ID

Task Name
Duration
Start
Finish
Predecessors

Tahap Persiapan
3,63 days
Mon 04/01/16
Thu 07/01/16

Site Clearing
1 day
Mon 04/01/16
Mon 04/01/16

Pengukuran dan Pemasangan Bow Plank

0,5 days
Tue 05/01/16
Tue 05/01/16
2

Pekerjaan Rumah jaga dan Bedeng Buruh


1,13 days
Tue 05/01/16
Wed 06/01/16

Mobilisasi Material
0,38 days
Tue 05/01/16
Tue 05/01/16
3

Pembuatan Rumah jaga


0,75 days
Tue 05/01/16
Wed 06/01/16
5

Pembuatan bedeng buruh


0,75 days
Tue 05/01/16
Wed 06/01/16
6SS

Pekerjaan Direksi Keet dan Gudang Kerja


2,13 days
Tue 05/01/16
Thu 07/01/16

Mobilisasi Material
0,38 days
Tue 05/01/16
Tue 05/01/16
5SS

10

Pembuatan Gudang Kerja


1 day
Wed 06/01/16
Thu 07/01/16
5SS;7

11

Pembuatan direksi keet


1 day
Wed 06/01/16
Thu 07/01/16
5SS;7

12

Pekerjaan Tanah
36 days
Thu 07/01/16
Fri 26/02/16

13

Pekerjaan Galian Tanah


0,25 days
Thu 07/01/16
Thu 07/01/16
11

14

Pekerjaan Timbunan Tanah


0,25 days
Fri 26/02/16
Fri 26/02/16
31FS+7 days

15

Pekerjaan Pengangkutan Tanah


0,25 days
Fri 26/02/16
Fri 26/02/16
13;14

16

Pekerjaan Bor Pile


4,25 days
Thu 07/01/16
Thu 14/01/16

17

Pekerjaan Mobilisasi Beton Ready Mix


0,38 days
Mon 11/01/16
Tue 12/01/16
21

18

Pekerjaan Mobilisasi Alat Berat


0,38 days
Thu 07/01/16
Fri 08/01/16
13

19

Pekerjaan Pengeboran
0,75 days
Fri 08/01/16
Fri 08/01/16
18

20

Pekerjaan Pembersihan Lubang Bor


0,25 days
Mon 11/01/16
Mon 11/01/16
19

21

Pekerjaan Pemasangan Besi Beton dan Pipa Tremi


0,5 days
Mon 11/01/16
Mon 11/01/16
20

22

Pekerjaan Pengecoran
2 days
Tue 12/01/16
Thu 14/01/16
17

23

Pekerjaan Beton
17 days
Mon 25/01/16
Wed 17/02/16

24

Pekerjaan Pile cap


2 days
Mon 25/01/16
Wed 27/01/16

25

Pekerjaan Bekisting Pile cap


1 day
Mon 25/01/16

Tue 26/01/16
22FS+7 days

26

Pekerjaan Pembesian
1,5 days
Mon 25/01/16
Tue 26/01/16
25SS

27

Pekerjaan Pengecoran
1 day
Tue 26/01/16
Wed 27/01/16
25

28

Pekerjaan Abutment
10 days
Wed 03/02/16
Wed 17/02/16

29

Pekerjaan Bekisting Abutment


5 days
Wed 03/02/16
Wed 10/02/16
30SS

30

Pekerjaan Pembesian Abutment


8 days
Wed 03/02/16
Mon 15/02/16
24FS+5 days

31

Pekerjaan Pengecoran Abutment


2 days
Mon 15/02/16
Wed 17/02/16
30

32

Pekerjaan Baja
12,75 days
Wed 17/02/16
Fri 04/03/16

Page 1

ID
Task Name
Duration
Start
Finish
Predecessors

33

Pekerjaan Girder
12,75 days
Wed 17/02/16
Fri 04/03/16

34

Pekerjaan Mobilisasi Girder


0,75 days
Fri 26/02/16
Fri 26/02/16
31FS+7 days

35

Pekerjaan Pemasangan Girder dan sambungan

5 days
Fri 26/02/16
Fri 04/03/16
34;36

36

Pekerjaan Perletakan
2 days
Wed 17/02/16
Fri 19/02/16
31

37

Pekerjaan Perkerasan
3,5 days
Mon 07/03/16
Fri 11/03/16

38

Pekerjaan Mobilisasi Material


0,5 days
Mon 07/03/16
Tue 08/03/16
35FS+1 day

39

Pekerjaan Pemasangan Bantalan Kayu


1 day
Tue 08/03/16
Wed 09/03/16
38

40

Pekerjaan Pemasangan Baja Rel dan Pengelasan


2 days
Wed 09/03/16
Fri 11/03/16
39

41

Pekerjaan Finishing
6 days
Mon 14/03/16
Tue 22/03/16

42

Loading Test dan Vibration Test


6 days
Mon 14/03/16
Tue 22/03/16
40FS+1 day

43

Pembongkaran direksi keet, bedeng, pos jaga dan gudang


3 days
Thu 17/03/16
Tue 22/03/16
42FF