COMFORT CRAFTS Project start: Wed, 2/7/2024

Project Schedule Display week: 1

Feb 12, 2024 Feb 12, 2024 Feb 19, 2024 Feb 26, 2024 Mar 4, 2024 Mar 11, 2024 Mar 18, 2024 Mar 25, 2024 Apr 1, 2024 Apr 8, 2024 Apr 15, 2024 Apr 22, 2024 Apr 29, 2024 May 6, 2024 May 13, 2024 May 20, 2024 May 27, 2024 Jun 3, 2024
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9
TASK ASSIGNED TO PROGRESS START END
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
developig the product 100% 2/7/24 2/9/24

prepare part 1 requirements 100% 2/9/24 2/9/24

formulate business plan 100% 2/10/24 2/17/24

Consultation 90% 2/19/24 2/19/24

product sketch drawing 90% 2/20/24 2/27/24

schedule a gnatt chart 70% 2/28/24 3/1/24

Component drawing 100% 3/2/24 3/5/24

consulation 100% 3/6/24 3/6/24

do an exploded view of the drawing 100% 3/6/24 3/10/24

make a list of make/by 80% 3/11/24 3/13/24

Part 1 Submission 100% 3/14/24 3/14/24

prepare part 2 requirements 70% 3/15/24 3/17/24

prepare a production routing 82% 3/18/24 3/25/24

draw assembly chart 76% 3/26/24 4/2/24

draw a flow chart 67% 4/3/24 4/8/24

draw a operation process chart 69% 4/9/24 4/13/24

draw a master flow flow diagram 55% 4/14/24 4/18/24

design evaluation sheet 75% 4/18/24 4/22/24

consulation 60% 4/22/24 4/22/24

Part 2 Submission 100% 4/25/24 4/25/24

prepare requirements for part 3 60% 4/25/24 4/28/24

draw a relationship chart 50% 4/29/24 5/3/24

design a warehouse including storeroom,shipping etc 70% 5/4/24 5/10/24

show offices,maintenance 60% 5/11/24 5/16/24

workplace/workstation design 50% 5/17/24 5/24/24

Layout plan & Area allocation 50% 5/24/24 5/25/24

Layout constrution 70% 5/25/24 5/29/24

consulation 75% 5/30/24 5/30/24

Part 3 Submission 100% 6/3/24 6/3/24