ID

Task Name

Duration

Start

Finish

START OF PROJECT

782 days

Sun 1/1/12

Thu 2/20/14

35 days

Sun 1/1/12

Sat 2/4/12

431 days

Sun 1/8/12

Wed 3/13/13

Wed 3/13/13

PRECONSTRUCTION MEETING

PROJECT CONSTRUCTION STAGE I

GENERAL REQUIREMENT

431 days

Sun 1/8/12

16

RELOCATION

171 days

Sun 1/29/12

Tue 7/17/12

27

AIRSIDE WORKS

417 days

Sun 1/22/12

Wed 3/13/13

LANDSIDE WORKS

279 days

Sun 1/22/12

Fri 10/26/12

1
- -

M1

M2

M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M13
M14
M15
M16
M17
M18
M19
M20
M21
M22
M23
M24
M25
M26
M27
M28
M29
M30
M31
M32
M33
M34
M35
M36
1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 5 5 5 5 5 5 5 5 5 5 6 6 6 6 6 6 6 6 6 6 7 7 7 7 7 7 7 7 7 7 8 8 8 8 8 8 8 8 8 8 9 9 9 9 9 9 9 9 9 91 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

215

216

217

Earthwork

66 days

Sun 1/22/12

Tue 3/27/12

220

Pavement

10 days

Wed 3/28/12

Fri 4/6/12

228

Landside Drainage works

32 days

Wed 3/28/12

Sat 4/28/12

240

Fence Works

37 days

Sat 4/7/12

Sun 5/13/12

252

Road Marking Works

7 days

Sat 4/7/12

Fri 4/13/12

1 day

Sat 4/7/12

Sat 4/7/12

254

Traffic Sign Works

267

Building Works

210 days

Wed 3/28/12

Tue 10/23/12

294

Landscape Works

114 days

Sat 4/7/12

Sun 7/29/12

302

Security system (Commissioning and SAT)

3 days

Wed 10/24/12

Fri 10/26/12

305

Landside works completion

0 days

Fri 10/26/12

Fri 10/26/12

0 days

Wed 3/13/13

Wed 3/13/13

344 days

Thu 3/14/13

Thu 2/20/14

Thu 2/20/14

306

PROJECT STAGE 1 COMPLETE

10/26

3/13

307

308

PROJECT CONSTRUCTION STAGE 2

309

GENERAL REQUIREMENT

344 days

Thu 3/14/13

318

AIRSIDE WORKS

300 days

Thu 3/28/13

Tue 1/21/14

35 days

Thu 4/11/13

Wed 5/15/13

319

Soil Replacement

324

Pavement

135 days

Thu 3/28/13

Fri 8/9/13

353

Coastal protection

221 days

Thu 4/11/13

Sun 11/17/13

367

Navigation, Telecomm, Meteo and Airfield Lighting

300 days

Thu 3/28/13

Tue 1/21/14

389

Airside Works Completion

0 days

Tue 1/21/14

Tue 1/21/14

330 days

Thu 3/28/13

Thu 2/20/14

0 days

Thu 2/20/14

Thu 2/20/14

2/20

0 days

Thu 2/20/14

Thu 2/20/14

2/20

1/21

390

391

LANDSIDE WORKS

454

PROJECT STAGE 2 COMPLETE

455

456

PROJECT COMPLETE

Task

Progress

Summary

Rolled Up Critical Task

Rolled Up Progress

External Tasks

Group By Summary

Critical Task

Milestone

Rolled Up Task

Rolled Up Milestone

Split

Project Summary

Deadline

Page 1