works shall be the most suitable for the duty
concerned and shall be new and of first class commercial quality, free from
imperfection and selected for long life and minimum maintenance.
19.3 VALVES
19.3.1 General
All valve waterways shall be coated internally with a solvent free epoxy or
polyester lining of 100% solid content to be applied at the place of
manufacture. The lining shall be of 250 micron nominal thickness and
holiday free.
All hand wheels shall have the words "to open" and "to close" in Arabic and
English with arrows indicating the direction of rotation cast on and shall be
coated in plastic, nylon or other approved materials in order to withstand the
ambient conditions.
All fixing brackets, bolts and nuts, washers, etc. shall be comply with AISI
grade 316.
The key shall be supplied at the rate of one key per two valves or two
penstocks unless the valve or penstock is to be installed in an isolated
location in which case one key shall be supplied for each fitting location.
Before delivery to site all working surfaces shall be thoroughly cleaned, and,
if metal, protected by grease.
Valves under 300 mm diameter together with all hand wheels and other
easily detachable items on both valves and penstocks are to be packed in
timber packing cases and properly bound with steel packing bands.
All valves of 300 mm and over are to be protected with wood or plywood
discs or flanges together with straw rope and hessian wrapping.
Unless higher pressure ratings are required for the pipelines non-return
valves shall have a pressure designation of 10 bar which shall be marked on
the valve body. Unless detailed to the contrary to suit existing pipework,
flanged valves shall have their flanges to a pressure of 10 bar and be drilled
accordingly. The face to face lengths of the valves shall be either 2 x ND +
100 mm or to an approved international standard, the longer length to be
allowed for in all cases using make up pieces where necessary to achieve
the required lengths.
All valves shall be clearway, and lugs provided on screwed seats, etc., for
assembly purposes shall be removed.
Valves shall be provided with a removable cover on top of the body casting,
to enable the hinge and door to be inspected or removed.
The door opening shall be restricted to a maximum angle of 700 at the
hinge, measured from a plane passing through the hinge at right angles to
the axis of flow. Valves shall be provided with extended door spindles fitted
with lever arms suitable for balance weights.
There shall be enough space between reflux valve and the wall of the valve
chamber so that the valve spindle could be withdrawn to the sides for
repair/maintenance of swing door without removing valves.
Unless higher pressure ratings are required for the pipeline, gate valves
shall have a nominal pressure designation of 10 bar which shall be marked
on the valve body. Unless detailed to the contrary to suit existing pipework,
flanges shall have a nominal pressure designation of 10 bar and shall be
drilled accordingly. The face to face lengths of the valves shall be in
accordance with an approved international standard.
Where resilient seated gate valves are detailed the valve bodies shall be
cast iron. The gates shall be of cast iron and wedge pattern with nitrile
rubber covering and with inside screw non-rising stems of stainless steel or
forged bronze. They shall have a seal of nitrile rubber ‘O’ rings to an
approved international standard.
Actuator operated valves larger than 300 mm dia. shall have copper alloy
faced guides and slippers. 300 mm dia. and smaller actuator operated
valves installed other than in a vertical position shall have machined guides
and gates.
Unless higher pressure ratings are required for the pipeline, or otherwise
indicated in the Contract Documentation air valves shall have a nominal
pressure rating of 10 bar which shall be marked on the valve body and shall
be designed for a liquid temp. of 500C and air temp. of 700C.
Air valves for pumped pressure pipelines shall be the special high pressure
‘Dual’ large orifice type. The following shall be used as a guide for the
general sizing of large orifice air valves :-
* For larger mains air valves may be fitted in clusters of two or more
as required.
For other duties, such as distribution mains single, small orifice type
standard air valves having a nominal 25mm male thread inlet and with a ball
size of 100 mm shall be used.
The test pressure for different components of the air valves shall be as follows:-
Ball/Guide : Polypropylene
All components shall be highly resistant to corrosion due to sewage and very
high concentrations of H2S and other gases. All internal components shall be
strong in design and of stainless steel comply with AISI grade 316.
The access cover for air valves shall be in such a position that the valves could
be easily removed for repair/maintenance.
The siting of the air valves shall be at locations shown on the drawings, as
recommended by the pipeline surge analysis or as decided by the Engineer on
site.
The valve shall be suitable for operation based on the ejector principle
utilising a ball as the closing device or shall be suitable for operation on AC
supply.
The material of construction for the flush valve shall be of cast iron to an
approved international standard.
Flap valves shall be designed for a nominal pressure rating of 10 bar which
shall be marked on the valve body, and a liquid temperature of 500C.
All cast iron surfaces shall be cleaned by grit or shot blasting to be free from
grease, then coated as specified for the environment. Hinge pins and
mating surfaces shall be smeared with grease.
Hinge pins shall be of stainless steel and all flaps shall be double hung and
seated off the vertical.
19.4 PUMPS
The fluid velocity at entrance to pump impellers shall not exceed 3.6 m/s for
pumps with suction pipework larger than 200 mm dia. nor 5.5 m/s for smaller
pipework. The fluid discharge velocity shall not exceed 3.6 m/s for all
pumps.
Pump bodies, covers, brackets, bearing housings, wearing plates, eye rings,
support brackets, etc., shall be manufactured from close-grained cast iron or
nickel iron.
Impellers shall be of best quality close-grained cast iron or nickel iron for
sewage pumps and stainless steel grade 316 or equal for storm/groundwater
pumps.
Shafting shall be of stainless Steel comply with AISI grade 316 or equal of
adequate size to avoid the possibility of fatigue failure. The duty speed
range shall be well below the first critical speed. At any change in diameter
of the shaft the shoulder shall be generously radiused to reduce stress
concentration.
Special pumps (ie. those for which the impeller is specially trimmed or
otherwise designed) shall be tested to prove the duty/guarantee point and to
develop Quantity/Head, Quantity/Power, Quantity/Efficiency curves for the
pump at operating speed, or if the pump is multi or variable speed, at
maximum and minimum speeds.
Submersible pumps shall comply with the General Requirements for Pumps.
Stainless steel lifting frames or eye bolts shall be fitted to casings for
connection of lifting chains.
Motors shall have IP68 protection and be continuously rated for use both
when submerged in sewage or storm/ground water at ambient temperature
and when in air. Motor windings shall be fitted with normally closed
thermistors complying with relevant specifications and providing protection
when the pump is running.
Two mechanical seals shall be fitted on the shaft between the electric motor
and the pump impeller. The space between these two seals shall be oil
filled.
Discharge bends shall be of close grained cast iron or stainless steel and
shall provide both pump support and lower guide rail/rope location. The
pump discharge connection system shall be designed so that the weight of
the pump provides a clamping force. Sealing between the pump and bend
shall be achieved by the weight of the pump and there shall be no leakage at
the joint between the faces.
Mounting brackets for the pump shall be comply with AISI of Grade 316
Stainless Steel.
Guide rails and holders shall be manufactured from stainless steel comply
with AISI grade 316 rigidly supported at both ends. Alternatively stainless
steel guide wire arrangement with stainless upper guide holder may be
used.
Lifting chains shall be of stainless steel and shall include shackles for
connection to pump lifting points. They shall be at least 1.50 m longer than
the guide rails.
The lifting chain shall be fitted with a stainless steel tag detailing the safe
working load, the test load, the date of testing and the name of the testing
authority.
Pressure gauges for use with sewage and sludge shall be Bourdon gauges.
The pressure transmission system shall be of the air-filled or oil-filled sealed
type incorporating reinforced plastic or stainless steel capillary tubing and
diaphragm transmitter.
Gauges shall be graduated in metres of water and bars gauge, together with
vacuum where appropriate. The accuracy of the system shall be ± 1.50% of
range or ± 2.50m bar.
The gauges shall not be connected to air release pipes or auxiliary suction
pipes.
The face shall have a warning label marked in red “IMPORTANT - TURN
OFF WHEN NOT IN USE” both in English and Arabic.
Centrifugal Fans to be used as air blowers shall be of heavy duty, single inlet
direct drive type. They shall be suitable for handling temperature upto 800C,
dust free air, and aggressive gases and moisture normal to the sewage
environment. The fan shall be low-noise, explosion proof and corrosion
resistant.
The blower shall be designed to handle, as a minimum, the rated air volume
against the stated head, as indicated in the Contract Documentation.
General Construction
The fan shall have a backward curved centrifugal impeller which shall be
overhung on the motor shaft.
The enclosure shall be U.V. resistant, have high impact resistance, high
abrasion resistance, low sound absorption dB 10-15 in the 100 - 500 Hz
range, low thermal conductivity of 1.4 W/m2 0C and be non combustable.
Unless otherwise specified all supports, fixing bolts, screws, etc., and other
fixings shall be provided, shall be stainless steel comply with AISI of
minimum Grade 316 and shall be as follows;
i) Threaded and fitted with 3mm thick washers beneath bolt and nut. The
length shall be such that when tightened down with a nut & bolt the
threaded portion will not protrude more than half a diameter of the bolt.
iii) AISI Stainless steel grade 316 shall be used for construction of pumps,
fastening galvanised or aluminium alloy components, holding down
and anchor bolts.
Not withstanding the above, the Contractor shall consider galvanic corrosion
between various metals when selecting materials for proposal.
The machinery shall be aligned, levelled and pulled down by the nuts of the
holding down bolts with a spanner of normal length. No grout shall be
applied until the machinery has been run and checked by the Engineer for
stability and vibration.
All necessary supports, saddles slings, fixing bolts and foundation bolts shall
be supplied to support the pipework and its associated equipment in an
approved manner. Valves, meters, strainers, and other devices mounted in
the pipework shall be supported independently of the pipes to which they
connect.
19.10 PENSTOCKS
19.10.1 General
Fixings shall be of the drilled anchor type and made of stainless steel.
All penstocks shall be suitable for an on/off seating head of 10m minimum
but in no instances shall be less than 1.5 the maximum working head.
(iii) Plastic
The frame, doors, sealing faces and spindles of each type of penstock shall
be as specified in the appropriate clauses herein.
Handwheels shall have the works “To open” and To close” in Arabic and
English with arrows indicating the direction of rotation cast on them. The
direction of closing shall be clockwise and a vandal/weatherproof, clear
polycarbonate tube cover shall be securely fitted to protect the thread of
rising spindles. The tube shall be clearly and permanently engraved to
indicate the position of the penstock.
Spindles shall have machine cut robust trapezoidal or square form threads
as necessary. They shall be of stainless steel. Extension spindle coupling
shall be of the muff type and they shall be drilled and provided with a
stainless steel nut and bolt for securing the spindle to the penstock spindle
head which likewise be drilled to take the bolt.
Off seating installation: - 30 litres per meter of slide perimeter per hour.
The slide perimeter shall be measured as the total length of contact faces
between the gate and frame in the closed position.
The frames, doors and stems guides for iron penstocks shall be made from
austenitic Ni resist iron. The penstocks shall be designed so as to ensure
tight closure while maintaining freedom of door movement during operation
and minimising sliding wear of the sealing faces. They shall incorporate
adjustable wedges manufactured from a material that shall not be
susceptible to corrosion.
Non-ferrous metal strips shall be fitted to the frame guides and gate.
The frames and doors of stainless steel penstocks shall be comply with AISI
of Grade 316 S31. The design of the doors shall be such that the required
working pressures can be withstood without deflection or distortion that
would affect the operation of the penstocks. Any strengthening of doors by
the provision of ribs and gussets shall be carried out by welding and not by
bolting.
The side sealing faces may consist of simple metal to metal contact between
the door and frames or by synthetic rubber seals and plastic guides as
necessary to withstand the required working pressure without leakages.
The doors of plastic penstocks shall be made from sheets of approved rigid
cellular polymer sandwiched between sheets of approved rigid compressed
composite plastics. The linear coefficient of thermal expansion of the
material shall not be greater than 1.6 x 10 per oC. No PVC or GRP
materials shall be used. The doors thus formed shall have sufficient
strength to withstand the required working pressures without deflection,
distortion or that would affect the water-tightness of the penstocks. Totally
enclosed steel matrices shall be incorporated in the door construction to
ensure adequate rigidity.
The sealing faces and side guides shall be to the approval of the engineer
and shall consist of plastic strips having a high resistance to sliding wear
and a coefficient of friction of less than 0.10. The sealing strips shall be
securely fixed to the inner faces of the frames and shall incorporate
removable stainless steel adjusting devices.
All plastic materials shall be non toxic ultraviolet stabilised and shall have fire
resistance in accordance with an agreed internationally approved standard.
19.10.5 Actuators
Where electric actuators are required for valves or penstocks they shall
comply with the requirements of Section 18 the Electrical Specification.
The gantry joists and rails shall be provided with provision for jointing and fix
to the structure. The lifting capacity of the apparatus shall be sufficient for
the heaviest load which will be obtained when erecting or dismantling the
plant or other parts of the installation. The capacity of the cranes proposed
shall be stated in the equipment supply schedule.
The crane shall be tested at the makers works at 25% above the rated load,
and test certificates shall be provided.
The crane shall be of the double girder travelling type. The traveller carriage
shall run on bridge rails which shall be securely fixed to the gantry.
The crane shall be provided with a maintenance platform over the full span.
The maintenance platform shall be provided with double handrails
throughout and a fixed ladder access.
Longitudinal and traverse motions shall be provided for the crane and shall
be such that operation is speedy without impairing safety in working. The
hook and load chains shall be such that the hook will reach to the maximum
depth.
Ball or roller bearings shall be employed on all motions and the load hook
shall revolve on a ball swivel. All gears shall be machine cut and all runway
wheels machined.
Two hoist speeds shall be provided, not exceeding 3 m/min across the
working range of the crane. Cross travel speeds shall be approximately 15
m/min. All motions shall be electrically driven. The speeds of all motions
shall confirmed in the appropriate schedule the speeds on all motions.
The load shall be carried on a flexible steel wire rope coiled onto a cast iron
barrel having right and left hand machine cut spiral grooves to ensure a true
vertical lift. The load rope shall be of sufficient length to reach the maximum
depth. The load hook shall comply with an approved international standard
and shall revolve on a ball swivel. A safety catch shall be fitted to the hook.
The power supply to the hoist shall be of festooned cable type running on a
rigid support system. An earth conductor shall also be provided.
All motors and electrical equipment shall be rated in accordance with the
climatic and other Specification requirements.
The integrity of the hermetic seal to the box girders is to be maintained. All
cables shall be enclosed in a steel conduit which is to fastened to the
exterior of the girder.
A close lift, hand operated gear driven lifting block, on a single runway
beam, shall be provided when specified in the Contract Documentation. The
Safe Working Load of block and beam shall be at least 25% above the
weight of the heaviest item which will require lifting for maintenance
purposes. Equipment shall have the following minimum ratings: 500 kg for
the hoist and 1000 kg for the beam.
The whole assembly including beam, gear driven travelling trolley, pulley
block and chains shall be subject to a capacity test carried out on site by an
approved independent body. The proof load applied for certification shall be
50% in excess of the Safe Working Load (SWL) shall be clearly marked on
the lifting block and on the runway beam. The test date is to be displayed on
the runway beam.
The bottom block shall be of the steel fully swivelling type with a safety catch
fitted to the hook.
ASTM C418
BS 466
BS 476
BS EN 10088-1
BS EN 1561
BS EN 837-1
BS 2061
BS 2374
BS EN 681-1
BS 2573
BS 2853
BS EN 1677-5
BS EN 13157
BS EN 13853
BS 3499
BS 3532
BS 3643
BS EN 14020
BS EN 1092
BS EN 12334
BS 5163
DIN 1690
DIN 1691
ISO 5752
ISO 5996
20.1.2 Steel
(2) Resins
(3) Curing
Curing systems shall be in accordance with the Resin Manufacturer's
recommendations. The manufacturer of the laminate shall
demonstrate that the laminate has been adequately cured prior to its
acceptance at the laminator's works.
(4) Reinforcement
(a) 'E' type glass chopped strand mat reinforcement shall be to the
approved standard and shall be to a maximum unit weight of 600
gm/m2.
(b) 'E' type glass woven roving fabrics shall be to the approved
standard and shall be to a maximum unit weight of 800 gm/m2.
(c) 'C' type glass veil (or synthetic fabric veil, where use is agreed by
the Engineer), shall be used to reinforce all surface sealing resin
layers on laminates.
(d) Use of 'ECR' Corrosion Resistant glass will be permitted.
(6) Moulds
(c) Chopped strand mat layers shall have a resin content of between
65% and 75% by weight.
(d) Woven roving glass fabric layers shall have a resin content of
between 40% and 60% by weight.
(e) Where edges of laminates are cut or exposed these shall be
sealed with a continuous layer of fully cured resin.
(f) Bisphenol or vinyl ester protective layers to
isophthalic/terephthalic laminates, shall be applied with a 'C' type
glass veil (or synthetic fabric veil) reinforcement after hardening
of the substrata. When this has sufficiently cured to prevent
movement, a continuous flow (top) coat of bisphenol or vinyl
ester resin shall be applied and fully cured. In such cases it is
anticipated that an appropriate paraffin wax additive will be
required to prevent air inhibition of the surface.
(8) Samples
(a) The following tests for inspection and quality control shall be
carried out:-
(1) The laminate shall be fully cured and shall show full
resistance to a commercial acetone sensitivity test.
(b) Resin burn off tests shall be performed on cut-outs, where no such
cut-outs exists the Engineer reserves the right to have 50 mm
diameter cut-outs for checks to be made on local glass
reinforcement content. The tests shall be conducted in accordance
with the approved standard and the result shall define glass
content.
(d) Where a laminate has been designed to take bolts in the make up
of the structure tests for bolt bearing strength shall be performed.
Bolt bearing strength tests shall be performed in accordance with
the approved standard.
(h) All the tests referenced in (a) to (f) above shall be witnessed by the
Engineer or his Representative unless waived in writing by the
Engineer.
Ladders and safety hoops shall be manufactured from either stainless steel
or glass reinforced plastic, as specified in the contract documentation.
dia. at the ends and rivetted over. They shall be spaced at 225 mm centres.
The ladders shall be provided with fixing brackets or the ends of the
stringers shall be turned over to form fixings. The fixings shall be drilled for
16 mm diameter bolts.
All fixing brackets, screws, bolts and nuts, etc. shall be SS comply with AISI
grade 316 S16.
Open mesh and chequer plate flooring shall be of mild steel, aluminium or
reinforced plastic as specified in the Contract Documentation.
Unless higher loadings are called for floorings shall be designed to take
pedestrian loading based on a central point load of 100 kg under which the
deflection shall not exceed span/200 for metal flooring and span/100 for
reinforced plastic flooring. Reinforced plastic flooring shall have a non slip
tread surface.
Unless a higher grade of protection is detailed all mild steel flooring shall be
hot-dipped galvanised after fabrication.
Heights of rails, overall dimensions and details of the bases for the
standards, fixing bolts and any other special requirements relating to the
guardrailing are shown on the drawings.
Heights of rails, overall dimensions and details of the bases for the
standards, fixing bolts and any other special requirements relating to the
guardrailing are shown on the drawings.
The Tenderer shall submit detailed proposals for the effective control of
odours emitted from wet wells.
A warning light of the flashing beacon type shall be placed at the entrance to
the wet well which shall operate if the system fails. It shall operate on the fail
safe basis and additional signage is to be provided warning operators not to
enter if the flashing/warning light is illumated. Safe working practices shall
be followed before any entry. A notice shall be placed underneath the
warning light and shall read as follows:-
DANGER
VENTILATION FAILURE
DO NOT ENTER WHEN THE RED LIGHT IS FLASHING
20.3.2.1 General
The odour control plant shall comprise a rechargeable activated carbon bulk
plant with pre-filter as follows:-
The filter media shall be activated carbon and must be effective in dealing
with odours arising from concentrations of Hydrogen Sulphide gas.
The Contractor shall state the expected life of the activated carbon and
guarantee sufficient supplies for five years of operation.
The activated carbon shall be suitable for insitu regeneration by water wash.
For which all necessary equipment shall be provided.
Extract fans shall be provided as necessary in the system prior to the main
filter to transfer foul air as described previously.
Each fan shall be of the multi-vane centrifugal type and fabricated from
stainless steel comply with AISI Gr. 316 S31
20.3.2.6 H 2 S Monitor
H2S Monitor for deodorising plants shall be of the "sensitised pad" type
enclosed in a factory manufactured clear UV protected housing mounted in
a clearly visible location on the filter media housing. The sampling point shall
be in the air stream just above the carbon bed level such that it detects the
level of H2S that is emitted from the filter.
The sensitised pad shall change colour relative to its exposure to H2S. A
colour chart with H2S (ppb) graduated against time (min) shall be supplied
for comparison.
20.3.2.7 Ductwork
Obtrusions to air flow with the exception to dampers, vanes, splitters will not
be accepted.
All joints, fittings, support etc. shall have all sharp edges removed.
Where ductwork passes through ceilings, roofs, walls etc.; purpose made
vermin proof fittings are to be used.
Ducts in close proximity to walls and ceilings shall be mounted in such a way
as to exclude vermin runs.
The external noise levels due to the operation of the ventilation equipment
shall be unobtrusive at all times.
20.3.2.8 Filters
Flexible joints shall have the effective cross sectional area as adjoining
ductwork or fan housing and shall be manufactured from material with a 15
minute fire penetration time.
20.4 VENTILATION
20.4.1 General
Ventilation equipment shall be supplied and installed for the areas specified.
The noise level due to ventilation equipment shall be no greater than sound
power level 65 dB(A) re 10-12 watts.
All inlets and outlets through the roof shall be fitted with approved GRP or
Aluminium cowls and bird screens. All inlets and outlets through walls shall
be fitted with sand trapped de-mountable aluminium louvers. All materials
used for external fittings shall be highly resistant to ultra-violet light
degradation.
All louvers shall be of the sand trap type and shall be fitted with internal
sand filters and mosquito screens.
Extract fans shall be roof, wall or duct mounted electric motor driven axial
flow type. They shall be complete with weather protecting cowls of GRP or
aluminium if mounted externally, and any necessary ductwork.
Extract fans shall be sized to provide the minimum number of air changes
per hour for the area specified:-
Toilets 12
Stores 6
Workshops 15
Motor Room 10 - 20
Ventilation equipment shall provide 20 air changes per hour to the dry well
area.
The system shall operate on the principle of forced draught outlet/ natural
ventilation inlet via the stairways and other apertures.
The system shall operate on the principle of forced draught outlet/ natural
ventilation inlet via inlet louvers. All inlet louvers shall be fitted with 50mm
thick metallic washable filters. Access shall be provided for cleaning/changing
filters.
20.4.6 Fans
Fans shall be of the axial flow or centrifugal types suitable for handling air of
high humidity and having concentrations of hydrogen sulphide.
All bearings shall be of the roller or ball race type and shall be sealed for life.
All motors shall comply with the requirements of the electrical section of the
Specification insofar as it applies.
20.4.8 Ducting
Ducting shall be complete with all necessary supports. Stainless steel nuts
and bolts shall be used for all ducting joints and all Supports and brackets
shall be galvanised except where otherwise specified. All supports, brackets
and fixings in wet wells shall be stainless steel.
Ducting shall be sized so that the air velocity within the ducts shall not
exceed 5.5 m/s.
Where ducts pass through walls roof or floor slab the gap shall be sealed
with a non degradable approved material.
Both fresh air and re-circulated air shall be filtered and the filter shall be
arranged for ease of removal from the main unit for cleaning and
replacement.
Depending on the size of the room space and the heat load therein, the air
conditioning units shall be of 1 ton, 1.5 tons or 2 tons refrigeration capacity
(equivalent to an air cooling capacity of 13,250; 19,880 or 26,500 B.T.U.’s
per hour) or multiples thereof.
1. Off.
2. Fan only with two speeds.
3. Cooling at two possible fan speeds.
4. Re-circulation of air from room, through unit and back to room.
5. Part re-circulation of air with some exhaust airflow.
6. Part re-circulation of air with some fresh air inlet flow.
Each unit shall also be fitted with an automatic delay timer in the
compressor control circuitry to prevent the compressor having to start
against gas pressure in the event of an interruption in the power supply or
the cooling mode being switched off and on rapidly.
Supply and return air ducting shall be run in the void above the suspended
ceiling where applicable. Air vents to conditioned areas shall be via slot
diffusers integral with the suspended ceiling. The whole system shall be
designed to give an even temperature distribution throughout the air-
conditioned areas.
Single package units shall be of the type with two compressors and split
coils arranged so that the failure of a compressor shall not lead to total
failure of the air conditioning to any area. The two units shall be identical to
limit the quantity of spares.
Condensate trays shall be fitted and the outlets piped to a suitable drain
point.
Fans shall have corrosion resistant steel impellers. Motors shall comply with
the relevant parts of the Specification. Anti-vibration mountings shall be
provided.
Air filters shall be fitted having 90% efficiency. If they are of the throw-away
type a five year supply of spare elements shall be provided.
The coils shall be pressure tested to 20 bars and fins shall be permanently
bonded to them.
Motors shall be weatherproof and shall comply with the relevant parts of the
Specification.
High and low pressure switches and overload protection shall be provided
and also an anti-recycling timer.
The units shall be sized to maintain a dry bulb temperature of 26oC and a
relative humidity of between 40% and 60% when the external shade
temperature is 52oC and the external relative humidity is 50%.
20.6.1 Application
The engine and alternator shall be mounted upon a purpose built one piece
robust rolled steel fabricated baseframe which shall be provided with lifting
lugs complying with an approved international standard. Steel support
channels shall be cast into the concrete base slab to which the base frame
shall be bolted. Jacking points and dragging points shall also be provided.
The Contractor shall supply the first fill of lubricating and fuel oil as well as
any necessary consumables for testing.
Rated for kW loading of the applied load with consideration given to sizing in
such a way that it is not subject to running for long periods of time under
light loading.
The engine shall directly drive the generator with the coupling arrangement
being flexible. A flywheel shall be fitted to ensure stable operation. Means
shall be provided for manual barring of the engine for maintenance
purposes.
Remote alarm contacts, where referred to, shall be voltage free SPDT
suitable for 1 amp at 24 V DC/220 V A.C.
The lubricating system shall be of the closed circuit type suitable for fast
automatic start of the unit. The oil shall be pumped round the oil circuit by
an engine mechanically driven pump having a suction strainer and the oil
system shall not require priming prior to starting the engine.
The oil pump shall have associated with it a pressure regulating valve and a
separate over pressure relief valve. Large capacity dual filters with auto
bypass shall be fitted immediately after the oil pump. The filters shall be of
the replaceable type. Each filter shall be fitted with a pressure gauge and
drain cock. The oil cooler shall use the coolant of the engine cooling
system.
Dial type gauges showing the oil pressure and temperature after the filters
shall be provided.
This shall include a fuel tank with the necessary mounting brackets, and
pipework (including a flexible connecting pipe if the tank is not engine
mounted). The tank shall be of sufficient capacity for 8 hours continuous
operation or as specified at full load and shall be complete with a fuel shut
off valve, a dial type level indicator, minimum and maximum level switches
having SPDT contacts suitable for 24 V DC/220 V A.C. at 1 amp (for filling
control and alarm), a protected vent, an overflow connection and a plugged
drain valve.
A fuel feed pump driven from the engine shaft shall be provided, together
with a hand priming pump, also dual filters and a drip tray to collect any fuel
spill or leakage. The drip tray to have a drainage cock and flexible draw-off
pipe.
A dial type gauge showing the pressure after the filters shall be provided.
The radiator shall be sized to allow for the ambient conditions and the plant
layout at 110% of the engine full load rating.
The coolant system shall include at the highest level in the system a volume
capacity either in the upper part of the radiator or by a separate header tank
to allow for coolant expansion and make-up. A coolant level indicator shall
be fitted.
Each plant set shall be complete with all exhaust pipework including
stainless steel flexible exhaust piping or stainless steel bellows pieces from
the engine and suitable silencers either mounted above the engine or
complete with the necessary brackets and hangers for supporting from the
enclosing structure.
The exhaust system shall be complete with all pipework, fittings and
mountings to carry the exhaust gases away from the enclosing structure. All
pipework within the enclosing structure shall be provided with efficient
lagging.
The engine exhaust system shall be fitted with temperature indicators at the
outlet of each cylinder block manifold arranged so that the indicators may be
satisfactorily observed from floor level.
Means shall be provided for electrical remote control of the speed over a
range of +5% of the normal speed.
After receipt of the starting signal, the starting system shall carry out all
sequential operations necessary to drive the unit up to normal voltage and
frequency. In the event of failure to start on the first starting control signal,
the system shall automatically initiate the starting sequence two further
consecutive times with the appropriate time spacing. Should no result be
obtained the system shall prevent further starting attempts and actuate a
circuit to provide a 'Failure to Start' alarm.
An engine shut down solenoid shall be fitted, this shall be of the "energised
to run type" for operation from the engine control system battery. An
emergency stop push button shall be provided.
Stopping shall be attained by interrupting the shut down solenoid circuit and
this shall also cancel any outstanding repeat start attempts.
The interconnecting cables between the starting battery and the engine
starter shall be provided.
The battery used for electric starting may also be used to energise the
diesel plant control system but shall have enough capacity remaining after
three engine start attempts to energise the control system continuously for
24 hours.
The following safety devices shall be fitted and arranged to stop the engine:-
All wiring associated with the engine shall be insulated with heat resistant
type insulation to an approved international standard for use at temperatures
of up to 85oC 600/1000 volt grade. Conductor section shall be stranded and
to suit the currents involved at the ambient temperatures arising but not less
than 1.5 mm2 excepting special types such as compensated or screened
cables.
All wiring on the engine (excluding starting cables) shall be brought out to a
common shielded terminal board mounted on the engine. Starting cables
may be connected directly to the items concerned on the engine.
The output shall be suitable for the load after the alternator has provided for
its own auxiliaries, and shall have an overload capacity of 10% for one hour
at the ambient conditions.
20.6.14 Alternator Construction
The frame of the alternator shall be fitted with lifting lugs or eye bolts to an
approved international standard.
Main terminal boxes shall be mounted on the alternator and shall contain
both phase and neutral terminals. The neutral end of each phase shall be
brought to a separate neutral terminal to facilitate testing of the windings
and a neutral link bar provided. The terminal box shall meet the
requirements of an approved international standard.
Provision shall also be made for manual adjustment of the regulated output
voltage over the range of 10% above and 10% below the normal specified
voltage.
The panel shall be constructed generally as described for FBA’s and shall
be suitable for indoor installation in the ambient conditions separately
specified, its construction shall be such as to allow full accessibility from the
front and to be suitable for mounting against a vertical wall with no rear
access. Floor fixing bolts shall be provided.
The following shall be mounted on the front face of the panel at suitable
viewing and operating heights:-
7. Push buttons:-
The 'start' push button to be functional only when the control selector
switch is at the 'Local' position.
8. Lamp Indications:-
Important Instruction
The panel shall be designed and constructed such that a general electrician
with no electronics experience or knowledge and with the use of standard
multimeter type instrumentation only can carry out fault finding, maintenance
and repair work with the guidance of the Operation and Maintenance
Manual.
The control panel shall contain the following items:-
8. Wiring, as necessary, PVC insulated of not less than 1.5 mm2. copper
cross section, to an approved international standard, with
each conductor reference coded at both ends for identification Green
colour to be used for earth circuits only.
iii) Provided with a 480 mm diameter raised manhole with joint and 8 mm
thick bolted on cover.
v) BSTP connections shall be provided for fill, vent, outlet and drain.
Manual fuel transfer pumps shall be of the self priming diaphragm type with
detachable handle arranged to pump diesel fuel from the bulk fuel tank to
the day tank.
Provision shall also be made to pump fuel from the day tank to the bulk fuel
tank to empty the day tank for maintenance purposes.
Fuel transfer pumps controlled by a float type level switch in the day tank.
Overflow back to the bulk fuel tank to be provided to guard against float switch
failure.
Mesh type filters not coarser than 120 mesh to be provided on the draw-off
line.
Free-fall fire shut-off valves to be fitted operated from the local fire alarm
system (where applicable) or a wire rope and heat sensitive fusible link.
Daily service tank to accommodate fuel for 8 hours running at full load.
20.6.26 Enclosure
Where specified the diesel generator shall be housed in a purpose built GRP
enclosure as follows:-
In all cases the maximum sound level shall not exceed 85dbA at 1m radius
from the generator and/or enclosure.
20.7.1 General
Manual fire alarm call points shall consist of a die cast plastic cover locked in
position with screws. The enclosure shall house a micro switch. The micro
switch plunger shall bear onto an inset break glass panel fixed into the cover.
The call point shall be arranged for surface mounting. The cover and the
enclosure shall be self coloured red. The words “BREAK GLASS FOR
ALARM” shall be printed on the frangible glass. A testing facility using a
special key shall be provided to enable the call point to be tested without
breaking the glass and the frangible glass shall be covered with plastic film to
prevent injury when the glass is broken. The mounting height shall be 1500
mm above finished floor level.
The switching unit contacts shall be gold or silver plated or an alloyed metal
which will not corrode when left unattended in a highly polluted environment.
Contact blades and other metal parts of the switching unit shall also be
constructed from plated or alloyed metal which will not corrode when left
unattended. Contacts shall be normally open or normally closed to suit the
alarm monitoring system. The voltage and current rating of the contacts shall
be marked within the enclosure.
The call point shall be resistant to the ingress of dust and water, and shall be
suitable for operation in the environmental conditions at the site of
installation.
20.7.3 Optical Smoke Detector
An operation indicator lamp of the light emitting diode type and a time delay
unit to override spurious alarms shall be fitted to the base.
The fire alarm panel shall be wall mounted adjacent to the motor control
centre. The fire alarm system shall protect risk areas within the premises by
giving warning of a fire condition relayed by an automatic detector or by the
operation of a break glass callpoint. Operation of an individual detector is to
be displayed by an indicator fitted into the base of the detector. This indicator
will illuminate when its detector goes into alarm. Fixed temperature heat
detectors will not have this local indication facility. Upon receipt of an alarm,
the control units shall perform the following actions:
Reset of the controller, after the fire incident has been investigated, will be
achieved by operation of the “Reset” switch.
The enclosures of the panels shall be fabricated from sheet steel, minimum
thickness 1.5 mm and shall be provided with a hinged lockable door.
Protection to an approved international standard shall be provided.
Alarm indicators shall be of the light emitting diode type. Indicators shall be
provided in pairs for each function.
Alarm panels shall continuously monitor all alarm circuits, including wiring and
control devices. When a fault monitoring circuit has been energised it shall not
reset until the fault condition is cleared.
Batteries shall be of the sealed lead acid type and shall have a capacity
capable of maintaining the system in normal working condition for at least 24
hours without recharging and subsequently to operate in the alarm condition
for at least one hour.
Monitoring circuits shall utilise solid state components. Output relay contacts
shall be gold or silver plated and shall be rated for the circuit conditions into
which they operate.
Alarm bells shall be of the gong type with a minimum diameter of 200 mm.
They shall be continuously rated and be mounted 2200 mm above finished
floor level.
2.5 kg hand held CO2 operated for extinguishers and 4.5 kg hand held dry
powder type fire extinguisher, suitable for Class A, B and C fire risks,
flammable liquid, and fires from electrical sources. The extinguisher shall
comprise a light alloy or steel cylinder finished in blue epoxy resin fitted with a
controllable brass valve with pressure gauge or aluminum head cap for CO2
operated cylinders. Valves to be fitted with safety pin lever.
All equipment supplied shall be suitable for the high temperatures, humidities,
and dusty atmospheres experienced in Dubai, with a minimum jet range of 5-
7m discharging in approximately 15 secs.
All equipment supplied under this section shall be obtained from a company
regularly engaged in the manufacture and supply of fire protection equipment.
It shall essentially be a duplicate of equipment that has been in satisfactory
use for not less than five years prior to the bid date and be supported by an
approved service organisation capable of carrying out regular inspection and
maintenance of fire protection systems.
Fire extinguishing devices shall be clearly and indelibly labelled with clear
instructions for their use in English, Arabic and pictorial form.
20.8 ACCESSORIES
The Contractor shall supply and install where specified the items listed below:
a. FIRST AID BOX - wall mounted first aid box marked with a red
crescent and containing:
25 g cotton wool
1 nr bottle antiseptic
1 nr card or booklet giving simple instructions
The display may be switchable between the three modes. However, should
any one of the three gas hazards occur, a warning lamp shall light and an
audible alarm shall sound, irrespective of the position of the switch.
Due to the limited life of gas sensor cells, the cells in the detector or any spare
cells provided shall be less than 3 months old at the time of handover to the
employer. Each cell shall have its date of manufacture indicated on its cover.
The detector shall be provided with an extension tube 2 m long and manual
pump for sampling inaccessible places.
1 No. box to house above equipment, suitable for wall mounting and
labelled “Portable Gas Detector”.
20.10 SURGE
The Contactor shall be responsible for supplying suitable pumping plant and
surge suppression equipment (if any) to ensure that transient pressure surges
do not exceed the following limits:
b) greater than 50% of the pressure rating of pipes and fittings installed
on the pumping main.
These limits shall not be exceeded under any condition of normal working or
power failure.
The Contractor shall include for all necessary surge suppression equipment.
The equipment (if any) should be compatible with the characteristics of the
To confirm the results of his initial assessment, the Contractor shall instruct
the pump manufacturer to carry out a comprehensive pressure surge analysis
on the complete hydraulic pumping system under all operating conditions, and
submit three copies of a report and calculations on the surge in the system
within 3 months of contract commencement to enable surge suppression
equipment to be manufactured in time for delivery and installation if found
necessary.
BS 649
BS EN 55014
BS EN 12285-2
BS 2869
BS 3116
BS 4278
BS 4999
BS 5000
BS EN 286-1
BS 5266
BS 5304
BS EN 60079
BS EN 60947
BS EN 3P1-6
BS EN 54
BS 5472
BS 5501
BS 5514
BS EN 60445
BS 5839
BS 6746
BS 6899
This general specification includes many requirements that may or may not be applicable to the
particular Project. This specification shall be read in conjunction with the particular specifications; and
the requirements of the particular specification shall predominate in case of any difference.
Scope
The contract shall include for the complete supply of material, installation completion, testing,
commissioning and one year maintenance of the existing and proposed irrigation system
summarised below and as per this specification.
The work shall comply with the Dubai Municipality standards for material and quality of
workmanship.
1. Installation of primary distribution mains with fire hydrants, chambers, ducts, future
connections, etc.
2. Laying of Ducts for Mains, Sub-mains, Laterals and Control Cables and spare ducts for
current and future development under footpaths and roads.
3. Relocation of existing mains, valve chambers, as required.
4. Removing existing trees and shrub lines where it is affected by new road layout and close
co-ordination with RTA Horticultural Department representatives.
5. Excavation to foundation level for sweet soil filling including excavation of plant pits and
removal of unwanted excavated material.
6. Reinstatement of the affected areas as and when required during the progress of the
project.
7. Testing & commissioning of the system and demonstration of automatic operation.
8. Operation and maintenance of complete irrigation system for a period of one year after
commissioning of the system including trained operator and labours.
The Contractor shall include for all materials, labour, plant and tools and preparation of
detailed and co-ordinated shop drawings.
Note: All crossings across major roads/dual carriageways and U-turns shall be either through
ducts or no dig method, where required.
Backfilling and road base to be tested by an approved independent laboratory at least one
test per 100 mtr. interval or as per the request at specific location by the Client and by the
Engineer.
The Contractor to modify the existing manhole chambers; if required in order to match top
levels with the proposed landscaping levels.
The Contractor shall reinstate all roads and footpath where affected by the installation of
irrigation system to the approval of the engineer and the Client.
Refer to “Particular specification and relevant application of Administrative order No. 16 and
22 for Drainage, Sewerage and Irrigation Projects.” (Annex I).
The Contractor shall be responsible for maintaining the main irrigation system in the contract
area and for existing plantations.
c. Grass................................ 12 lit/m2/day
d. Shrubs & hedges.............. 15 lit/day
e. Ground covers, Flowers & creepers 12 lit/m2/day
The Contractor shall include for all materials, labour, plant and tools.
Contractor shall make the connections to effluent line, complete with all fittings (GRP tee, VJ
Flange adopters), valve chamber etc. to the approval of the Engineer. The size, placement
and orientation of Valve chambers etc. has to be in such a way that sufficient room for laying
other services are maintained.
All crossings across major roads/dual carriageways and U-turns shall be either through ducts
or no dig method.
It shall be done strictly as per DM specifications and to the Approval of the Engineer. Back
filling and road base to be tested by an approved independent laboratory at least one test per
200 mtr. interval and part thereof & 30 mtr interval and part thereof respectively or as per the
request at specific location by the Engineer.
The contractor to modify all the existing manhole chambers; in the proposed Landscape area
(if required); to the approval of the Engineer and the concerned service authorities; in order to
match its top levels with the proposed landscaping levels.
The contractor shall reinstate all roads and footpath where affected by the installation of
irrigation system to the approval of the engineer.
Refer to the attached “Particular specification and relevant application of Administrative order
No. 16 and 22 for Drainage, Sewerage and Irrigation Projects.”
The contractor shall be responsible for maintaining the main irrigation system in the contract
area and for existing plantations.
21.1 SUBMITTALS
The Contractor shall submit to the Engineer the following documentation for review and
approval, before commencing work.
All catalogue cuts, diagrams, samples, drawings and such other data as may be required to
demonstrate compliance with the specification.
Prior to start of any work at site the contractor has to approach all Service Authorities in
Dubai to get their no objection for the work included in this contract and a record drawings for
their existing services. Copy of these drawings and no objection certificate should be
submitted to the Engineer before starting the actual work at site.
Trial Trenches: Contractor to make detailed survey of project area, note existing levels
in the project area and take trial trenches for all the locations where plantation and irrigation
system has been proposed.
All these details to be submitted to the Engineer along with digital format.
Based on the information of existing levels and trial trenches made Contractor to propose
final location of tree plantation and irrigation services and submit shop drawings.
Please note that the contractor to make detail survey of existing levels in the contract area.
Trail pits should be taken at every 50 meter interval, mark all the existing services in reference
to the road edge & building line along with its depth from existing the ground level & the
proposed Landscape finish level. Contractor to check availability of all the existing ducts that
are marked on the tender drawings. Contractor to propose the route of Irrigation piping based
this information. All this information regarding trial pits, existing and proposed levels,
availability of existing ducts shall be made available to DM Engineer within
mobilisation period of the contract. All this information shall be made available on
hardcopy & in Digital format to DM as it is required for adjusting landscape and pipes/services
alignment.
Any delay to provide the above-mentioned information regarding trial trenches, existing
services & levels which affects the progress of works shall be the responsibility of the
Contractor. The Client/Engineer keeps the right to take necessary action and penalise the
Contractor in such circumstances.
The successful Contractor shall submit shop drawings, for approval by the Engineer, for the
following:
a) In case of any conflict between contract drawings and any existing or future services
which may necessitate re-routing proposed irrigation Main or laterals, the contractor has
to prepare the shop drawings accordingly and submit it to the Engineer for approval. This
should be considered as integral part of the contract.
d) Wiring diagrams including conduits, pull boxes, sizing and calculations to verify that cable
sizing is in accordance with DEWA regulations and equipment manufacturers
recommendations.
May 2017 Page 21/3
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
e) Electrical power and control wiring diagrams for irrigation controllers, field wiring and
grounding and CCU system including all decoders and interfaces.
h) Detail of valve chambers and any modification to the existing feeding chambers.
The approval shall not relieve the Contractor of any of his responsibility under the contract for
successful completion of the work.
The Contractor shall submit manufacturer's list of spare parts for approval prior to
commissioning any piece of equipment. Recommendations shall include stocking
recommendations, exploded assembly diagrams illustrating location and spare parts to be
utilized and all relevant operational data.
The Contractor shall submit his proposed work method statement for approval prior to
commencing work. The statement shall detail proposed sequence of work, hold points,
testing frequency and document control.
The Contractor shall submit a program of works as per the Clause 14 of the condition of the
contract for approval.
The Contractor also shall submit monthly progress report at the end of each month including
all the works constructed during the month with photographs, numbers of staff and labourers,
cash flow, test reports, overall progress and general details as per engineer approval.
At such time as the list of materials has been approved by the Engineer, the Contractor shall
provide four (4) sets of manufacturer's technical and maintenance literature to the Engineer.
Data sheets shall provide sufficient technical information to identify each product and shall
include the name and the address of the nearest supply firm, which should have a local
representative in the Emirates of Dubai.
A) AS-BUILT DRAWINGS
The Contractor shall maintain one set of contract drawings for the sole purpose of recording
accurate changes made as the work progresses ("As-Built" conditions) of the irrigation
system. All changes previously approved and all completed work shall be recorded on these
drawings.
The Contractor shall prepare as-built drawings clearly showing all location, depths, slopes,
heights, shapes and dimensions of all works as executed. All valve locations and piping shall
be dimensioned and recorded (except that wire locations, common to pipe ditches, need not
to be dimensioned). The Contractor must submit as-built drawings for all electrical
installations. The contractor should clearly mention location of lines, chambers etc. in
reference to building line and center line of the roads. The contractor must submit as built
drawings for all electrical installations.
Sizes of all the as-built drawings should be the same as that of DM Drainage & Irrigation
Department Standard (approx. 120cm x 60cm) size.
All as-built drawings should be prepared using Microstation program (latest version for
Windows). Mainline layouts to be on DM Survey sheets (scale 1:1000) as per Dubai
Municipality Drainage & Irrigation Department requirements and the Client approval. As-built
drawings of Mainline layouts of Automatic Irrigation system Main and Irrigation Network
Mains should be on separate drawings for each.
Contractor should prepare and submit as-built drawings for the pipeline profiles of the
Mainlines which are of size 6” and above. Pipeline profile drawings should be in Horizontal
scale of 1:1000 and Vertical scale of 1:100. Pipeline profiles to be submitted on separate
drawings with clear references to Mainline layout drawings marked on the same.
The Contractor to follow the Standards (regarding legend, line styles, colours, levels, size of
drawings etc.) of DM Drainage and Irrigation Department while preparing As-Built Drawings.
Chambers schedule are to be prepared indicating all relevant construction items and giving
co-ordinates for each manhole in compliance with DM grid system.
The Contractor must submit as-built drawings for all the electro-mechanical installations. All
the details of the installed equipments regarding manufacturer, model no., type, size. etc.
shall be provided in the legend of the drawings.
Pipeline profile drawings should be in Horizontal scale of 1:1000 and Vertical scale of 1:100.
May 2017 Page 21/5
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
Lateral line layouts for sprinklers/sprayers, drip and bubblers shall be in scale 1:500. All the
Layout drawings should be shown on background of light coloured Landscape as-builts, for
easy reference
The Contractor should follow the Standards (regarding legend, line styles, colours, levels,
size of drains, title block etc.) of DM Drainage and Irrigation Department while preparing As-
Built Drawings.
After final approval to the As-Built Drawings, Contractor to submit the following before the
final taking over of the project.
1) Three complete sets of “As-Built Drawings” folded properly and provided in plastic folders
as a part of Operation and Maintenance Manual;
2) A set of Mother Prints (on Heavy grade Polyester) and;
3) A copy of computer discs, CDs (with proper titles and plastic enclosure box) please note
that zip files will not be accepted.
Provisional acceptance will not be considered unless Contractor submits all the above said
As-Built Drawings.
Notes:
1) Contractor to check all existing irrigation system within the contract area (along with
existing filtration chambers) and shall record those details in the as-built drawings of the
project.
2) Contractor to prepare & submit the detailed records results of trial pits and trenches. All
such information shall be submitted to DM in digital format and hard copies.
3) Contractor to prepare and submit the detailed results of trial pits and trenches. Record of
all trial holes executed under this contract shall be made available in the form of drawings
(Scale 1:1000 for Plans & 1:100 for sections) to be the part of as-built set of drawings.
These drawings shall be made available to Services Co-ordination Unit of Roads
Department, RTA. All such information shall be submitted to RTA in digital format and
hard copies.
01 Assemble three (3) copies of manuals containing Operating & Maintenance instructions
for each piece of equipment and systems requiring service and Prints of As-Built
drawings as described above. O & M Manuals shall be bound in a hard cover 3-ring
binder of suitable size and properly indexed. Cover and Manual shall be as per DM
standards and to be approved by the Client. Contractor should also submit digital copy of
Maintenance Manual on CD.
a. Description of equipment
b. Operation of equipment
c. Maintenance of equipment and lubrication schedule
d. Servicing of equipment
e. Control Diagrams
f. Irrigation Valve Operation Schedule c/w Controller Station no., valve no., valve size,
flows, operating time, etc.
g. Diagrams of the system
h. Logic of operation of the systems
i. Valve charts
j. Performance characteristics: Curves and charts for equipment (Data shall refer to,
and identify specific modeling service and shall not be general advertising data).
k. Spare parts list
l. Names, contact numbers and addresses of spare part suppliers.
m. Test reports
n. Certificates
May 2017 Page 21/6
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
A digital copy (on computer CD) of Operation & Maintenance manual complete with
Valve operation Schedule, Circuit & control diagrams shall be submitted to DM along with
As-built drawings
03 Submit one copy of the manual to the Engineer for review and three final copies to the
Client after the final approval of the Engineer. Provisional acceptance will not be
considered unless Contractor submits completed O & M manuals and as-built drawings.
The apparent silence of the specification, drawings or other contract documents as to any
detail or the apparent omission from them of a detailed description concerning any point shall
be regarded as meaning that only the best general practice is to be used. All interpretations
of the specifications will be made by the Engineer on this basis.
During site visits by the Engineer, operation of the system will be delineated to all authorized
persons desiring such information.
Three copies detailed system operation and maintenance brochure will be provided to the
Client at the completion of the project by the Contractor.
The Contractor shall stake out the irrigation system in accordance with the scaled plans.
Staking shall be erected in such a manner as to insure permanency of the staked locations
until such time as the irrigation system is installed. Stakes shall be placed to show location of
valves, pipelines and control head. Stakes shall be flagged with bright flagging for ease of
location. All staking by the Contractor shall be subject to approval of the Engineer.
The Contractor shall stake the landscape patterns as shown on the landscape
drawings. These patterns shall be marked with lime powder and nylon ropes for future
use during plantation phase.
21.1.16 CLEAN-UP
During the course of construction, the Contractor shall remove waste material from the site
continually as is necessary to keep the site in an orderly manner. Waste material shall be
removed from the work site and not to be used as back-fill material. Upon completion of the
contract, the Contractor shall remove all waste equipment and parts and leave the site in a
neat and orderly condition.
21.1.17 WARRANTY
All work included under this Contract shall be warranted by the Contractor against all defects
and malfunction of materials and workmanship for a period of one year from the date of
completion of works. Should problems arise with the system during the warranty period, all
necessary repairs and/or replacements shall be made by the Contractor in an expedient
manner at no additional cost to the Client.
The Contractor shall be responsible for operation and maintenance of the system for a
period of one year from the completion date.
All products shall be delivered in the manufacturers' original protective packaging and shall
be inspected at time of delivery. Any product, which are damaged and not in accordance with
specifications, or date stamp expired, shall be immediately removed from the site and
replaced.
Evidence must be submitted to verify materials, such as uPVC pipes, solvent cement, rubber
gaskets etc., have been properly protected during transport and storage prior to delivery to
the site.
All products shall be handled and stored in accordance with printed recommendations of the
manufacturer.
All site storage areas shall be shaded at all time. Pipe stacks shall be designed to ensure that
pipes and especially pipe sockets are not deformed during storage and/or effected by
sunlight.
Precautions shall also be taken to protect items sensitive to sunlight or heat prior to backfilling
operation. uPVC pipes shall on no account be exposed to sunlight for more than two days in
summer, or one week in winter. Any pipe, whether installed or not, which is observed to be
sunburn, or oval, shall immediately be removed from the site and replaced.
The Contractor shall be responsible for operation and maintenance of the system till
the completion of End of Defects Liability period.
The Contractor will be responsible for operation, scheduling, and inspection of the system.
Contractor should be provide a skilled operator, a pipe fitter and a helper who are
experienced in widely varying irrigation requirements over various planting times and climatic
conditions for the optimal performance of the irrigation system. All these staff should be
available for full time on the site. Operating the system should be combined with the
instructions of the designer to formulate a set of standard operating procedures for the
system. During the planting and establishment time of the plantation Irrigation operation
should be provided as required.
Complete inspections are necessary during the operation of the irrigation system as follows:
Inspections of all the irrigation equipments line sprayers, sprinklers, Dripperlines, bubblers,
valves, pressure regulators, filters, pumps, flow/pressure sensors, fertiliser injection system
etc. should be done regularly during the operation of the system for their proper & optimal
operation. Each zone should be inspected for excessively wet areas that might indicate leaks
and dry patches which indicate improper coverage of the sprayers/sprinklers.
Driplines, and irrigation pipes should be inspected for breakages and attended immediately to
repair the same.
Arc and throw of sprayers and sprinklers should be inspected and adjusted in such way that it
will not throw the water on the roads and stems of the palm trees. All the pressure regulators
of solenoid valves should be adjusted to give the recommended pressures.
Filters and Basket Stainers must be inspected and cleaned periodically.
Scope
The scope of this section includes a description of materials and methods for the hydraulic
element of the system.
May 2017 Page 21/8
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
All materials covered by this specification shall be from an approved local representative in
the Emirate of Dubai qualified to provide the appropriate level of technical support.
All equipment, fittings and accessories shall be suitably rated to comply with the system
design and operating parameters.
Note: Following are general specifications of DM for the Irrigation materials, the items which
are not required in this project shall not be considered in the scope of the works.
All joints in pipe shall be made by solvent welding using adhesive solvent and primer as
recommended, in writing, by the manufacturer and approved by the Engineer. All cans of
solvent and primer shall have labels intact and shall be stamped with date of manufacture.
No cans dated over two years old will be permitted. No thinning of solvent or primer will be
permitted. Lubricant and solvent cement used to make joints shall be approved in writing by
the pipes manufacturer or his designated representative and the Engineer. Only male joints
may be used up to 2". Joints larger than 2" shall not be threaded. All threaded joints shall be
made up using PTFE tape or an approved equal thread sealant.
Pipes sized 1-1/4 " and larger shall be of class D (12 bars working pressure) and smaller
pipes shall be class E (15 bars working pressure). Fittings shall be fabricated from UPVC
according to BS 4346.
For sizes up to 6” uPVC fittings shall be used. All uPVC pipes and fittings should be covered
by licensed Kite mark. All uPVC fittings shall be of pressure ratings not less than 15 bar at 20
deg. Celsius and 9 bar at 50 deg. Celsius.
For sizes 8” and above; GRP fittings with 15 bar pressure ratings shall be used in
chambers.
On no account shall saddle and cross type connections be made to uPVC pipe. All pipes
passing through ducts shall be solvent weld joints.
Flange couplers shall be PN 16 and in accordance with BS 4504. Bolts and nuts (whether
part of the coupler or for fixing) shall be A4 – 70 stainless steel.
Threaded riser pipe used to support valves and sprinklers and fittings may be galvanized
steel, or brass. All galvanizing shall be carried out after threading.
The pipes shall be PN 20 rating with PE 100, SDR 9 for all distribution system. HDPE material
shall have density greater than or equal to 0.941 g/cm3. Pipes and fittings shall be
homogenous throughout and free from visible cracks, holes, foreign inclusions, blisters, dents
or other damaging defects. Joints are not acceptable. Material shall be uniform in opacity,
density, interior smoothness, and other physical properties. It shall have adequate resistance
to weathering and other ageing from outside storage for a minimum of two years after
manufacture.
If rework material is added or used, it shall be clean, derived from the same resin and
reground under the supervision of the same manufacturer and shall be compatible with the
material to which it is added.
The pipes and fittings shall be manufactured from HDPE containing only those antioxidants,
UVstabilizers and pigments necessary for the manufacturing of the pipes and confirming to the
requirements of this specification. This shall be suitable for butt fusion or electro fusion welding
techniques.
Any CONTRACTOR/ SUPPLIER shall follow manufacturer’s guideline for the applicability
of the material used. If required pipe manufacturers shall provide assistance and training. This
involves quality check of the material, handling of HDPE material, warehousing, preparation
for fabrication, selection of appropriate techniques and implementation of recommended
procedures, and testing of the components. Pipes shall be hydrostatically pressure tested
certified at the manufacturer's plant in accordance with ISO 1167.
As stated below, physical properties of the pipes and fittings shall be:
a) Made of high-density polyethylene (HDPE) and shall comply with the requirements of ISO
4427 PE 100.
b) The material used for the manufacturer of pipes and fittings shall be in accordance with
Table 1 and Table 2 of clause 4.4 of ISO 4427-1.
c) The minimum required strength (MRS) of the material compound shall be 10 MPa at 20º
C.
d) Hydrostatic strength of the material shall be in accordance with ISO 1167. It shall be more
than100 hours @ 20 0C on stress level: 12.4 Mpa for PE 100.
e) Lifecycle durability of 20 years is to be confirmed. The design temperature shall be 40º C.
f) The thermal stability of HDPE material shall meet the requirements of ISO 4427.
The pipe dimensions for water systems shall be based on standard dimensions according to
ISO 4427 and measured in accordance with ISO 3126. Straight pipe shall be supplied in
standard lengths measured at 23º C ± 2º C unless otherwise specified.
When viewed without magnification the internal and external surfaces of pipes shall be
smooth, clean and free from scoring, cavities and other surface defects. The pipe ends shall
be cut cleanly and square to the axis of the pipe. All HDPE pipes to be used for the
transmission and distribution of water shall be black and have purple stripes or according to
the national preference. The carbon black content in the compound shall be 2.25 ± 0.25 % by
mass when measured in accordance with ISO 6964. The dispersion of carbon black when
determined in accordance with ISO 11420 shall be equal to or less than grade 3.
The fittings shall be injection moulded or formed from material compatible to that of the pipe
and shall be as resistant to the external and internal environments as the other elements of the
pipe system. At locations where HDPE to metal connections are specified, slip-on flanged
connection is recommended along with HDPE stub-end (refer ISO-4427 Part-III and ISO 9624)
or special restrained transition fittings subject to approval by the CLIENT/ SUPERVISING
ENGINEER. The flanges shall be drilled to ASME B 16.5, as per the design requirements.
When viewed without magnification the internal and external surfaces of fittings shall be
smooth clean and free from scoring, cavities and other surface defects. The fitting shall be
blue or black and dimensions shall be measured in accordance with ISO 4427-3. Wall
thickness of the body of the fitting at any point shall be equal to or greater than the minimum
wall thickness of the corresponding pipe.
May 2017 Page 21/10
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
Straight lengths and coils of pipe shall have internally fitted end caps that prevent dirt and
debris from entering the pipe during handling, storage and transport. Caps shall be attached
by an approved method to prevent the accidental loss of the cap. All end caps shall have an
outer lip, which prevents the accidental insertion of the cap into the pipe. A method to permit
venting shall be provided in order to allow expansion of air due to temperature changes during
storage.
Steel pipe shall conform to API standard schedule 80 or other equal and approved. Welded
fittings shall be schedule 80 and weldneck. Flanges shall be in accordance with BS4504
PN16. All bolts, nuts and washers used for flange assembly or integral with bolted couplers
shall be stainless steel (A4 - 70).
All Pipes and fittings to be coated inside and outside by electrostatic fusion bonded
epoxy to average DFT 150 microns, or by fusion bonded plastic powder coating to
average DFT 500 microns.
Threaded steel pipes and fittings used for risers shall be hot dip galvanized mild steel class
(C) in accordance with BS 1387.
All G.I. & Steel Pipes and fittings to be coated, inside and outside with electrostatic
fusion bonded epoxy to average DFT 150 microns or by fusion bonded plastic powder
coating to average DFT 500 microns.
Any galvanized pipe installed in contact with the soil shall be wrapped with at least two layers
of an approved petrolatum impregnated tape of min. thickness of 1.15mm and applied with
50% over lap. The wrapping tape shall extend a minimum of 100 mm above the soil. Steel
piping and fittings shall only be installed above ground or otherwise specified.
Joints shall be threaded and sealed with PTFE tape or some other approved method.
Connections to the flanged equipment shall be via threaded flanged adopters. All bolts, nuts
and washers used for flange assembly or integral with bolted couplers shall be stainless steel
A4-70.
21.2.1.5 DUCTILE IRON PIPE AND FITTINGS
Ductile iron pipe and fittings shall be in accordance with BS 4772 or ISO 2531 and EN 498.
They shall be supplied by an internationally known and approved manufacturer. Ductile iron
pipes and fittings shall be supplied, stored, laid, back-filled and tested in accordance with CP
2010. The pipes shall not exceed 5.5 meters in length and push-in or flexible mechanical
joints shall be used unless otherwise stated.
Where flanged joints are used, the flanges shall be faced and drilled to PN16 as defined in
BS 4504, unless directed otherwise. Flanged joints shall be made with inside bolt circle
gaskets as described in BS 4865 part 1, and gaskets from plain rubber to BS 1737. Bolts
shall be stainless steel Grade A4-70, complete with nuts and washers. The threaded portion
of bolts shall be of such length that at least two threads shall protrude beyond the nut when
tightened.
Pipe barrels shall be class K9, tapers, bend and pipes with cast on flanges shall be class
K12, and tees shall be class K14.
The internal and external surfaces of all-ductile iron pipes and fittings shall be coated
according to one of the following methods:
All pipes and fittings shall have a resin rich inner layer, having a minimum thickness of 1.0
mm and a resin rich outer layer having a minimum thickness of 0.25mm incorporating one
layer of "C" glass. The remainder of the liner shall consist of at least one layer of 450 g/m
powder bound acid resistant chipped glass strand mat having a glass content between 25
and 30 % by weight.
All glass reinforcement shall be of the "ECR/Advantex" type. All pipes and fittings shall have
2
an stiffness of not less than 10,000 N/m and satisfy the requirement of ASTM D 3262-87.
Pipes shall withstand longitudinal tensile force of 100 N/mm of circumference. All the flanges
shall be PN16.
Pipes shall withstand longitudinal tensile force of 100 N/mm of circumference. All the flanges
shall be PN16.
All fittings (including bends, tees, reducers and flanges) used with AC pipelines shall be GRP
(glass fibre reinforced plastic) fittings and shall comply with the following specification:
.01 - General
This specification covers the design manufacture and testing of glass fibre reinforced plastic
(GRP) pressure fittings for use with Asbestos cement pressure pipe in nominal sizes 80mm
and larger. GRP fittings and pipe shall be designed and manufactured in accordance with
AWWA C 950-95 and the requirements herein. All components shall be produced by one
manufacturer.
The manufacturer shall be approved by Client and must demonstrate the experience and
capability to produce fittings of the same diameter and pressure range as those required. The
manufacturer shall be certified to ISO 9002 or BS 5750 Part : 2. Full range of fitting diameters
used for the project must be manufactured and delivered by the same manufacturer.
.02 - Construction
A structural wall consisting of continuous glass filament findings and/or woven rovings and
chopped glass reinforcement and may include fine fillers, all impregnated with Isophethalic,
Vinylester or Epoxy resin as required.
.03 - GRP fittings and flanges shall be designed in accordance with AWWA C950 for service at the
May 2017 Page 21/12
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
following conditions:
Flange X flange fittings shall be designed for installation above ground (in chambers) without
thrust blocks. Flange branches on Spigot Tees shall be designed to resist end thrust from
closed valves.
Spigot joints, where specified shall have the same outside diameter (OD) as approved by
Dubai Municipality for Asbestos cement (AC) pipe to which it is to be joined. The joint
dimensions and tolerances shall be equal to AC pipe spigots such that joint remains
watertight under all normal operating and surge conditions. The spigot ends shall be clearly
marked with a “homeline” indicating the proper insertion limit for the AC couplings. The spigot
width shall not be less than half the AC coupling joint width.
Flanged joints, where specified shall be GRP filament would flanged manufactured from
Epoxy or Vinylester resin and glass reinforcements. Flanges shall be flat faced and drilled to
BS 4504 PN 16 drilling pattern.
GRP Flange gasket (full face) design and thickness shall be as recommended by the GRP
fitting manufacturer. Hand lay-up flanges shall not be acceptable.
Laminated or Adhesive joints used in the fabrication of fittings shall be equal or superior in
strength to the sections they join. The thickness of laminated joints shall not be less than the
wall thickness of the adjoining pipe section. All hand laminations or windings shall utilize only
one type of resin throughout.
.05 - Dimensions
GRP fittings shall be produced in Metric sizes and shall be classified by their nominal inside
diameter (ND). The actual fitting inside diameter shall not be less than that shown in the table
below:
900 895
1000 995
1200 1195
All standard fittings up to and including diameter 300mm used in the distribution system shall
be filament wound on precision steel moulds. Standard 90 and 45 degree bends of nominal
diameter 300mm and smaller shall be of the smooth radius type, having a turning radius of
1.5 times the bend nominal diameter. Fittings diameter 350mm and larger may be of the
moulder or mitered (manufactured from GRP pipe sections) construction and internal
surfaces shall be finished smooth.
The thickness of GRP flanges shall not be less than shown in the table below:
The wall thickness of GRP fittings shall be determined by the manufacturer to meet the
design requirements of this specifications but shall in no case be less than the minimum
thickness shown in the table below:
1. Hoop Tensile Stress ASTM D2290 Portable 10 of AWWA C950 for class 250 psi
2. Axial Tensile Stress ASTM D 638 Portable 11 of AWWA C950 for class 250 psi
.08 Testing
1. Routine Tests
The following test shall be carried out by the GRP pipe/fittings manufacturer at the frequency
specified. Test results and certificates shall be submitted to the Engineer for each
consignment delivery. Witnessing of factory testing by the Engineer may be required. The
Client and the Engineer shall have the right to retain up to 2% of the material delivered back
to the factory for inspection and /or testing by their representative at no additional cost. Test
method shall be in accordance with AWWA C 90 5480.
Test Frequency
i. Visual Inspection Every item
ii. Dimensions Every item
iii. Hydraulic pressure at 24 bars Once per 10 Flg. x Flg.
for 30 seconds items
iv. Stiffness Once per 100 items
v. Barcol hardness (resin cure) Every item
vi. Axial & Hoop Tensile stress Once per 100 items
vii. All GRP pipe used for fitting fabrication shall be factory
pressure tested at 24 bars for 60 seconds.
a) Long Term hydrostatic design pressure of the GRP pipe or fitting shall be established in
accordance with AWWA C950 Section 2.4.2.
b) Short term hoop tensile strength shall be within the ultimate strength of the pipe fittings.
Laminated joints and flanged joints shall withstand a hydrostatic test pressure of 3.5 times the
rated working pressure with no signs of leakage or weep. For Flanges joints, the flanges shall
be blinded and the ends unrestrained during the test.
.09- Submittals/Drawings
Prior to start of production, the fittings manufacturer shall submit to the Engineer detailed
drawings of each fitting required for approval. Design calculations, samples and sample
testing may also required by the Engineer for approval at no extra cost to the client.
For flanged fittings, the manufacturer shall submit before delivery, the recommended gasket
details, the bolt torque sequence and maximum recommended torque for each flange shall be
supplied.
.10 - Markings
Each fitting shall be indelibly marked with the following:
.11 – Tangential Flanged Tee: this shall be used as Washout tee which shall have a bottom
tangantial flanged outlet. Tee shall be Spigot X spigot X Branch Flange. The size and the
configuration of the Tee shall be as detailed on the drawings. The detail of the product and
engineering data shall be submitted.
Dust cap should be fixed at the end of each 4mm tube to prevent insects and dirt from
entering the tube. The cap should be durable plastic and heat resistant.
All drip tubes shall be held on the soil by Staple stake. The stake should be polypropylene,
minimum 220mm long, durable and heat resistant. Tails of the stakes shall be provided with
integral barb type flaps to increase retention in soil. The drip line shall be hold on the soil by
the same length staple stake at 10 m interval. The stake shall be featured separated surface
to grip the drip line.
21.2.2 VALVES
Automatic remote control valves shall be of the sizes prescribed on the plan. The valves shall
be normally closed diaphragm type with slow opening and closing action for protection
against surge pressure. Actuation shall be by encapsulated type solenoids and rated 24
volts, 50 cycle unless otherwise specified.
The valve shall able to operate under very low flow and pressure conditions.
Construction shall provide for convenient access to functional parts without removal of valve
from system plumbing. A manual flow control adjustment, with shut-off capability, shall be
furnished on all valves. Valve pressure rating shall not be less than 200 PSI.
The diaphragm shall be of nylon reinforced BUNA-N rubber, and provide for a positive seal
between bonnet and body. The solenoid functional parts shall be of stainless steel, brass or
bronze for corrosion resistance. Diameter shall be as shown on plan. A mechanism shall be
provided for bleeding of the diaphragm chamber for manual operation. Valves shall be
fabricated from heavy cast brass or bronze. The valve shall be capable of working under dirty
(Treated sewage) water conditions. Inlet and outlet shall be threaded B.S.P.
All valves shall be provided with a pressure regulator capable of regulating downstream
pressure between 15 to 100 PSI (within an accuracy of +or- 5PSI) regardless of upstream
pressure. It shall provide full and accurate pressure regulating capabilities irrespective of
whether it is operated electrically or manually. The pressure measurement should be possible
via schrader valve or integral pressure gauge.
Check valves three inches (3") and above shall be double flanged single door swing type
having ductile iron body and gunmetal seat to BS1400. Pressure Rating to be PN 16 or
more. All valves shall be coated with epoxy internally and externally to average DFT 300
microns for protection against corrosion of body components. All nut bolts to be of stainless
steel grade 316/ A4-70.
Check valves of two inches (2") and smaller shall be spring type manufactured from Brass or
Bronze. Inlet and outlet to be BSP female threaded. The spring to be of stainless steel.
Pressure rating to be PN16 or more.
Gate valves three inches (3") and larger shall be double flange, ductile iron waterworks
valves, with wedge type gate and non-rising stem. Valves shall be manufactured in
accordance with DIN3352. All valves shall be coated with epoxy internally and externally to
average DFT 300 microns for protection against corrosion of body components. Valves
installed below ground shall be provided with stem cap for key operation.
Valves to have non-rising stem of stainless steel, stem nut brass or cast aluminium bronze
with gun metal. Body components shall be of Ductile cast iron SG GGG-50. Stem sealing by
elestomer/ NBR rubber ‘O’ rings.
Up to size DN 400 resilient seated Gate valves are preferred with ductile iron wedge fully
covered with special grade elastomer EPDM rubber. Heavy duty steel keys with head
configuration to fit operating nut and handle length as required for proper above ground
operation shall be provided in numbers specified by the Engineer.
Valves above ground shall be provided with hand wheel. Nominal pressure for the valves
shall be 16 bar or more. All bolts and nuts to be stainless steel grade A4-70.
Gate valves two inches (2") in diameter and smaller shall have non-rising stem and be
manufactured from brass or bronze according to BS 5154. Inlet and outlet to be screwed
BSP. Rating to be PN16 or above.
Provide automatic double orifice air vents at all high points at all high points on the pressure
mains. Air valves and other similar items shall confirm to BS 2591. Automatic air valves shall
have non-corrosive floats in chambers with clear space ensuring blockage free operation. All
components for the air valve actuating mechanism including lever shall be stainless steel.
The body and cover of the valve should be of bronze or ductile iron with phenolic primer
coating. Nozzles with seals and actuating mechanism to be located in the removable upper
plate connected to the valve body using stainless steel (grade 316/A4) bolts. Valves shall be
coated with epoxy internally and externally to average DFT 300 microns for protection against
corrosion of body components. All nut bolts to be of stainless steel grade 316/ A4-70.
Pressure rating of the valve shall be 16 bar. The internal components shall be stainless steel.
The valve size and installation shall be as per site conditions and engineer instruction.
Electrically actuated Butterfly valves shall comply in all respects with DIN 3354 - PN16 Body
of Ductile cast iron SG GGG-50 Valve disc shall be of Stainless steel 316.
All valves shall be coated with epoxy internally and externally to average DFT 300 microns for
protection against corrosion of body components.
Valves shall be flanged type or mounted between flanges to DIN 250, part 1 for PN 16, face
to face dimensions to DIN 3202-K1 corresponds to ISO 5752, concentric type, streamlined
design.
With replaceable seat ring, fusion bonded on backing ring, leak tight closure on both
directions. For operation at differential pressure at maximum 16 bars with operating gears
with electric part turn actuator.
Variant DN-40-300, K1, Seat ring NBR (BUTA N), Shaft S.S. 1.4005, Maximum working
temperature +80 degree Celsius with maximum working pressure 16 bars.
Electric actuators shall have to open and close of at least 60 seconds and shall be provided
with an auxiliary operating wheel. The motor control should allow for stepped closing of valve
pausing at ½ closed and ¼ closed.
Motor and electrical protection shall be in strict accordance with the electrical specifications
and DEWA regulations; motors shall be rated to operate at an ambient temperature of 50
degrees centigrade, and a relative humidity of 100 %.
Electrically actuated butterfly valve shall be connected to low pressure cut-off switch for
automatic closing of valve in case of low pressure (down stream of valve) due to any
breakage in the system. But valve should not be closed if both downstream and up- stream
pressure is low.(due to shutdown/ breakage of TSE Network Main). For this purpose
Contractor should arrange a differential pressure switch and arrange required control in
combination with other controls.
Complete control of the valve including partial closing of valve should be possible.
The valve shall open and close in modulating action. On pressure reversal, valve shall close
tightly. Adjustable pressure range shall be from 1.0 kg/cm 2 to 8.5 kg/cm2.
These valve shall be installed in the pump room as shown on drawings to release excess
pressure away from the system.
The valve shall be flanged, diaphragm type, hydraulically operated, pilot controlled, and
modulating type. The pilot shall be brass and tubing of copper/brass. The valve shall be fast
opening and slow closing. The valve shall be flanged and of ductile iron body. All internal and
May 2017 Page 21/18
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
external exposed surfaces shall be FDA approved epoxy coated to minimum DFT 300
microns. All nut bolts to be of stainless steel grade 316/ A4-70.
Air valves (1" or smaller only), quick coupling valves, solenoid valves and wires pull boxes to
be installed in an access box of sufficient size to permit ready removal of the valve inner
assemblies without removing the box from the ground. Valve names and numbers must be
clearly marked inside and outside of the box with permanent plastic tags.
Valve boxes shall be fabricated from reinforced plastic and minimum recommended size shall
be as follows:
COVER DEPTH
Measurement are taken from the top of boxes. Covers shall be secured by stainless steel
(A4-70) bolts.
Please note- Installation of plastic valve boxes in Paved areas and Sikkas are not allowed.
All the valve chambers/pullboxes in paved areas and sikkas shall be in RCC and with heavy
duty ductile iron manhole covers.
Ductile iron basket strainer with bolted cover, inlet and outlet to be flanged and drilled to PN
16. The strainer should be stainless steel with 1/8 inch. perforations. Working pressure is 150
psi. All bolts and nuts to be stainless steel grade 316/A4-70. The basket strainer shall be
coated internally and externally with coal tar epoxy 300 DFT micron.
For sizes 2" and below, "Y" type threaded end bronze strainers should be used for protecting
the performance of pipeline equipment by Removal of debris from the water.
The strainer should PN16 rating with Bronze body material and screen should be of Stainless
steel 316.
Water Meters should be horizontal Woltman-type meter designed for installation where
occasional low and moderate to high sustained flows are demanded. Accuracy should be
maintained in both forward and reverse flow directions.
Water meter should comply with with all relevant international quality standards, substantially
exceeding ISO4064 BS5728 Class B specifications for forward flow installations in horizontal,
vertical and inclined pipelines.
The meter should have Robust shroud and copper can register for long life and clear
readability, optimum accuracy. The Meter should given reading in cubic meter and/or US
gallons.
The meter shall be suitable for installation in horizontal, inclined or vertical lines.
The meter to be suitable for use up to 120° F (50°C) and working pressures up to 230 psi (16
Bar). The meter will perform with accuracy registration of 100% ± 2% within normal flow*. The
Meter should be certified by manufacturer in factory for both pressure loss and accuracy tests
before shipment. No adjustments need to be made before installation.
The main case to be of cast iron with raised characters showing size and direction of
flow. Meter body and cover are epoxy powder coated for protection in all environments.
Thrust pads and stub spindles are manufactured in tungsten carbide and jewelled rotor
bearings are used for maximum wear life.
The measuring element assembly should consist of the rotor, straightening vanes, accuracy
regulator, spindles and gears. The measuring element is attached to the underside of the
cover with three stainless steel screws and washers. The main case and cover are
assembled with an o-ring gasket and stainless steel nuts, bolts and washers. The
register/pulser assembly is secured to the cover with a lock wire and lead seal.
A in-line strainer should be installed proior to the meter to protect the rotor and help reduce
the effect of turbulence.
The meter should be capable of being easily fitted with pulser output feature on site; when-
ever required in future without disturbing the calibration seal or interrupting the water supply;
for providing pulser-out for automatic water reading through central control system. Pulse out-
put should be possible by two types of pulsers: opto-electronic and reed switch.
Emitters shall be constructed from durable black-heat resistant plastic. The emitters shall be
of barbed configuration which can be inserted easily in to Polyethylene tubing. Pressure
compensation shall be achieved by a flexible orifice located in resilient Silicone Elastomer
diaphragms. The orifice should be self-flushing type and shall clean itself during each
irrigation cycle at the start up and the shut down. The emitters should have manual flushing
capability also. The emitter exponent shall be 0.10 or less. The body and the diaphragm
should be resistant to high concentration of Chlorine, fertilizers and pesticides.
Irrigation equipment - Dripperline shall consists of linear low density Polyethylene tubing with
pressure compensating, self flushing type integral drip emitters. The tubing shall have an
minimum outside diameter (O.D.) 16mm and thickness of 1.1 mm + 0.05mm. Pipes for drip
lines shall be manufactured from low density polyethylene incorporating a minimum of 2.8%
carbon black, antioxidants in an amount not exceeding 0.5% and shall have a nominal
pressure PN 6.
A random samples of drip pipes shall be subjected to the Teepol crack resistance test. The
samples shall be immersed in a bath containing a solution of 10% Teepol and 90% water
maintained at 50 degrees C. The pipe should resist the solution without showing any fatigue
or crack for a period of 150 hours.
The emitters must be pressure compensating according to ISO 9260 and emission rate of the
emitter shall remain constant at varying water pressure from 1bar to 4.5 bar. The flow path in
emitter must ensure turbulent flow and emitter must confirm to excellent pressure
compensation and self-cleaning/Flushing mechanism. The emitter must be clogging resisting
and the filtration requirement not more than 150 mesh. Coefficient of variation shall be less
than 5%. the flow of emitter must remain same/constant at temperatures varying from 0 to
60 deg. Celsius.
The product must have warranty against cracking and performance for 7 Years.
No. of dripline risers shall be as per Engineer’s approval. Separate dripline risers shall
be for each planter. Each tree in grass areas shall be provided with separate dripline
riser. Drip stakes shall be provided at each point of change in direction of drip line and
spacing between drip stakes shall not be more than 10.0 meters. Drip stakes shall be
provided at each point of change in direction of drip line and spacing between drip stakes
shall not be more than 10.0 meters.
The capacity and spacing of the inbuilt emitters in the dripperline shall be as follows:
For ground covers: Emitter discharge rate shall be 0.9 GPH and spacing between emitters
shall be 50 cm in dripperline and 50cm between dripperlines.
For seasonal flowers: Emitter discharge rate shall be 0.6 GPH and spacing between
emitters shall be 50cm in dripperline and 30cm between dripperlines.
For hedge: Emitter discharge rate shall be 0.6 GPH and spacing between emitters In
dripperline shall be 50 Cm.
For trees: A loop of dripperline (around tree) with 0.9 GPH in line emitter at every 30 cm
length of dripperline in a loop shall not be less than 3.2 metre.
For shrubs: 2 Nos in line PC emitters (each emitter 0.9 GPH) per plant shall be used for
shrubs if spacing between shrubs is less than or equal to 1.5 metre. A loop of dripperline with
3 Nos inline P.C. emitters (each emitter 0.9 GPH) per plant shall be used for shrubs (if
spacing between shrubs is more than 1.5 mtr).
For bougainvillea: 2 nos. in line p.c. emitters( each emitter 0.6 gph) per plant
Irrigation equipment- Subsurface Drip tubing shall consists of linear low density Polyethylene
tubing with pressure compensating, self flushing type integral drip emitters. The Tube shall be
suitable for subsurface installation in grass areas.
The drip tubing shall be a pre-bonded emitter type. The tubing shall have emitters spaced at
12 inches (30 cm) and in flow rates of 1.0 gallons per hour (GPH) with a coefficient of
variance (Cv) less than 0.05. The spacing between the drip tubing should not be more than
12"(30cm) .
Maximum length of run of the drip tubing (for relatively flat levels/grade) from drip line riser
point should not be more than 55 mtr.
Water distribution shall be via an integrated turbulent flow path emitter with dual discharge
May 2017 Page 21/21
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
ports on opposing sides of the tubing. The tubing shall consist of nominal-sized, linear, low-
density 5/8" (15,8mm) polyethylene with an outside diameter (O.D.) of approximately .710"
(18mm) and an inside diameter (I.D.) of approximately .620" (16mm). The emitters shall be
molded from virgin polyethylene impregnated with TREFLAN(R) to inhibit root intrusion. The
tubing shall be available in pressure-compensating type. The pressure-compensating type
shall incorporate a circular silicon rubber disk designed to flush at startup, shutdown and
during the irrigation cycle to inhibit debris collection.
The tubing shall have at least seven-year warranty for root-intrusion protection.
The flushing valve shall be with inlet size minimum 1/2" MPT. The flushing valve shall be
entirely of non-corrosive plastics. Maximum Flow rate should be 15-20 gpm. Line Flushing
Valves should be used to provide a cleansing action in the sub-surface drip tubing each time
the zone is turned on. The Line Flushing Valve should have ability to dump water which
allows the velocity of water inside the drip tubing to increase momentarily during turn-on. This
action should move sediments out of the system through the Line Flushing Valve. Place a
Line Flushing Valve (one per 15 GPM of zone flow) as far away from the source as possible.
This should typically be somewhere along the exhaust header. Note: Where Center Feed
layouts are used, install one Line. Flushing Valve on each exhaust header.
Line Flushing Valves should be buried in a valve box with a gravel sump adequate to drain
approximately 1 gallon of water as shown on the details drawing. Installation of the Line
Flushing Valve should be in an inconspicuous area as far away from the source (solenoid
valve) as possible.
1. To freely allow air into a tubing after shutdown. This ensures a vacuum doesn’t draw debris
into the drip tubing.
2. To provide a means of releasing air from the drip tubing when the zone is turned on, thus
eliminating air pockets.
Air/Vacuum Relief Valves are installed at the highest point(s) of a subsurface drip-tubing
zone. Instillation of Air/Vacuum Relief Valves should ensure all rows of drip-tubing can take
advantage of the Air/Vacuum Relief Valve, install it on a line perpendicular to the dripline
rows. This may be an exhaust header, or a special lateral connecting all the rows of drip-
tubing such as going over a berm.
The air vent/vacuum relief valve shall be an O-ring seal type with inlet threads of 1/2" (16mm)
MIPT capable of venting air until 4 psi (0,27 Bar) is achieved at system startup, and vacuum
relief when 4 psi (0,27 Bar) is reached during system shutdown. The air vent/vacuum relief
valve shall be rated at a maximum operating pressure of 100 psi (6,8 Bar). The air/vacuum
relief valve body and shuttle shall be constructed of corrosive-proof engineering
thermoplastics. The seal shall be a rubber O-ring. Air/Vacuum Relief Valves should be
installed in a valve box with a gravel sump as per details drawings.
On slopes in line spring check valves should be installed to avoid wet areas in the lowest
areas in that zone due to low line drainage.
The check valve shall be a preset, adjustable type with 1/2" (16mm) female slip inlet and
outlet capable of eliminating reverse water flow when the system is depressurized. The check
valve body shall be molded from polyvinyl chloride (PVC) capable of being solvent-welded to
any appropriate PVC pipe or fitting. The check valve seat shall be constructed of rubber. All
internal metal components shall be constructed of stainless steel. Opening pressure of the
check valve should be 5 psi (0,3 Bar) and be capable of maintaining elevation change up to
12' (3,6m).
Provide at least one operation indicator per zone. The operation indicator shall include two
feet of 1/4" (6,4mm) blank tubing with a pre-installed barbed coupling. The operation
indicator's stem shall extend to 9" (229mm) with 10 psi (0,68 Bar) of working pressure.
Bubblers shall be constructed from UL stabilized engineering grade plastic and rubber,
delivery shall be pressure compensating in the range of 2.00 to 5.00 bar, delivery shall be
umbrella pattern, flow shall be 1gpm. Inlet shall be ½ inch female threaded.
Stakes for bubblers shall be constructed from strong temperature resistant polypropylene
plastic construction with protective stop collar, length shall be 12 inches each side of inlet with
barbed side inlet suitable for class “C” polyethylene pipes, outlet shall be ½ inch external
male thread.
2 NOS. BUBBLERS SHALL BE USED FOR EACH PALM TREE, EACH 1 GPM
The sprayers shall have a high level impact strength corrosion resistant body, stem and
nozzle. Pop - up height should be 4". The sprayer shall have a heavy-duty stainless steel
retraction spring and piston with slip clutch to facilitate nozzle positioning. The sprayer shall
incorporate a wiper seal to protect the internal mechanism against ingress of foreign material
and prevent pressure blow out and shall have an easily accessible under nozzle screen. The
wiper seal should be co-molded type that ensures flow-by of less than 0.10 US. GPM at low
pressure and complete sealing at pressure greater than 10 psi. The sprayer shall have
12mm (1/2") threaded inlet.
The sprayer shall have the following performance specification at 2 bar operating pressure:
The nozzles shall have precipitation rates matched across sets and across patterns. The
standard nozzle shall be capable of covering 4,5 metre radius at 2.0 bar pressure.
Spacing for the sprayers with standard nozzle shall be 4 meters. For small areas sprayers
with low flow nozzles shall be used as shown on drawings.
Standard Sprayers shall have the following performance at 2.0 bar and 30° trajectory:
Low angle/low gallonage sprayers shall have the following performance at 2.0 Bar and 15°
trajectory:
All nozzles for standard and low angle shall be MPR. Sprayers / sprinklers should be
installed in such a way that water will not hit the stem of the palm trees.
Sprayers and sprinklers shall be installed 30cm away from heel kerb / edge of footpath.
Turbine or gear drive rotor pop up sprinklers, full and part circle operation with Memory-Arc to
automatically return nozzle stream to set arc. Part circle adjustment shall be from minimum
40 deg. to 350 degrees. All adjustments of the sprinklers shall be from the top.
The internal mechanism is water lubricated. Heavy duty plastic case with multi-function wiper
seal and heavy duty retraction stainless spring. All sprinklers should be provided with seal-A-
matic check valve. Bottom inlet to be 3/4" BSP female threaded. Pop up height to be not less
than 3 5/8". The nozzles of all the sprinklers shall be low pressure models for proper
performance even at low pressures.
The sprinkler shall approx. match the following performance specification at 3.0 bar operating
pressure:
Spacing for these sprinklers shall not be more than 10.0 meters.
Spacing for these low angle sprinklers shall be not be more than 6.5 meters.
21.2.9 PUMPS
The irrigation network is used for both irrigation and fire water supply. The main irrigation
pumps are to be switched off whenever a fire is detected.
Hydrostatic flow switches are to be installed at each fire hydrant connection chamber.
Whenever a fire hydrant is opened, the flow switches will send a signal to the main control
system to switch off the main irrigation pumps and close the solenoid valves. Irrigation pumps
to be started only after fire mode signal has been removed.
In order to achieve the above described function, a control system is to be installed consisting
of at least the following components:
1. Integrity of the system after installation of piping and equipment inside the pumping station.
2. Entire piping system shall be restrained and/or protected against unbalanced forces.
3. Stress analysis shall be carried out by specialist engineer to design appropriate supporting
system and to maintain loads on pipes and equipment within allowable limits.
Centrifugal pumps shall be vertical, multistage, cast iron body and base. The pump section
(shaft, impellers, guide vanes and chambers) shall be of stainless steel. The mechanical shaft
seal shall have diamond polished Tungsten Carbide or Silicon Carbide seal faces and heat
resistant O-ring. Thrust bearing shall have ample capacity to carry the weight of all rotating
parts plus the hydraulic thrust of the impellers. Motors shall be closed coupled type.
During normal operation system shall allow for 30-40m head pressure for each automatic
irrigation connection point for streets, open areas and lease lots.
Motors shall nominally 2900 RPM, TEFC Class F, manufactured generally in accordance with
DEWA regulations and electrical specifications. The power rating for the electric motor should
be 30% above the rated power shown in the manufacturer catalogue.
Supply and install packaged booster pump set for irrigation water supply, designed for the
total system capacity as shown in the pump schedule. The system shall be completely factory
May 2017 Page 21/25
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
assembled, tested and shipped to the job site as an integral unit ready to receive suction and
discharge piping and incoming electric power.
Out of the 4 duty pumps one will be of variable speed and control panel to be assembled
either by the pump manufacturer or by their local representative. Local assembling facility
should be minimum ISO9002 certified for manufacturing and servicing of packaged pump set
and variable speed drive unit.
Provide water pumps of type and size as indicated on the equipment schedules.
1. Pump shall be selected for non-overloading characteristics, and the contractor shall submit
performance curve on pumps proposed for installation. Select pumps to operate near their
point of peak efficiency, flexible coupled to an electric motor and mounted on common steel
base plate.
3. Pump shall be of single stage vertical mounting type to suit the specified capacity.
21.2.9.1.3 Motor
The pump shall be connected to a totally enclosed fan ventilated motor with class F
insulation. Motor shall be in accordance with latest NEMA / BS standards and shall have
following characteristics.
Each motor shall have a sufficient horsepower rating to operate the pump at any point on the
pump’s flow-head curve without over loading the name plate horsepower rating of the motor.
The motor shall be suitable for continuous duty and variation of + 5% in voltage.
Piping shall be steel Sch 80 epoxy coated, with isolating cast iron epoxy coated gate valve on
each pump suction and discharge, cast iron check valves on each pump discharge, strainer
on the suction of each pump, flexible connectors on suction and discharge of each pump.
Common header shall be of steel Sch 80 epoxy coated. Provide pressure gauge in suction
and discharge header.
21.2.9.1.5.1 General
Pump set to be suitable for 400V/3Ph/50Hz power supply and 240V/1Ph/50Hz control.
The control system shall enable the pumps to maintain a set point pressure with variable flow
rates utilizing pressure sensing to vary the pump speed to suit the flow.
The controller shall utilize a VFD frequency inverter to modulate the speed of VFD pump and
the number of pumps running to maintain a constant pressure in the reticulation. The
operation shall be controlled by a pressure transducer to determine the actual pressure and
compare the pressure with a reference pressure set in the controller.
The control shall be a purpose built microprocessor dedicated to pump control. PLC control
units shall not be considered.
When the system pressure drops below the System Cut In pressure the controller shall signal
the VFD to run. The first pump will ramp up in speed until the Set Point pressure is reached. If
one pump cannot satisfy the pressure requirement it will be placed on fixed speed and the
next pump will ramp up on the VFD and try to achieve the Set point pressure. This procedure
shall be repeated until the set point is reached or all pumps are running. The controller shall
then modulate the speed of the VFD pump to maintain this pressure.
The controller shall receive signal from the Fire pump control panel to alter set point to
desired level on the fire pump coming into operation. On completion of the fire pump
operation, the controller shall set the pressure setting back to the original set level.
The Contractor shall provide the surge and stress analysis in order to determine
impact on pumps and piping system.
1. All electrical works must be installed to international standards and comply with regional
power authorities requirements. It shall be the contractors responsibility to obtain permits
and inspections from those authorities where required.
2. The Control Switchboard shall be located in a position protected from direct sunlight and
the elements.
3. All equipment mounted within the switchboard shall have all wiring numbered and
confirmed to an `AS BUILT’ Circuit Diagram.
4. The control power supply shall be 240V AC 50Hz with suitable protection to stop
unauthorized access to the high voltage areas.
5. All control wiring shall use multi-strand multi-cored shielded control cable of at least 1mm2.
6. Pressure input shall be via a pressure transducer. The controller shall be suitable for any
full scale pressure transducer that still satisfies the hydraulic requirements.
7. The switchboard shall have Din rail terminals located in the bottom half with the following
inputs/output sized for 2.5mm building wire with opto-isolation of the input voltages to the
main control board.
8. All wiring shall be numbered and conform to the as built circuit diagrams.
9. The switchboard shall be manufactured from 2mm thick mild steel with exterior quality
powder coating applied to prepared surfaces. The Ingress protection shall be to IP54
minimum with removable filter pads for dust ingress protection.
MANUAL-OFF-AUTO switches shall be installed for each pump located on the front of the
switchboard with the pump number clearly labeled adjacent to this switch.
Provision shall be made for the control of pump operations as follows:-
MANUAL - run pump irrespective of all other commands
AUTO - Modulating control for the selected pump.
OFF - Selected pump remains isolated at all times
Selection of any of the above functions will not effect the operation of other pumps.
After restoration of power following a power failure the system shall power up to normal
operation with the system operating with the previously set parameters. Power up to
DEFAULT parameters shall not be acceptable.
Any failure of the VFD shall not preclude the MANUAL operation of the system.
The control of the pump set shall incorporate the following protection features.
The shutdown events must be resettable by any operator & a relay shall be available to drive
an indicator such as a dome light in case of a shutdown occurrence.
The control system must log data for display on the screen. The items to be logged are:
Hours run per pump
Flow rate
Total flow
Fault history
Resetting of these items to zero shall be made from screen key presses.
The controller shall have a nested menu structure that allows access to specific areas for site
tuning. The menus shall be in English text. Abbreviations shall not be accepted.
All control equipment shall be rated to a minimum of 50 deg. C & 90% humidity without
causing any shutdown. The unit shall be cooled by means of an internal fan sized to maintain
May 2017 Page 21/28
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
lower than maximum temperatures within the unit. The control box shall be mounted under
cover away from any direct sunlight with access denied to unauthorized personnel.
The enclosure shall be rated to IP54 with forced cooling fans designed to handle heat
extraction of suitable capacity assuming a 3% VFD power loss. This calculation shall be
made with an ambient temperature of 46 deg.C. Calculations shall be provided if requested to
prove this capacity.
The control system shall have the feature of selective entry for personnel based on key press.
Sensitive areas of adjustment shall be accessed by a security code. All areas that would
effect the configuration of the system shall be security protected.
21.2.9.1.5.8 Outputs
The controller shall have 4 programmable outputs that can be selected to any of the functions
listed below but not limited to these options. They shall be rated to 10 amps 240VAC with
change over contacts.
Shutdown Fault
Low Pressure Fault
High Pressure Fault
High Pressure Alarm
Pump 1 Run
Pump 2 Run
Pump 3 Run
Pump 1 Shutdown
Pump 2 Shutdown
Pump 3 Shutdown
System Paused
Any pump shutdown
Any pump running
No Flow Shutdown
VFD Fault
Pressure Trip 1
Pressure Trip 2
21.2.9.1.5.9 Inputs
The controller shall have 4 fixed voltage free inputs and a minimum of 8 programmable
inputs. The programmable inputs shall have the following options:-VFD Fault
Set Point 2
Set Point 3
Soft Pause
Pump 1 Protection
Pump 2 Protection
Pump 3 Protection
Pump 1 Stop
Pump 2 Stop
Pump 3 Stop
Phase failure
Fire Mode
Pump 1 Manual Run
Pump 2 Manual Run
Pump 3 Manual Run
Cycle pumps
Shutdown No Flow
21.2.9.1.5.10 Telemetry
The controller shall be capable of communicating with an external telemetry system based on
digital Inputs and Outputs from a remote source.
21.2.9.1.5.12 Documentation
The contractor shall provide the following documentation prior to Practical Completion being
awarded:
- Instruction manual for the controller
- As-built drawings of the mechanical components in AutoCAD 2000 format copied to an
- IBM compatible 3.5” floppy disk
- A1 sized drawing of the as built pump station.
- Full set of circuit diagrams on AutoCAD 2000 format
- Bound copy of as built circuits with pumpstation showing all circuits, exterior
dimensions and components, detail of all components used within the switchboard by
Make & model.
- VFD instruction manual
ITEM COMPLY
Control features Yes No
IP Compliance Yes No
Switchgear included Yes No
Pump protection Yes No
Input capacity Yes No
Output capacity Yes No
Set points – 3 off Yes No
Data log suitability Yes No
Switchgear standard Yes No
VFD type Yes No
Cooling capacity Yes No
Telemetry serial communications Yes No
TEMPERATURE RATING 40degC Yes No
OUTPUTS Yes No
Documentation Yes No
QA compliance Yes No
Centrifugal pumps shall be cast iron body and base. The pump section (shaft, impellers,
guide vanes and chambers) shall be of stainless steel. The mechanical shaft seal shall have
diamond polished Tungsten Carbide or Silicon Carbide seal faces and heat resistant O-ring.
Thrust bearing shall have ample capacity to carry the weight of all rotating parts plus the
hydraulic thrust of the impellers. Motors shall be closed coupled type.
May 2017 Page 21/30
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
System shall allow for xx m head pressure and xx GPM flow for each fire hydrant while
operating one at the time of fire.
Fire pump shall be local Civil Defence approved and manufactured by an approved
manufacturer. Packaged fire pump set along with the control panel to be assembled in a
ISO9002 Certified facility within the United Arab Emirates.
Each pump shall have capacities as shown in pump schedule, adjusted as necessary to suit
the hydraulic calculation.
Electric fire pump shall be vertical centrifugal single stage or multistage construction and
Diesel driven pump shall be horizontal single stage or multistage construction to suit the
specified rating. The pumps shall be connected to the standpipe system. The suction supply
for the fire pump shall be from storage tank at a maximum pressure of 1.0 bar. The pump
casing shall be cast iron and rated to withstand at least 1.5 times the working pressure.
The casing will be of the end suction design made of cast iron, designed for 1720 kPa
hydraulic test pressure. The casing shall have tapped and plugged holes for priming, vent
and drain.
The impeller shall be designed to give the characteristics outlined under “Performance”. It
shall be of the enclosed type, vacuum cast in one piece. It shall be furnished all over, the
exterior being turned and the interior being furnished smooth and cleaned of all burrs,
trimmings and irregularities. The impeller will be dynamically balanced. It shall be held
securely to the shaft by a key of ample size and impeller nut.
A stuffing box shall be provided, designed with sufficient area for incorporation of mechanical
seals.
Pumps shall have balanced mechanical seals. Mechanical seals shall be with carbon rotating
ring, stainless steel spring, ceramic seat and flexible bellows and gaskets.
The pump shaft shall be one -piece finished and polished on all sections. The shaft shall be
of ample strength and rigidity and the shortest practicable distance between bearings shall be
used to keep deflection and vibration to a minimum.
A flexible coupling shall be provided to connect the pump shaft to the motor shaft. The
coupling shall be of an all metal type with a flexible rubber insert. The entire rotating coupling
element shall be enclosed by a coupling guard.
The pump, motor and diesel engine shall be mounted on a groutable steel base plate with
integral drip channels incorporated on each side. The base shall be sufficiently rigid to
support the pump and motor without the use of additional supports or members.
21.2.9.2.2 Accessories
The electric motor shall be totally enclosed fan ventilated, wound for 380/415V/3Ph/50Hz
current. The motor shall be such capacity that 115% of full load ampere rating shall not be
exceeded at any condition of the pump load. Acceptable suppliers shall be: Brook Crompton
(UK), General Electric (USA), Schoch, US motors or equal.
Motor shall be IP55, class F insulated suitable for ambient temperature of 50 0C. Bearings
shall be anti friction ball or roller type.
Diesel engine shall be provided with electric starting system. Engine shall be either radiator
cooled or heat exchanger type. In case of heat exchanger, the factory supplied heat
exchanger piping loop complete with required strainers, a pressure reducing valve and
bypass line shall be installed between the pump discharge head and engine heat exchanger
by the installing contractor. Each engine shall be furnished by a lead acid heavy duty starting
batteries, battery rack and cables, a flexible exhaust connector and industrial type silencer.
The fire pump control panel shall be completely assembled, wired and tested by the control
manufacturer before shipment from the factory, and shall be labeled “Fire Pump Controller”.
The controller shall be located as close as practical and within sight of the motor, preferably
mounted on the pump skid. The controller shall be so located or protected that it will not be
damaged/effected by water escaping from the pump or connection. The controller shall be of
combined manual and automatic star delta type, and shall be complete with:
21.2.9.2.6 General
Pump set with diesel and electric driven shall be complete with suction and discharge header,
pressure gauges, coupling guard and control panel.
Batteries shall furnished in a dry charge condition, with electrolyte liquid in a separate
container. Electrolyte shall be added and the battery given a conditioning charge at the time
that engine is put into service. Batteries shall be located so as to be readily accessible for
servicing and at least 300 mm above floor level.
All wiring between controller and building fire alarm system shall be carried by the contractor.
A wring diagram shall be provided inside of the control panel enclosure showing exact wiring
for the controller, including a legend of identifying number of individual components. All wiring
terminals shall be plainly marked to correspond with the diagram furnished.
Wiring elements of the controllers shall be designed on a continuous -duty basis. All wiring
leading from the panel to the engine and to the battery shall have adequate current carrying
capacity. Such wiring shall be protected against mechanical injury by conduit.
Prior to shipment, the pump set shall be thoroughly shop tested for leakage. Test pressure
shall be 1.5 times the working pressure.
Electric fire pumps shall be the lead fire pump. Diesel engine pump shall be backup fire pump
and shall only operate if the lead pump cannot maintain system pressure.
Pump and motor to be aligned by the pump supplier prior to commissioning using Laser
alignment equipment. Software generated alignment report to be submitted along with
commissioning report.
The pump driver all controls and necessary attachments specified herein shall be purchased
under a unit contract. Field wiring of fire alarm panels, installation and wiring of fuel piping,
wiring from the suction tank to the panel shall be provided by the contractor. The pump
manufacturer shall assume unit responsibility and shall provide the service of a qualified
engineer to supervise the installation and alignment of equipment. Field tests shall be
conducted in the field to satisfy Local Authorities having jurisdiction of satisfactory operation
of pump, driver and controller. The pump manufacturer’s engineer shall be at the job site
supervising the test. The control manufacturer shall have their representative at the job site to
train operators in the use of the controls.
Sump pump is required for the Main Irrigation Pump Station, location and arrangement
should be as per details drawings.
The pump shall be of robust construction and suitable for pumping corrosive, treated effluent
with high sand content. It should operate at minimum 100mm depth of water. Pump body,
impeller as well as vital pump components to be of Stainless steel.
Capacity of these pump should be 130 m3/hr at 12 metre head. Delivery line of these pumps
to be connected to the nearest storm water Drainage manhole. This connection shall strictly
be as per the specifications & the requirements of Drainage & Irrigation department.
Float switch to be provided to operate these pumps automatically if the level of water inside
the filtration chambers comes up.
All switches and control devices related to these pumps to be fixed in the electric control
panel.
Drain line to be connected from fertilizer room to sump pump pit in pump room.
21.2.10 LAGOONS
21.2.10.1 General
The TSE generated from the STP is stored in the lagoons located in the green buffer zone.
The lagoons are not within the scope of work for this contract.
21.2.11 FILTERS
Automatic self-cleaning filters specifically designed for use with organic contaminants.
Cleaning shall be effected by a hydraulically powered suction scanner, automatically
activated when the differential pressure across the filter reaches an adjustable level,
nominally 5 psi.
The screen shall be stainless steel grade 316 L with 200 micron mesh size. Flushing line to
be connected to the soak pits or nearest storm water drainage manhole.
The control system shall feature a fail safe timer to prevent continuous flushing due to
malfunction.
The control System for the filters should be such that it will not flush the filters if the pumps
and/or irrigation system is not operating. Filters should flush; only during the operating hours
of the Irrigation System.
6 filters to be installed in pumping station, 4 duty and 2 standby. The capacity of each filter
should be minimum 3960 GPM.
All the filters shall have isolation valves in the suction as well as delivery side for easy
maintenance. The controller for the filters shall be equipped with timer and pressure
differential control unit. Controller will be fixed in the Electric control panel.
The filter body and internal parts including flanged connection shall be stainless steel.
Pressure gauges to be connected to suction and delivery side of each filter, pressure gauges
to be mounted in the Electric control panel in isolated compartment.
Pressure gauges for filtration chambers shall be stainless steel, direct reading, Glycerin
filled capable of 0-10 kg/cm2 register with 0.25 graduation. Gauge shall be of glass or
Plexiglas faced, drip-proof and minimum dia. of 50mm. Gauge cock shall be of same size as
pressure gauge and be fabricated from stainless steel.
Warning tape shall be laid above main pipes. Tapes shall be durable and detectable by
Electro-Magnetic means using low output generator equipment. They shall remain legible
and color fast in all soil conditions at PH values of 2.5 to 11.0 inclusive.
The tapes shall be flexible and subject to the Engineer's approval. Width of the tape should
be at least 6"(150 mm.).
Tape shall be Orange color with Black text in Arabic and English as " CAUTION:
IRRIGATION PRESSURE MAIN BELOW ". The text on the tape shall be permanent ink
bonded to resist prolonged chemical attack by corrosive acids and alkaline with message
repeated at a maximum interval of two meters. The tapes shall be laid 300 mm above the
pipeline.
The tape shall be continuous over pipelines and at joints there should be a minimum of one
meter over lapping.
All electrical equipments shall be in accordance with DEWA regulations and electrical
specification. Enclosures shall be protected in accordance with IP55 for equipment installed
above grade and IP58 for equipment installed below grade.
Wiring to and from control panels shall be routed in pvc conduit below the ground. Above
grade conduit to be liquid tight flex, or galvanized steel, provision to be made for inspection
tee's and ells to facilitate removal in the future.
1. SIEMENS
2. LEGRAND
3. ABB
All electrical wire for underground use shall be single core solid "Underground Feeder" type
insulated with a flame-retardant thermoplastic compound, rated for 600 volts and direct burial.
The Contractor shall prepare a wire-sizing chart with effective lengths of each station and
common wires, which shall be submitted, for approval prior to commencement of work.
Cable markers shall be used for indicating valve number each cables at both ends as well as
at splices. Cables shall be laid in PVC conduits.
Two-way signal cables should be laid in separate conduits between irrigation Controller and
Main control panel for future use. Separate wire to be laid for each solenoid valve, and valve
combination to be arranged at the respective Irrigation Controller. Power cables for Irrigation
controllers shall be armoured cables without any conduit for it.
Two-way Signal wire between the Main Control Panel and the Irrigation controllers should be
double jacketed, two conductor cable intended for future central control system.
The cable manufacturer should certify that the insulated conductors have been tested for and
meet the requirements of U.L.
The two conductors shall be color coded with one conductor BLACK and the other RED. The
conductors shall be tin coated, soft drawn, annealed solid copper conforming to the
requirements of ASTM -33.
The cable shall be suitable for direct burial in the earth, whoever it is required to be installed
in ducts or conduits.
Pull boxes shall be provided at every place of change in direction of conduit piping, near to
solenoid valves. In any case spacing between adjacent pull boxes in a line shall not exceed
50 meters.
Size of the cable depends on the distance between the Main Control Panel and the field
Controllers and according voltage loss calculations.
SEPARATE PULL BOXES SHOULD BE USED FOR POWER CABLES AND MAXI COM
SIGNAL CABLES.
All wire connections at electric remote control valves and all splices of wire in the field shall
be made using wire connectors. The wire connectors shall be specifically designed to ensure
waterproof underground wire connections. The connectors shall be under-writers laboratories
listed water-resistant wire connectors, rated 600 volts for PVC insulated copper wire with
insulation temperature rating of 105 degree C.
The connector shall be insulated with color coded, pliable, vinyl skirt. They shall feature alive
spring which assures a tight grip even on small wire combinations.
All wire connections to be arranged in plastic pull boxes at fixed interval distances of max.
100 meters and/or at any change of direction.
Pressure switches shall be fabricated from die cast aluminum per ASTM B-85 and designed
to meet IP65 specifications. Transducers shall be fabricated from brass and buna N.
The pressure switches shall incorporate an alternating fulcrum balance plate allowing
independent adjustment of both set and reset point over the full range.
Both set and reset points shall be adjustable 1.40 to 14 bar, having a minimum deadband
range less than or equal to 1.40 bar. Repeatability shall be +/-0.5% to 2% of full scale.
Switches shall be vibration resistant and shall have front access to electrical connections and
adjustment nuts.
Flow sensing and control system to sense the flow data and display that data as both flow
rate and volume on digital indicator.
Flow sensing and control system to sense the flow data and display that data as both flow
rate and volume (in US gallons) on digital indicator.
Digital Indicator displays for both flow rate and total volume to be provided and to be mounted
inside the panel. The digital indicator unit should be powered with external 220 volts AC
power supply and rechargeable Lithium battery. The unit can run of internal or external power
and should have automatic changeover switch which is activated during a power failure. The
battery will be automatically recharged during normal mains operation.
Flow sensing and control system should sense high flow rate (above the max. flow rate for
any combination of valves) and close the butterfly valve in filtration chamber.
1. General
Flowmeter shall comprise of a flow sensor and a transmitter unit. The Transmitter and
Display unit shall be remotely mounted in a dedicated Control Panel. The flowmeter shall be
microprocessor based, modular design. Total measuring system shall be suitable for a
minimum ambient temperature of +60º C. Each meter shall be provided with the validation on
site without removing the sensor. Flowmeter processor unit must be digital to reduce noise
level. All inputs, outputs and power supply shall be galvanically isolated. Overall accuracy
should be +/- 0.5% and repeatability shall be 0.1% or +/- 0.5 mm/s (or = of reading).
Each unit shall have electromagnetic compatibility with more than 10 V/m and shall withstand
an isolation test up to 1600 V for 2 sec. min. Complete flowmeter should have good
resistance to shock and vibration. It should withstand acceleration of 2g/2h per day, 10-100
Hz.
2. Sensor
Submersible, flanged process connection of carbon steel material with zink aluminium alloy
coating rated suitably for TSE application. Metering tube shall be at least SS 304. Each
sensor should have 2 measuring electrodes, 1 empty pipe detection electrode and 1
reference electrode. It is essential to have additional empty pipe detection electrode for
proper detection of pipe condition. Electrodes material shall be stainless steel SS 316.
Sensor housing material should be powder coated die-cast aluminium. Sensor lining shall be
polyeurethane, abrasive resistant, suitable for TSE & potable water. Each sensor shall be
protected to IP 67 or IP 68 as required. If the sensor is installed in a flow chamber sensor
must be IP 68. Also, IP 68 protection shall be from the manufacturer, without using any
external kit or gell locally. The connection cable between the sensor and transmitter should
be original and fitted and potted from manufacturer. The coil cable shall be 2x0.75 mm2 PVC
braided copper shield and the signal cable shall be 3x0.38 mm2 PVC braided copper shield.
In case of non conductive pipe materials grounding rings shall be used for proper grounding
or complete meter must be isolated.
3. Transmitter.
The transmitter must be microprocessor based remote wall mounting type. It shall have
modular design and field configurable by its built-in buttons via matrix. Transmitter housing
shall be robust powder coated diecast aluminium construction with IP 67 protection. It is
essential that the transmitter is of modular design for ease of maintenance and future
expendability. In case of any fault in the transmitter one should be able to change individual
modules. The flow meter shall have 4-20mA DC (into a minimum 1,000-Ohm load) HART
and Pulse (frequency) analog output suitable and compatible with DFC SCADA system.
Relay output – 8SPDT contacts rated 8A at 250VAC.
It should have 2-line, 16-character LCD display for flow rate and totalized flow indication with
LED back lighting. Transmitter should be configurable for error messages, empty pipe
detection, flow direction etc.
The sensor and transmitter shall be connected with 10m cable from the manufacturer. The
coil cable shall be 2x0.75 mm2 PVC braided copper shield and the signal cable shall be
3x0.38 mm2 PVC braided copper shield. The meter should be able to operate at the voltage
range of 100-260 VAC, 45-65 Hz supply.
Digital indicator displays for both flow rate and total volume to be provided and to be mounted
inside the panel. The digital indicator unit should be powered with external 220 / 230 volts
AC power supply and rechargeable lithium battery, which can operate continuously for five
hours. The unit can run of internal or external power and should have automatic changeover
switch which is activated during a power failure. The battery will be automatically recharged
during normal mains operation.
Flow sensing and control system should sense high flow rate (above the max. flow rate for
any combination of valves).
4. Other Requirements.
Installation of all equipment and components shall be in accordance with approved shop
drawings and installation instructions furnished by the equipment manufactures.
The Flow transmitter, controller and indicator to be installed remotely for easy access and
maintenance. Sunshade protection to be for all equipment if required.
Suitable connections shall be provided and allowed for future interface with a general DFC
SCADA monitoring system.
Flow switches should be suitable for a maximum operating pressure of 10 barg and a
temperature range from 0°C - 60°C.
Flow switch should have a relay output which will give a signal to the programmable Logic
Controller (PLC) of the irrigation/fire pump control panel system.
Flow switch should be compatible with the pump control system.
Electrical control panels for this project shall be constructed of mild steel sheet enclosures
with stainless steel 316 lock and hinges front opening door having a protection range not
lower than IP 65 according to IEC and to be class 3. The panel shall have provision for
connecting to generator.
The Control Panel For Filtration Chamber shall be Form 2 and that for pumping
station, Class 3 ( Form 4 ) and all the control panels to be fixed in GRP kiosk on
concrete base (300 mm above ground level)
The panels to be fixed above the filtration chamber/pump room as per the Engineer’s
approval and shall include the followings:
Panel shall have main circuit breaker for the power main and earth leakage protection. Each
power circuit should have circuit breaker, earth leakage protection and power indication lamp.
Each switch and light on the exterior of the panel shall be marked with an engraved plastic
name identifying each item. Truncking shall be used when wiring the panel. The panels shall
have serially numbered terminals for terminating all incoming and outgoing cables. Anti-
condensation heaters should provided inside the panel. The panel shall be installed above
Pump or filtration chamber. Pump or filtration system Control panels shall strictly be as per
DEWA and /or DM standard Specifications in all aspects and subject to the Engineer’s
approval.
Same as above to accommodate the control system and injection pump switch gear.
The Irrigation controllers shall be solid state type and shall have 220 Volts power input and
26.5 Volts, 50 cycles.
If the input Voltage to the controller is other than 220 Volts AC, the Contractor must ensure
continuous regular Voltage to controllers equivalent to the input Voltage marked out on the
controllers. If Voltage fluctuations are noted, controllers must be equipped with automatic
voltage regulations.
May 2017 Page 21/39
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
The controllers shall have 24 stations as mentioned on drawings. The controller should be
weather- proof lockable cabinet with minimum one meter high stainless steel pedestal. The
pedestal to fixed on proper concrete base, 300 mm above ground level. All irrigation
Controller(s) shall be installed in GRP Kiosk enclosure.
The two way signal cables from the controllers shall be laid up to the Main electric control
panel for future use. The power supply for all Controllers on a pumping station / filtration
chamber should be taken from single source.
Power supply to the controllers should be by Armoured cables. No conduit is required for
these armoured power cables. Contractor to provide calculations for cable sizing for the
Engineer's approval. Size of the power cables should not be less than 2.5mm2 X 4 core.
Cables laid under ground should be tested in accordance to IEC standards and DEWA's
standards for insulation resistance, continuity etc. in presence of DM and the Engineer before
the backfilling of the cable trenches
The contractor has to check the number of electric valves connected to each station, if
number exceeds the manufacturer recommendation a multi-station relay has to be included
with the corresponding controller. Lightening protection shall be provided for all controllers.
Allow cascade flushing of filters if differential pressure exceeds 0.30 bar, or on command
from central controller. Flush time to be adjustable. Control panel to be provided with a flush
counter (resetable) and a selector switch to allow manual flushing, and/or cancelling each
automatic function.
Controller to be provided with circuits to flow switch mounted in the flush lines to detect any
flow of water after the flushing cycle has ceased, and linked to the alarm circuit, time delay
2.00 minutes. The controller will be mounted inside the electric control panel.
Extra heavy duty industrial type Aluminium body exhaust fan size 18" to be fixed in the
Pump/filtration chambers, minimum three nos. of 8” dia GRP vent pipes to be fixed in each
Pump/filtration chamber for circulation of the air in the chambers.
The isolation valves shall be in R.C.C. chambers as shown in the detail drawings.
The Contractor has to propose a design for chambers to suit the site conditions. The covers
shall be double triangular heavy-duty ductile iron cover with clear opening 600x900 mm,
bitumen epoxy coated. The cover should be loosely coupled by stainless steel bolts and nuts.
Covers to be painted green and should as per DM standard. The word of "IRRIGATION" in
English and Arabic should be casted on the covers.
Valve chambers with depth more than 1.5 meters shall be provided with a heavy duty
Aluminium ladder.
Chamber is required for filters arrangement flow sensors and Fertilizer injection
System.
The filtration chambers shall be in reinforced cement concrete (with Proper finishing including
painting and lights) as per detailed drawings and shall be as per DM general specifications.
The access cover for filtration chamber shall be minimum 1200x1400mm overall in two
pieces of Heavy duty aluminum checkered plate with stiffeners and lifting handles and
painted green. The cover should be lockable and easy to open and should be tight to prevent
dirt or soil into the chamber. The contractor has to propose a design for the chamber to suit
the site condition.
The filtration chambers shall be provided with two spare electrical sockets (Capacity 15 kW
each) for future use.
Flushing pipe line from Filters and discharge line of sump Pump to be ended separately ten
meters away of the chamber in 2m x 2m x 3m soak pit filled with gravel or to be connected to
the nearest storm water system as per Engineer’s approval
Soak away shall have heavy duty ductile iron cover 600x900mm.
The electrical control panel shall be constructed of mild steel sheet enclosures with stainless
steel hinges and lock front opening door having a protection range not lower than IP 55
according to IEC and to be class 3. The panel shall have provision for connecting to
generator.
The Contractor should provide single phase and three phase waterproof power sockets (one
each), and three fluorescent light for filtration chamber.
The fertilizer/chemical injection unit shall comprise of 1000 litre rigid polypropylene make tank
(2 Nos.) with reinforced ribs mounted on a pedestal and a suitable dosing pump complete
with valves and fittings, filters and connecting pipes.
The elevated make up tank shall have level marks molded into the side of the tank. A second
outlet complete with stop-cock shall be provided in bottom of tank for draining and washing
out. An agitator shall be provided to ensure that there is no separation of liquids. The agitator
unit shall be removable to allow access for cleaning the tank.
The dosing pump shall be constructed of corrosion resistant material, close coupled to a
suitable splash proof electric motor. The unit shall have an operating head of 70m over the
full flow range. The injection rate shall be set manually to required flow.
The Fertilizer tank should be fixed to ground using stainless steel straps and nut/bolts
(grade 316) which will keep the tank at its place in case of flooding.
21.2.23 DUCTING
uPVC ducts shall be class B to BS3506. Asbestos cement ducts shall be class 12, to ISO-
R-160 made with sulfate resistant cement bitumen coated from outside and shall be pressure
tested.
Duct markers shall be used and should be aluminium and shall clearly indicated the name in
Arabic and English: IRR ".
Prior to trenching all services crossing or running close to the line of the trench shall be
identified and exposed. In addition the line of the trench shall be swept using an approved
detection device, capable of detecting both live and 'dead' cables.
Trenches shall be made as narrow as practicable, but not less than the pipe diameter plus
300mm, and shall provide sufficient room for laying jointing and testing. The width of the
trench at the crown of the pipe shall not exceed the pipe diameter plus 600mm. Sheeting,
bracing and shoring shall be used to provide for the safety of all personnel for all trenches.
The trench bottom shall be composed of stable uniform sand with no protuberances that
might cause point loading of the pipe. The trench formation shall be trimmed to an even
finish which will provide continuous support for the pipe. Additional excavation shall be
carried out at the position of the pipe socket to ensure proper joint assembly and pipe
support.
If the existing formation is unsuitable for direct laying, the pipes shall be laid on a bed of
imported sand 100 mm thick (minimum). This sand may be sourced from sieved excavated
material, but should not contain any particles larger than 5 mm, and should have good self
compacting properties.
De-watering shall be provided to remove any surface or ground water entering the
excavations. Ground water level shall be maintained at least 100 mm below the bottom of
each excavation.
The trench should not be excavated more than 3 days production rate in front of pipe laying.
Pipes shall be center loaded leaving joints exposed within three days of laying. Initial back-fill
shall be by hand in 300 mm lifts, and carried out in such a manner as to ensure adequate
support under the pipe and distributed evenly to ensure there are no voids under or to the
side of the pipe.
Back-fill material shall be sand and shall be compacted by water tamping once the level of
back-fill reaches the crown of the pipe.
For pipe sizes 4" ( dia ) and above , back-fill material shall be deposited in 300 mm lifts in
general areas and compacted to relative degree of compaction of 95% ( by approved method
)and tested by large pouring method. In paved areas layers shall be 150 mm and back-fill
shall be compacted layer by layer to reach relative degree of compaction of 95% to DM
roads department approval. Mechanical compactors shall not be used until there is a
minimum of 300 mm above the crown of the pipe.
Back-fill material shall be sand and shall not contain any particles larger than 25 mm for the
first 100 mm above the pipe; thereafter back-fill material shall contain no particles larger than
50 mm.
Whenever ambient temperatures exceed 35 degrees centigrade, center loading for PVC
pipes greater than 3" shall only be carried out in the early morning, or shall alternatively be
preceded by cooling of the pipe string by application of water.
For pipe sizes of 3" and below compaction as mentioned is not required.
PVC pipes shall be stored on site in a covered pipe store. Pipe stacks shall not be greater
than seven layers or two meters high. Pipes shall be shielded from the sun at all times and
shall be placed on a sand bed, or on supports at least 75 mm wide and placed not greater
than 1.50 m apart; side supports shall be similarly constructed and placed not greater than
3.00 m apart. The pipe store shall allow for circulation of air. Rubber sealing rings shall be
stored inside closed boxes in a shaded place, and shall on no account be exposed to sunlight
for more than a few hours.
Pipes shall be transported on the site on a flatbed trailer, and should never be dropped or
dragged along the ground.
Spigot ends of all pipe shall be chamfered to a depth of half the wall thickness at an angle of
15 degree. Pipes cut on site should be cut square to the pipe axis with a fine toothed saw. All
swarf and burrs should be removed from the pipe prior to assembly of joints. Pipe cutters
may be used for 1" pipe. Spigot insertion depth shall be measured and marked on all pipe
larger than 3" using indelible ink to allow checking at a later date.
Ring joints shall be made using an approved non ionic lubricant compatible with the sealing
ring. Pipes sized up to 8" may be jointed using a crowbar and a timber protection piece,
joints larger than 8" shall be assembled using a clamped lever device. Before back-filling
joints shall be checked to ensure that the spigot is inserted to at least 90% of the socket
depth in all circumstance.
Solvent welding shall be carried out by experienced fitters who fully understand the
technique, and have successfully made a solvent weld joint in the presence of, and to the
approval of the Engineer. Helpers brought up on site may only be allowed to make solvent
joints after inspection of their technique by the Engineer.
Solvent welded joints made on pipe 3" and above shall be preceded by lightly sanding both
surfaces to be jointed using a medium glass paper or clean emery cloth. Solvent "cleaner"
shall be applied to all mating surfaces using a dauber or brush (application using rags will not
be allowed). After ensuring that mating surfaces are clean and dry solvent cement shall be
applied in sufficient quantities to ensure bonding, but not in excessive quantities that will
leave appreciable residues inside the pipe.
Brush size shall be 3/8" round for 1" pipe, 1" flat for 1-1/2" pipe and 2" flat for larger pipes.
Solvent cement should be applied by two people simultaneously for pipe 3" and above.
Immediately after application of solvent cement pipes shall be pushed together in a smooth
continue motion, that ensures that the spigot is at least 90% inserted into the socket, the joint
May 2017 Page 21/43
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
shall be held for a minimum of 20 seconds after insertion, and then surplus cement shall be
cleaned from the outside of the pipe using a rag or paper. Solvent cement and cleaner shall
be provided in tins with brush or dauber fixed to the lid of the tin. The lids shall be firmly
closed at all times except when the joint is being made. Any tins of solvent cement that
become viscous or hardens shall be disregarded.
On no account shall brushes on which solvent cement has hardened be used for making
joints. All fitters involved in solvent cement jointing shall be provided with safety gloves that
prevent solvent touching the skin, gloves shall be kept in good condition and shall be
replaced periodically.
Jointing shall not be carried out in windy conditions (wind speeds greater than 18 km/hour).
All lines shall be capped at the end of the days work.
uPVC mains with sizes 8" and above shall have minimum cover of of 1.2 mete over the top
of the pipe. Mainline sizes 6" and below should have minimum cover of 1.0 meter. Pipes
should be laid in such a way it should have minimum clear space as per DM standards &
requirements from other services and trees.
Please note that uPVC lateral lines should have minimum cover of 60 cm over the crown of
the pipe. laterals should be laid in such a way it should have minimum clear space as per DM
standards & requirements from other services.
Minimum distance of uPVC Lateral lines for drip and bubblers system from the centre
line of trees shall be as follows.
Palm Trees -------------------------------------------------------2.0 metre.
Trees----------------------------------------------------------------1.5 metre.
Shrubs------------------------------------------------------------- 1.0 metre.
Drip line pipe shall be installed above ground as shown on the drawings and shall be
anchored to the ground with staple stake at every 10m.
21.3.4 VALVES
Butterfly valves, Gate valves, air valves and solenoid valves shall be installed as shown on
the drawings. Installation shall be neat tidy. Valve boxes shall be installed level and aligned
with the pavement.
Cover of the valve chambers and valve boxes shall be level and aligned with pavement as
instructed by the Engineer.
The Contractor has to follow strictly the instruction of the suppliers and provide the Engineer
with all technical information related to this equipment.
21.3.7 TESTING
May 2017 Page 21/44
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
The length of test section shall be maximum 500 m or as directed by the Irrigation Engineer.
The pipe length to be tested may be blanked off using a blank iron or steel flange previously
drilled and tapped for test equipment connection and strutted as necessary against end
thrust. The blank flange may be attached to the pipeline by a V.J. flange adopter or similar
fitting.
Testing should not be carried out against closed valves. All charging and testing should
preferably be carried out from lowest point of the under test section and all testing equipment
should be located at this point.
The pressure gauge also should be located at the lowest point or adjustment must be made
for the level of the pressure gauge relative to the pipes location.
Prior to testing, care should be taken to ensure that all anchor blocks have attained adequate
maturity and that any solvent welded joints included in the pipe system have developed full
strength. Correct support and anchorage of any above ground sections of the pipeline is also
necessary. Underground pipelines should be back-filled, taking particular care to consolidate
around lengths which may have been deflected to negotiate curves.
The main pipe should be charged slowly, preferably from the lowest point with any air cock in
the open position. They should be closed in sequence from the lowest point only when water
visibly free from aeration is being discharged through them.
Satisfactorily charged, the main should be allowed to stand overnight to allow any residual air
to settle-out. Reventing is then necessary and any water deficiency should be made-up.
Pressure testing can then begin by pumping slowly until it reaches to 9 bar. This pressure
shall be kept for 24 hours.
A permissible water loss of 3 liters per 1000m length per 25 mm nominal bore per 24 hours
shall be considered reasonable for PVC pipe.
For AC pipes the pressure test should be according the manufacturer's recommendation.
21.3.7.2 PAINTING
Dry film thickness (DFT) of all painted valves and spool pieces shall be measured on delivery
to site. DFT shall be the average of no less than three measurements, with no one
measurement less than 75% of nominal average DFT. Holiday tests shall be carried out on
internal and external surfaces on delivery, and also on external surfaces prior to back filling.
All crossings across major roads/dual carriageways and U-turns shall be either
through ducts or no dig method.
Where it is necessary to cross roads in order to complete the work, the Contractor should first
obtain N.O.C. from service companies and submit where appropriate for road cutting to DM's
road Department. The Contractor should follow strictly DM's regulations. Ducts to laid at least
100 cm below tarmac surface.
Road cutting will only be permitted if it can be proved that all forms of non destruptive method
of crossing is possible. In the event of road cutting is permitted, the reinstatement of wearing
course shall be extended to 15m from each side of the disturbed edge of trench.
Traffic diversions shall be carried out in accordance with the requirements and
approval of Engineer, Roads & Transport Authority Roads Department & Dubai Traffic
Police. If trench is left open overnight, proper lights & caution lights shall be provided.
Trenches to be back filled with fine gravel around ducts to minimum depth of 50 cm.
Remaining depth to be back filled with 15 cm thick layers of Subkha or sub grade material
with minimum 30% CBR properly compacted & tested by approved Independent Laboratory.
Only a RTA Roads Department approved sub-Contractor shall be permitted to carry out Road
reinstatement works (sub-base, base, wet-mix, asphalt, road marking etc.) and non
destruptive crossing works such as the thrust boring, directional drilling etc.
Road crossings for the main and lateral pipes or cables should be carried out preferably by
horizontal drilling. Wherever it becomes impossible to drill because of existing services or any
other reasons acceptable by Irrigation Engineer, the road cutting shall be done as specified
above.
Any tiled area damaged during construction, drilling or road cutting should be reinstated.
Separate ducts shall be used for irrigation pipes, electrical cables, control wires and maxi-
com signal wire.
At each bend, diversion or at the end of pipeline, a thrust block shall be provided. Heavy duty
polyethylene sheet shall be used to wrap the pipe at the point of contact between pipeline
fittings and the thrust block. Design of the thrust blocks shall be done by the Contractor and
to be approved by the Engineer.
All the electrical installations shall operate at a system voltage of 380 volts AC three phase
four wire 50 cycles.
The entire works shall be carried out in strict accordance with this specification and
instruction as issued by the Dubai Electricity and Water Authority.
Each electrical equipment, cable and complete system shall be thoroughly inspected and
tested before finally placing in service under the full responsibility of the Contractor. All tests
shall be made in compliance with respective regulations, recommendations and standards.
Any modifications or repairs deemed necessary upon completion of the tests shall be
executed at the Contractor's expenses. Further tests shall be carried out on any modified or
repaired equipment until it is certified trouble free and acceptable for its intended service. All
testing shall be demonstrated to the Engineer in a manner to be agreed later.
All electrical equipment under these contract documents shall have passed adequate routine
May 2017 Page 21/46
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
factory tests. Field tests shall be made by qualified personnel, approved by the Engineer.
The Contractor shall furnish all apparatus, material, labour and facilities for performing the
required tests. Unless otherwise specified the individual electrical equipment shall undergo
the following tests in accordance with the IEC recommendations or other approved
standards.
In Workshop:
- High voltage test
- Check on mechanical function
- Pre-test of functional sequences
At Site:
- Visual inspection
- Insulation test (megger test)
- Check of functional sequences
The Contractor shall submit to the Engineer acceptance test certificates of all tests carried out
in his workshop including all measuring data and subsequent evaluation.
The following tests are to be carried out for all cables as a minimum:
- Resistance measurements
- Insulation test with specified AC power frequency test voltage
- Insulation resistance measurement of every individual cable length at site
- Electrical continuity test for all controls.
The following test shall be carried out upon completion of the earthing system:
The Contractor shall provide at his expense the necessary qualified personnel and measuring
instruments of the above measurements.
Panels shall be installed onto concrete bases (300mm above ground level). Control wire shall
be color coded, and provided with tags. Control cable shall be bundles and tied with a plastic
cable tie at least every 5 meters, installation of cable bundles in conduit shall be carried out in
such a way as to preclude the possibility of stretching the cable, or damaging the insulation.
All cable splices shall be waterproof, and made inside valve or conduit boxes, leaving at least
one meter of spare cable neatly coiled at each joint, and bend.
Panels shall be individually earthed by an approved copper clad grounding rod minimum
length 15 mm x 3 meter rod driven down into the water table and connected to the controller
by a brass clamp and a 4 mm2 grounding wire as per DEWA and engineer approval.
All stages of the control system installation shall be supervised by a factory-trained engineer,
recommended by the manufacturer who has previously been in charge of all aspects of
installation of a similar control system and approved by the engineer.
The field satellite controllers shall be installed near the Pump/Filtration Chamber. Controller
shall be installed on the concrete bases (300mm above ground level) and shall be in pedestal
enclosure as specified, control wire shall be color coded, and provided with tags.
Control cable shall be bundles and tied with a plastic cable tie at least every 5 meters,
installation of cable bundles in conduit shall be carried out in such a way as to preclude the
possibility of stretching the cable, or damaging the insulation.
All cable splices shall be waterproof, and made inside valve or conduit boxes, leaving at least
one meter of spare cable neatly coiled at each joint, and bend.
Controllers shall be individually earthed by an approved copper clad grounding rod minimum
length 15 mm x 3 meter rod driven down into the water table and connected to the controller
by a brass clamp and a 4 mm2 grounding wire. Decoders, encoders, and terminators shall
be installed in plastic valve boxes, and their function and reference number shall be clearly
indicated in indelible ink.
21.4.1 FLUSHING
21.4.2 FIELDWORK
Commissioning of fieldwork and equipment shall include all works required to bring the
system into service, and to make sure that it is operating efficiently, and shall include but not
be limited by the following:-
3. Adjust sprayer to ensure spray onto pavement and paths is minimized. Replacing any
spray nozzles that have uPVC burrs, or sand lodged inside. Adjust spray patterns to
ensure optimal coverage.
4. Ensure that all sprayers and valve boxes are flush with the finish grade.
5. Replacing any clogged or partially clogged emitters(delivering less than 50% of nominal
flow) or any emitter overflowing by more than 50% (squirting). Carrying out emission
uniformity test involving at least 40 emitters on up to 10 valves, as directed by the
Engineer.
6. Controllers shall be adjusted to give an optimal flow regime, generally in accordance with
the drawings and as instructed by the Engineer. Valves sequence may be modified to
ensure that valves operate in a logical sequence to facilitate maintenance operations.
7. Irrigation cycles for sprinklers and sprayers should be programmed during night time and
early morning (from 12 mid night up to 5 am).
A full cycle shall be run four times, and total system flow rates shall be recorded, and stations
shall be adjusted in accordance with the instructions of the Engineer, base on the results of
these trials.
Trials shall only be carried out after all valve's pressure have been adjusted. During these
trials main line head losses shall be verified by installing pressure recorder at the start and
the end of the main line.
Three standard irrigation schedules shall be developed in accordance with the requirements
of the Engineer, and tested per controller schedule as above. Each particular function of the
system shall be demonstrated in accordance with an approved commissioning procedure
developed by the Contractor.
Operational and maintenance manuals shall be prepared and submitted for approval in draft
form prior to commencement of commissioning. Manuals shall contain comprehensive
operational schedules, recommended spare parts list, manufacturers' operating data,
Catalogues and exploded parts diagrams where applicable for the entire irrigation scheme.
The materials used for the system shall be listed in the manual.
Manuals shall be revised in accordance with Engineers instructions, and reflect, and record
the results of the commissioning procedures described above. Three bound copies of the
manual shall be delivered to the Engineer prior to the date of substantial completion
certificate issuing.
The Contractor must submit As-Built drawings for all works included in this contract.
Completion certificate will not be issued unless the contractor submits the As-Built drawings.
Three complete set of "As Built" drawings along with a negative and all diskettes should be
submitted before handing over of the project.
The civil works of the project shall be carried out by Main contractor or an approved
sub-contractor as per general specifications of Dubai Municipality and subject to
approval of the Engineer.
21.5.1.1 PRE-EXCAVATION
b) Contractor shall check with all the concerned Service Authorities for any existing buried
plants inside the excavation site. Contractor shall be responsible for any damages of
service plants caused by excavation.
d) Top soil and other surfacing materials shall be stopped and stored separately from the
subsoil. Subsequent spreading of top soil shall be as directed on site.
21.5.1.2 All excavated material shall be deposited so that it will cause as little damage and
inconvenience as possible. Different classes of material shall be handled and deposited
separately.
21.5.1.3 Excavated material for use as back-fill shall be as approved, and shall be kept in a suitable
safe place and surrounded by a suitable fence as directed by the Engineer.
21.5.1.4 Where ordered if necessary for reasons of limited access or any other reason, excavation
shall be carried by hand.
21.5.1.5 All excavation shall be kept free of water. In addition, precautions shall be taken to prevent
floatation of partly built structures, completed structures to be filled on commissioning of the
works and unback-filled pipelines. All necessary precautions shall be taken to prevent any
adjacent ground from being adversely affected by loss of fines through any dewatering
process.
21.5.1.6 The sides and or the bottom of excavation shall be adequately supported.
21.5.1.7 Back-filling shall be carried using selected excavated materials and in layers not greater than
150 mm thick (compacted thickness) and compacted such that throughout each layer placed
the dry density is not less than 95% of the site dry density of the soil prior to excavation.
Back-filling shall be tested to ensure the specified compaction.
21.5.1.8 All surplus material shall be either spread on site or shall be removed and disposed off the
approved Municipality tips, immediately after excavation as directed by the Engineer.
21.5.1.9 In case of extra excavation deeper than the level required by the Engineer, Contractor shall
fill the same with selected well-compacted material or plain concrete as directed by the
Engineer.
21.5.1.10 Excavation to the required level shall be carried out by the contractor as part of the contract
regardless of the kind of soil strata or rock to be excavated.
21.5.1.11 Contractor shall bear the responsibilities and consequences of any damage caused by the
excavation to the adjacent structures, roads or plants.
21.5.1.12 Contractor shall take all the necessary precautions at the excavated sites to protect his own
staff, Engineer's representative, site visitors, pedestrians, traffic movement by supporting
excavation sides, providing proper guard rails fences, cones, warning tapes and traffic signs,
and by keeping 24 hrs. guard attendance to all excavated locations.
Contractor shall bear all the legal responsibilities in case of accidents caused by lack of
safety precautions.
21.5.2 CONCRETE
21.5.2.1 GENERAL
a) All materials forming the concrete mix shall be approved by the Engineer.
b) Complete detailed design of all the reinforced concrete structures shown on drawings
shall be carried out by the Contractor following the relevant British Standard. Drawings
and calculation shall be submitted to the Engineer and subject to his approval. However,
it shall be understood that the Engineer's approval of the design and calculation does not
release the Contractor from his responsibility in case of any structural failure due to
design faults.
GRADE
-------------------------------------------------------------------------------------------------------
B C
------------------------------------------------------------------------------------------------------
NOMINAL MAX. 20 20
May 2017 Page 21/50
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
AGGREGATE SIZE mm
-------------------------------------------------------------------------------------------------------
3
CEMENT CONTENT kg/m of
FINISHED CONCRETE
MINIMUM 370 300
MAXIMUM 400 400
-------------------------------------------------------------------------------------------------------
MAX. WATER CEMENT RATIO 0.45 0.45
-------------------------------------------------------------------------------------------------------
2
MIN. MEAN CUBE STRENGTH N/mm 35 25
-------------------------------------------------------------------------------------------------------
FINE AGG./TOTAL AGG.% MAX. 35 35
-------------------------------------------------------------------------------------------------------
e) Immediately following the land excavation to formation level for floor where shown on the
drawing or as ordered by the Engineer, a sealing coat of 75 mm minimum thickness of
concrete grade "c" shall be placed on polyethylene sheet (1000 gauges) placed on the
surface of the formation a carefully spade finished to an even surface floors shall be laid
on the sealing coat as soon as may be practicable and if required by the Engineer, the
sealing coat shall be kept thoroughly damp by watering.
f) Unless tolerances for particular surfaces are specifically shown on drawings, they shall
be as follows:
1) FLOORS: The level of the surface at any point shall be plus or minus 5 mm of the level
desired from drawings.
2) WALLS: The position of the face at any point shall be within 10 mm of its position desired
from the drawings. There shall be no irregularity exceeding 3 mm in 3 meter template.
3) CURVED SURFACES: Shall be within plus or minus 2 mm of the level desired from the
drawings.
g) Concrete shall not be placed when the sheds temperature exceeds 40 degrees C.
The temperature of batched concrete at time of placing shall not exceed 30 degrees C.
21.5.2.2 MATERIALS
a) AGGREGATES:
Coarse aggregate shall consist of crushed stones free from salt and clay or any other
materials harmful to the concrete such as organic, coal, mica, gypsum and fines. In any case
the percentage of fines shall not exceed 1% of the dry weight.
Fine aggregate shall consist of Natural Sand with hard grains of any other similar inert
material. Sand shall be free from organic, salts, clay, mica and fossils. It shall also be sieved
and washed.
Percentage of Sulphate and Chloride in aggregates shall not exceed the figures listed in the
following table:
Chloride as Na Cl 0.01 %
Chloride as Cl 0.06 %
May 2017 Page 21/51
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
b) CEMENT:
Cement shall be supplied from approved factories in closed bags. In case of bulk cement
supply, it shall be delivered using special containers for the same purpose. Cement shall
always be accompanied with its origin certificate showing its test results and date of
manufacture.
When stored on site, cement shall be kept in a dry place raised above the floor and not
touching the walls of the store. It shall not be allowed to use the cement which is more than 4
months old, nor that which has hardened in the form of grains regardless of its age.
Ordinary Portland Cement shall be used for all concrete works unless it is otherwise specified
in any of the contract documents.
c) WATER:
Water used for the concrete mix and aggregate washing and cleaning of formwork and curing
of casted concrete shall be a potable water. In any case it shall comply with the following
conditions:
1) Should be clean and free from oil, organic, metals, acids and bases.
2) Should not contain more than 600 mg/l of Chlorides or 500 mg/l of Sodium Sulphate.
In general, mixing water shall not contain any harmful materials which is sufficient to change
the concrete setting time by more than 25% or to decrease the concrete compressive
strength by more than 20% of that which is made of distilled water.
d) ADMIXTURES:
Concrete admixture shall be used in case it is specified in any of the contract documents. In
case the Contractor requires to use any of them (such as plasticizer and retarders), it shall be
subject to the Engineer's approval who might require a modified concrete mix design to suite
the used admixture.
e) REINFORCING STEEL:
Reinforcement shall be epoxy coated and free from rust or other extraneous matters. They
shall be cut and placed as detailed in the drawings and as approved by the Engineer.
Concrete shall be mechanically mixed until getting a homogeneous viscosity and color mix.
Mixing time shall not be less than two minutes or twenty revolutions of the mixing machine or
which ever is greater. Mixing time is considered to start when all the contents of the concrete
mix including the mixing water are loaded inside the mixer. Concrete mix unloading shall be
carried out in such a way that will not cause separation of the mix contents.
The Contractor shall make the standard concrete cube and test them as directed by the
engineer for all the structural concrete elements.
Number of cubes and method of their making and testing shall comply with the relevant
British Standard.
21.5.5 TRANSPORTATION
In case of pre-mixed concrete, the concrete shall only be transported to the casting site, using
special containers equipped for the same purpose to prevent the separation of the materials
forming the concrete mix.
Concrete casting shall always be subject to the written approval of the Engineer on the
reinforcing steel and suitability of the concrete mold and formwork and supports.
Reinforcement and mold shall be sprayed with water prior to casting. It shall not be allowed
to cast the concrete which was mixed before more than 30 minutes unless plasticizing agents
are used, in such cases the time allowance shall be decided by the Engineer.
All concrete works shall be compacted during casting using mechanical vibrator. Care shall
be taken so that the vibrator's rod does not touch the reinforcements or the mold. In any
case, the casted concrete which has started setting should not be distributed as a result of
casting or working nearby.
21.5.9.1 Movement joints or construction joints in concrete shall be provided as directed by the
Engineer.
21.5.9.2 Water Bars shall be manufactured of extruded PVC or of nitrile rubber. They shall be of the
types and general shape indicated on the drawings and shall have the minimum
characteristics:
3
DENSITY: 1300 kg/m
WEB THICKNESS: 10 mm
Water bars shall not be displaced during the placing of concrete which shall be fully
compacted around them. Jointing of water bars shall normally be carried out by clamping and
welding or adhesion and shall be in accordance with the recommendations of the
manufacturer. Water bars shall be arranged so that there is a minimum distance of 25 mm
from the water bars to the reinforcement.
21.5.10.1 Unless tolerances for particular surfaces are specifically shown on drawings, they shall be as
follows:
FLOORS: The level of the surface at any point shall be plus or minus 5 mm of the level
desired from drawings.
WALLS: The position of the face at any point shall be within 10 mm of its position desired
from the drawings. There shall be no irregularity exceed 3 mm in to 3 m template.
CURVED SURFACES: Shall be within plus or minus 2 mm of the level desired from the
drawings.
21.5.10.2 As directed by the Engineer, contractor shall repair or demolish and re-build the concrete
works which had any concrete quality or dimension or reinforcement or segregation defects,
or any other defects that the Engineer might decide they cause the concrete to be
unsatisfactory to its required purpose. In case of repair, its method and results shall be
subject to the Engineer's approval.
21.5.10.3 Where required by the Engineer, the Contractor shall fill cracks which have developed in
concrete structures using an approved resin based sealing compound. Method of injection
may include pressurized injection techniques.
21.5.11.1 Formwork shall be designed and constructed so that the concrete can be placed and
compacted without disturbing or displacing the reinforcement. It shall be firmly supported,
braced, guyed or tied back so that it is stable against vertical and horizontal formwork.
Internal spacers and ties shall be of approved types that do not produce holes completely
through the concrete. Joints in the formwork should be close fitting to prevent leakage.
The arrangement shall allow for removal of formwork from the sides and members without
disturbing soffit formwork. Rough faced formwork may be used for surfaces which are
normally never exposed to view.
Formwork shall be designed so that splays, fillets, chamfers and projection are cast as the
work proceeds. Unless specifically deleted all external angles on exposed concrete shall
have a 25mm x 25mm chamfer.
Before placing concrete all extraneous material shall be removed from the interior of the
formwork and the faces in contact with the concrete shall be wetted or treated with a non-
staining composition to prevent adhesion.
Concrete shall be placed in the formwork only after examination and approval of the formwork
by the Engineer.
21.5.11.2 Formwork shall not be struck until the structure has attained sufficient strength and in no case
less than the period given below:
21.5.11.3 CONCRETE SPACERS AND COVERING BLOCKS The minimum possible number of
concrete spacers and covering blocks which provides the concrete covers for the reinforcing
steel, shall be made of concrete which has same compressive strength of that to be casted.
For the planting areas, Contractor shall clear all rubbish and remove the existing topsoil and
dispose off as directed and prepare the area to receive sweet soil, in such a way that it will
below 60 cm than the proposed final level of landscape/existing and proposed footpath The
Contractor has to refer to the landscaping drawings. Levelling and contouring shall be done as
per the Landscape drawings and to the approval of the Engineer. The minimum acceptable
depth of sweet soil filling in proposed planting area is 50 CM. Sweet soil levels should be10
cm below the existing/proposed foothpaths and chamber levels
Contractor will remain responsible for maintaining the levels of sweet soil against wind erosion
till the final hand over of the project.
Contractor to make tree pits and fill them with fresh sweet soil. The size of tree pits to be as
follows:
THE EXISTING SWEET SOIL SHOULD NOT BE USED FOR FILLING THE TOP 50 CM
LAYER AND TREE PITS.
21.6.2 CONTOURING
The Contractor has to level the landscaped areas and bring it to the contours as shown in the
landscaping drawings. Contractor to make arrangements to prevent the loss/ drifting of soil
due to wind. Contractor will be responsible for maintaining the levels and contours of the
sweet soil till the Final Handing over of the project.
21.6.3 GRAVEL
Gravel shall be white to light beige crushed gravel (to Engineer’s approval) size 10 - 20mm to
fill the areas as shown on the landscape drawings. The Depth of gravel mulch shall be at least
10 cm.
Wadi gravel shall be naturally occurring water rounded stones of approved origin. Stones
shall range from 50mm to 100mm diameter and shall be washed and free of sand, debris and
fine material. Color shall be brown.
A layer of geotextile filter fabric is to be installed on prepared ground formation below the
gravel bed layer/ gravel mulch in tree areas and where directed by the Engineer. A minimum
of 300mm overlap shall be provided at junctions between strips and roll ends. The fabric shall
be secured by steel pegs at maximum 3m intervals prior to covering with gravel layer.
The geotextile filter fabric shall be U. V. resistant and resistant to all naturally occurring soil
acids and alkalis and be non degradable.
The fabric membrane shall be manufactured from bonded non-woven or woven continuous
filament synthetic fibers.
The fabric shall be pliable and strong enough not to be damaged during placement and
subsequent backfilling yet permeable without clogging by possible ingress of fine particles and
flying sand.
The geotextile filter fabric shall be approved by the Engineer. The fabric shall not be
punctured, torn or otherwise damaged in any way during installation.
The contractor shall modify the existing chambers in the proposed Landscape area (if
required) to the approval of the Engineer and the concerned service authorities in order to
match the proposed landscape levels.
The Contractor has to use cream white crushed gravel size 20mm to fill the areas as shown
on landscape drawings. Depth of filling with gravel shall be at least 10 cm. Gravel shall be
installed on Geotextile membrane.
This works shall consists of covering certain areas (Top of filtration chamber and 1.0 meter
around and 0.6 metre wide strip by the side of road kerbs all around landscape areas) with
paving blocks and heel kerbs in accordance with specifications, the drawings and Engineer’s
instructions.
Paving blocks and heel kerbs shall be as per D.M. Roads Department standard Specification.
Paving blocks type shall be matching type available in the vicinity and/or as approved by RTA
Roads Department Services Co-ordination office all as per RTA Roads standard
specification.
The materials, dimensions and tolerances, test for comprehensive strength, test for water
absorption and certificate of compliance for the paving blocks shall conform to the
requirements of Local Order of 44/90. Water absorption and abrasion resistance shall be
carried out in accordance with the requirements of particular specifications.
The laying course shall consists of sharp black sand containing not more than 3% silt and
clay by weight and not more than 10 % retained on 4mm sieve. The sand shall be obtained
from single source, allowed to drain before use and shall be covered with suitable sheetings
to minimize moisture changes. Permissible sulphate (as SO3) and chloride (as Cl) shall not
exceed 0.3% and 0.5% respectively (expressed as a percentage by weight.).
21.7.4.2 The profile of laying course before compaction shall be similar to that of finished surface.
During laying, the sand shall be in uniform moisture content and screened carefully.,
screened to form smooth compacted surface to receive the paving blocks. The maximum
deviation from design shall be 5 mm.
21.7.4.3 The edge restrained to the paved areas shall be laid in advance of the laying course and all
permanent obstacles within the area, such as manhole covers shall be adjusted to the correct
finished levels.
SURFACE COURSE
21.7.4.4 The paving blocks shall be laid on sand laying course in such a manner as not to disturb the
blocks already laid. Each block shall be placed firmly against its neighbour so that they fit
closely together. The joints between the blocks shall exceed 3 mm. Laying of paving blocks
shall commence at right angles to the main pavement axis starting at one end of the area.
The paving blocks shall be laid in a herringbone pattern unless otherwise shown on the
drawings or instructed by the Engineer at 45 deg angle to main pavement axis.
21.7.4.5 Where blocks do not fit the edge restraints or other obstructions such as manholes or
upstands the gaps shall be filled using cut blocks.
21.7.4.7 Dimensional accuracy, uniformity of joint gaps alignment and squareness shall be checked
after laying the first three layers of the blocks and thereafter at regular intervals. If joints begin
to open, the blocks shall be knocked together using a hide mallet.
21.7.4.8 After every 20 sq. m or such areas that has been agreed with the Engineer, has been laid the
blocks shall be compacted to the required levels using plate vibrator.
2
21.7.4.9 The plate vibrator shall have a plate area of 0.2 to 0.35 m . and have compaction force of 12-
24 kN and a frequency of approx. 75 to 100 Hz.
21.7.4.10 A minimum of two passes of plate vibrator shall be made in each direction i. e. at 90 deg to
each other. Vibration shall continue until no further compaction of sand layer is apparent. The
laying course shall have compacted thickness of 50 mm. Fine dry sand with particle size of
0.3 mm shall be then brushed over paving. And further passes of plate vibrator shall be made
in each direction, until sand is no longer absorbed in the joints.
21.7.4.11 The plate vibrator shall not pass closer than 1 mtr to a temporarily unrestrained edge during
laying.
21.7.4.12 No paving shall be left uncompacted overnight except for the 1mtr strip at the temporarily
unrestrained edge.
21.7.4.13 On compaction the finished surface level shall be within 5 mm of the design level and
maximum deviation within the compacted surface, measured by 3 mtr straight edge shall not
exceed 3mm. The level of any two adjacent blocks shall not differ more than 3 mm. Any
areas of paving which do not comply with these tolerances shall be removed. The sand laying
course adjusted and paving blocks re-laid to the correct levels.
21.7.5.1 This work shall consist of the construction of kerbs in accordance with specifications and in
conformity with the lines grades and typical sections shown on the drawings or established by
the Engineer. These specifications refer to the following types of precast kerbs to be
constructed: Non mountable Kerbs, Dropped kerbs, Heel kerbs, Quadrants and Flush kerbs.
All kerbs and edgings shall be hydraulically pressed and shall comply with the requirements
May 2017 Page 21/57
R1048: Improvements of EXPO 2020 Roads Network
Drainage and Irrigation Specifications Volume 2 Part III
of BS7263 Part 1. They shall be uniform in colour, free from cracks, flaws or other defects
and they shall have well defined arises.
21.7.6.1 Materials shall confirm to the requirements specified in part 4 “concrete” of the specifications
and as specified here in.
21.7.7.1 A Layer of geotextile filter fabric is to be installed on prepared ground formation below the
gravel bed layer/gravel mulch in areas shown on contract drawings and where directed by the
Engineer. A minimum of 300mm overlap shall be provided at junctions between strips and roll
ends. The fabric shall be secured by steel pegs at maximum 3m intervals prior to covering
with gravel layer.
The geotextile filter fabric shall be U.V resistant and resistant to all naturally occurring soil
acids and alkalis and be non degradable.
The fabric membrane shall be manufactured from bonded non-woven or woven continuous
filament synthetic fibers.
The fabric shall be pliable and strong enough not to be damaged during placement and
subsequent backfilling yet permeable without clogging by possible ingress of fine particles
and flying sand.
The geotextile filter fabric shall be approved by the Engineer. The fabric shall not be
punctured, torn or otherwise damaged in any way during installation.
ANNEX – I