PROJECT MANAGER AC
1 Project Initiation
Research data points on reservation systems
1.1 1/8/18
and enhancement
3 Planning
Create contracts and statements of work for
3.1 2/12/18
vendors
1
4.5 Create troubleshoot/support plan 2/20/18
4.6 Launch day 3/1/18
2
t Plan
m Implementation: Sauce and Spoon COMPANY NAME Sauce and Spoon
DATE 1/1/18
PHASE ONE
DURATION PCT OF TASK
DUE DATE WEEK 1 WEEK 2 WEEK 3
(DAYS) COMPLETE
M T W R F M T W R F M T W R
1/15/18 7d 100%
1/15/18 0d 100%
1/17/18 2d 100%
1/18/18 1d 100%
1/19/18 1d 100%
1/26/18 4d 100%
1/29/18 0d 100%
2/2/18 4 100%
2/5/18 3 100%
2/9/18 4 100%
2/9/18 4 100%
2/10/18 4 100%
2/15/18 3 100%
2/13/18 0 100%
2/28/18 13 100%
2/25/18 10 100%
2/25/18 7 100%
2/22/18 2 100%
2/23/18 0 100%
2/24/18 0 100%
2/25/18 0 100%
3
2/25/18 5 100%
3/1/18 0 100%
4
PHASE TWO PHASE THREE
WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8
F M T W R F M T W R F M T W R F M T W R F M T W
5
6
PHASE THREE PHASE FOUR
WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12
R F M T W R F M T W R F M T W R F M T W R F
7
8