Professional Documents
Culture Documents
1.Prepare an organizational chart depicting the construction process. Identify parties involved, their
functions, responsibilities and connection with each other.
An organizational chart depicting the construction process is shown below.
ID Task name Duration Start Finish
1 Start 0 days Mon 6/24/13 Mon 6/24/13
2 Mobilize 10 days Mon 6/30/13 Wed 7/10/13
3 Site Storm Drainage 44 days Mon 7/1/13 Tue 8/13/13
4 Site Water Lines 20 days Mon 7/1/13 Fri 7/19/13
5 Site Sanitary Lines 15 days Mon 7/1/13 Mon 7/15/13
6 Clear/Cut/Strip Site 15 days Mon 7/1/13 Mon 7/15/13
7 Survey & Layout 15 days Mon 7/1/13 Mon 7/15/13
8 Rebar Drawings & Fabrication 20 days Mon 6/30/13 Sat 7/20/13
16. What is the purpose of manufacturer association and how do they accomplish their purpose