Professional Documents
Culture Documents
: 7 MISCELLANEOUS
(ALL QUANTITIES ARE PROVISIONAL)
7.2.1 Allow for search of known records to identify the nature and
location at site of all underground utility location, GPR
scanning and mapping of services which exists within the
limits of the works.The contractor is required to submit plans
showing the nature and location of these underground services
before commencement works to the satisfaction of the S.O.
6.1 To supply and install 10m hot dip galvanised pole c/w
alignment backfilling and c/w 2.4m single arm bracket Nos 11 1,140.00 12,540.00 2,100.00 23,100.00 1,200.00 13,200.00
6.4
4C-25mm2 XLPE/SWA/PVC underground Aluminium
cable from street lighting feeder pillar to TNB Substation
including from street lighting feeder pillar to TNB
Substation including Metre 20 20.00 400.00 170.00 3,400.00 25.00 500.00
a) Average depth e. 7.0m but n.e. 10.0m m 310 620.00 192,200.00 2,500.00 775,000.00 650.00 201,500.00
5.2 MANHOLES
a) Depth e. 6.5 m but n.e. 8.0m No. 4 9,350.00 37,400.00 5,000.00 20,000.00 9,000.00 36,000.00
b) Depth e. 8.0 m but n.e. 9.0m No. 1 9,900.00 9,900.00 5,500.00 5,500.00 10,000.00 10,000.00
5.3.1 Supply and install in position heavy duty D.I. Manhole cover and frame to BS 497
including painting with 2 coats of for expoxy paint Manhole cover shall be hinged to
the frame. No. 5 350 1,750.00 1,500.00 7,500.00 600.00 3,000.00
5.4.1 Extra over to provide concrete bedding or surround as directed for sewer for very soft
sub-soil including provision of 25mm thick timber board joint at every 8th pipe or as
specified in the Drawings.
m³ 5 195.00 975.00 250.00 1,250.00 200.00 1,000.00
5.4.2 Supply, handle, pitch and drive vertical 75mm dia. (min) x 5m long bakau piles under
the concrete bedding for sewer and manhole on very soft sub-soil.
No. 50 9.50 475.00 15.00 750.00 13.00 650.00
5.5.1 Supply and lay close bakau pile mattress below the crusher run bedding of sewer pipe
:-
a) 75mm dia. x 650mm long bakau pile for 225 mm dia. V.C.P. No. 30 4.50 135.00 10.00 300.00 5.00 150.00
5.6.1 Allow for excavation in rock including disposal to contractor's dumping ground.
m³ 10 60.00 600.00 100.00 1,000.00 50.00 500.00
5.7.1 Concrete encasement shall include all material and labour, excavation of all material
encountered excluding rock and all work necessary to complete the installation as
shown on the plans and specifications or as ordered by the Engineer.
Measurement will be as actual amount ordered. No payment will bemade for concrete
required in accordance with the contract. All concrete required for purposes other
than concrete encasement shown on the plans shall be paid for under the unit rate for
rate for concrete encasement. Concrete required because of pipe strengths lower than
specified is considered to be included in the unit rate for pipe.
5.8.1 Extra over for backfilling of sand as directed by the Engineer. m³ 30 35.00 1,050.00 16.00 480.00 16.00 480.00
5.9.1 Supply and install concrete end plug to the end of sewerline for future connection
for :-
a) 600 mm dia. RCP No. 1 300.00 300.00 2,500.00 2,500.00 500.00 500.00
5.10.1 Connection to existing manhole / sewer shall include all material and labour,
excavation of all encountered excluding rock and all work necessary to complete the
installation as shown on the plans and Specifications or as ordered by the Engineer.
No. 1 3,000.00 3,000.00 4,500.00 4,500.00 3,000.00 3,000.00
Allow for inspection of sewer pipeline with CCTV as per requirement of JPP/IWK.
Only CCTV that is accepted by JPP/IWK will be paid.
m 115 35.00 4,025.00 600.00 69,000.00 50.00 5,750.00
4.1 EXCAVATION
4.1.1 Excavate pipe trench through all classes of material (except rocks) including sand and
ordinary earth backfilling, tamping, ramming, disposal of surplus excavated material
and levelling after laying and testing of pipeline (Depth to invert not exceeding 2.0m)
4.2 PIPEWORKS
4.2.1 Supply, lay and join including jointing material, the bituminous felt wrapping cement
mortar lined steel pipe to specification in trench.
4.3.1 Supply, lay and join including jointing by welding for the following plain gusseted steel
bends installed below ground :
4.3.1.1 a) 150 mm dia. x 90 deg. No. 1 170.00 170.00 400.00 400.00 200.00 200.00
b) 150 mm dia. x 45 deg. No. 2 123.00 246.00 450.00 900.00 150.00 300.00
c) 150 mm dia. x 22 1/2 deg. No. 1 102.00 102.00 550.00 550.00 150.00 150.00
d) 150 mm dia. x 11 1/4 deg. No. 1 102.00 102.00 400.00 400.00 150.00 150.00
-
4.3.1.2 a) 200 mm dia. x 90 deg. No. 2 265.00 530.00 550.00 1,100.00 300.00 600.00
b) 200 mm dia. x 45 deg. No. 6 223.00 1,338.00 620.00 3,720.00 300.00 1,800.00
c) 200 mm dia. x 22 1/2 deg. No. 2 165.00 330.00 680.00 1,360.00 200.00 400.00
d) 200 mm dia. x 11 1/4 deg. No. 2 165.00 330.00 580.00 1,160.00 200.00 400.00
4.3.1.3 a) 400 mm dia. x 90 deg. No. 1 725.00 725.00 750.00 750.00 750.00 750.00
b) 400 mm dia. x 45 deg. No. 2 510.00 1,020.00 800.00 1,600.00 550.00 1,100.00
c) 400 mm dia. x 22 1/2 deg. No. 1 385.00 385.00 850.00 850.00 400.00 400.00
d) 400 mm dia. x 11 1/4 deg. No. 1 385.00 385.00 750.00 750.00 400.00 400.00
4.3.1.4 a) 750 mm dia. x 90 deg. No. 1 2,380.00 2,380.00 2,400.00 2,400.00 2,400.00 2,400.00
b) 750 mm dia. x 45 deg. No. 4 1,990.00 7,960.00 2,300.00 9,200.00 2,200.00 8,800.00
c) 750 mm dia. x 22 1/2 deg. No. 2 1,150.00 2,300.00 2,250.00 4,500.00 2,000.00 4,000.00
d) 750 mm dia. x 11 1/4 deg. No. 2 1,150.00 2,300.00 2,000.00 4,000.00 2,000.00 4,000.00
4.3.2 Supply, lay and join including jointing by collar welding for the following plain end
gusseted steel bends installed above ground:
a) 150 mm dia. x 45 deg. No. 2 133.00 266.00 450.00 900.00 250.00 500.00
b) 200 mm dia. x 45 deg. No. 2 233.00 466.00 650.00 1,300.00 350.00 700.00
4.3.3 Supply, lay and join including jointing by collar welding for the following steel tee
installed below ground:
a) 150 x 150 mm dia. No. 1 610.00 610.00 350.00 350.00 350.00 350.00
b) 200 x 150 mm dia. No. 1 670.00 670.00 500.00 500.00 500.00 500.00
4.3.4 Supply and install the following flexible (Viking Johnson Coupling) c/w bitumen
protection as directed by Engineer.
a) 150 mm dia. pipe No. 1 184.00 184.00 300.00 300.00 250.00 250.00
b) 200 mm dia. pipe No. 1 212.00 212.00 500.00 500.00 350.00 350.00
c) 400 mm dia. pipe No. 1 470.00 470.00 800.00 800.00 550.00 550.00
d) 750 mm dia. pipe No. 1 1,340.00 1,340.00 1,300.00 1,300.00 1,300.00 1,300.00
4.3.5 Supply, lay and join including jointing by collar welding for the following steel taper
installed below ground:
4.3.6 Provide end cap to M.S. pipe including m.s plate, welding, concrete thrust block,
excavation, back filling, compaction and disposal of surplus earth for :-
4.4 VALVES
4.4.1 a) 150 dia.sluice valve No. 1 1,400.00 1,400.00 4,000.00 4,000.00 2,000.00 2,000.00
b) 200 dia.sluice valve No. 3 2,330.00 6,990.00 8,000.00 24,000.00 2,500.00 7,500.00
c) 400 dia.sluice valve No. 1 8,000.00 8,000.00 20,000.00 20,000.00 9,000.00 9,000.00
4.5.1 Supply and construct thrust blocks, anchor blocks and end caps including formwork,
excavation, backfilling with compaction and removal of surplus material. m3 10 200.00 2,000.00 250.00 2,500.00 250.00 2,500.00
4.6 REINFORCEMENT
4.6.1 Reinforcement of Y12mm and R6mm diameter for anchor blocks, inclusive of cutting,
bending and placing in position
tonne 5 2,500.00 12,500.00 2,500.00 12,500.00 2,500.00 12,500.00
4.8.1 Connect to existing reticulation main pipe using hot tapping under pressure system as
per PUAS BERHAD requirement including labour, equipments, pipe pipe and fittings,
liaison with PUAD BERHAD, and all other ancillary works necessary to complete the
works.
a) By direct cutting, removing existing end cap and connect to existing water main.
No. 2 1,000.00 2,000.00 25,000.00 50,000.00 5,000.00 10,000.00
b) By under pressure / hot tapping for 200mm dia ms offtake existing 600mm dia.
ms pipe. No. 1 12,000.00 12,000.00 55,000.00 55,000.00 15,000.00 15,000.00
a) Depth E 1.0m but N.E 1.5m m 116 11.00 1,276.00 13.50 1,566.00 13.00 1,508.00
b) Depth E 1.5m but N.E 2.6m m 360 20.00 7,200.00 16.00 5,760.00 16.00 5,760.00
3.1.2.1 Supply, deliver and construct concrete base for concrete drain section
to the lines and grades (inclusive cascading drain not steeper than
1V:3H) as shown in drawings. m3 1,300 170.00 221,000.00 210.00 273,000.00 165.00 214,500.00
3.1.2.2 Supply, deliver and lay standard precast concrete drain section to the
lines and grades (inclusive of cascading drain not steeper than 1V :
3H) as specified including trimming for drain section, cement mortar
joints and a minimum of 25mm thick cement mortar tapering for :-
a) 300 mm block drain m 1,296 20.50 26,568.00 220.00 285,120.00 21.00 27,216.00
b) 600 mm block drain m 476 41.00 19,516.00 350.00 166,600.00 42.00 19,992.00
3.1.3 Supply, deliver and lay standard precast concrete drain section to the
lines and grades as specified to form cascading drain for slope steeper
than 1V : 3H including trimming for drain section, concrete base,
reinforcement, cement mortar, tapering, backfilling and disposal of
surplus material for:
3.1.4 Supply deliver and form Rubble Pitching.The average size of rock
should not be less than 150 mm. m³ 860 170.00 146,200.00 185.00 159,100.00 170.00 146,200.00
3.2.2 Supply, handle, pitch and drive 75mm dia. x 5m long vertical bakau
piles under the concrete base of pipe culvert when very soft sub-soil is
encountered or to be directed by the Engineer. No. 2,244 9.50 21,318.00 15.00 33,660.00 10.00 22,440.00
i) Depth N.E 1.5m No. 2 905.00 1,810.00 575.00 1,150.00 1,000.00 2,000.00
ii) Depth E 1.5m but N.E 2.0m No. 2 1,120.00 2,240.00 1,065.00 2,130.00 1,100.00 2,200.00
i) Depth E 1.5m but N.E 2.0m No. 2 1,535.00 3,070.00 1,500.00 3,000.00 1,500.00 3,000.00
i) Depth N.E 1.5m No. 2 750.00 1,500.00 500.00 1,000.00 750.00 1,500.00
ii) Depth E 1.5m but N.E 2.0m No. 2 1,150.00 2,300.00 925.00 1,850.00 1,200.00 2,400.00
3.4.1 Supply, deliver and place in position precast concrete slab with one
layer of BRC as shown in drawing for road side drain.
(a) 725mm x 600mm x 75mm No. 850 13.00 11,050 50.00 42,500.00 20.00 17,000.00
3.5.1 Allow for connection to existing drainage. No. 2 1,000.00 2,000.00 2,500.00 5,000.00 1,500.00 3,000.00
Excavate down to prepare road formation level for receiving road pavement, shoulder and
island/ median in all material other than solid rocks and disposal of surplus material.
m3 17,000 4.00 68,000.00 7.00 119,000.00 4.30 73,100.00
2.1.2 Supply, deliver, lay and compact sand sub-base to a compacted thickness of 50mm. m2 38,620 1.50 57,930.00 6.50 251,030.00 2.00 77,240.00
2.2.1 Supply, deliver, lay and compact for crusher run as roadbase in two equal layer to a total
compacted thickness.
2.2.2 Supply, deliver and apply bituminous prime coat to surface of the roadbase including
cleaning of the surface of the roadbase prior to the application of bituminous prime coat.
m2 38,620 1.00 38,620.00 1.50 57,930.00 1.00 38,620.00
2.2.3 Supply, deliver, lay and compact the asphaltic concrete binder course to 50mm compacted
thickness using mechanical spreader and properly rolled to required camber and fall using
8 to 10 tonne smooth wheeled roller followed by tyred smooth tread roller with tyre
pressure of 5.98 kg/cm2 to 6.33 kg/cm2
m2 38,620 10.50 405,510.00 15.00 579,300.00 10.50 405,510.00
2.2.4 Supply, deliver, lay and compact the asphaltic concrete wearing course to 40mm
compacted thickness using wearing course to 40mm compacted thickness using
mechanical spreader and properly rolled to required camber and fall using 8 to 10 tonne
smooth wheeled roller followed by tyred smooth tread roller with tyre pressure of 5.98
kg/cm2 to 6.33 kg/cm2 before handing over to Majlis Daerah Hulu Selangor at the written
directive of the Engineer including application of tack coat.
m2 66,000 10.00 660,000.00 13.00 858,000.00 10.00 660,000.00
2.3.1 Backfill and compact excavated material in Item 2.1.1 to form shoulders on both side of the
carriageway to receive top soil and turfing. m3 5,000 1.00 5,000.00 15.00 75,000.00 2.00 10,000.00
2.3.2 Supply turf of minimum 300mm x 300mm from an approved source, soil and peg in close
turfing to all designated area in accordance with the Specifications. m3 31,030 3.50 108,605.00 5.00 155,150.00 3.00 93,090.00
Supply, deliver, setting out and provide the following carriageway marking with road line
paint as shown in the drawing and specification : -
a) 100 mm wide lane marking (1000/1700) m 11,000 1.70 18,700 2.40 26,400.00 2.40 26,400.00
b) 150 mm wide edge marking m 5,400 2.55 13,770 2.90 15,660.00 2.90 15,660.00
c) 200 mm wide continuity marking (1000/1000) m 2,000 3.40 6,800 3.90 7,800.00 3.90 7,800.00
d) 150 mm wide continous line m 300 2.55 765 2.90 870.00 2.90 870.00
e) 305 mm wide for stop line m 500 4.20 2,100 5.20 2,600.00 5.20 2,600.00
f) Turning arrow No. 40 65.00 2,600 100.00 4,000.00 80.00 3,200.00
g) Go-straight arrow No. 120 65.00 7,800 100.00 12,000.00 80.00 9,600.00
h) Go-straight and turning arrow No. 20 85.00 1,700 120.00 2,400.00 100.00 2,000.00
i) Turning arrow (left and right) No. 20 85.00 1,700 120.00 2,400.00 100.00 2,000.00
j) 300mm wide chevron hatching with 200mm wide edge line marking (Area measured
based on the net painted marking) m2 250 50.00 12,500 18.00 4,500.00 18.00 4,500.00
2.5.1 Supply, deliver and erect the following signboards make of retroflective sticker high
intensity type in accordance to JKR's Standard as shown in the drawing. This rate should
include painting work for the post.
2.6.1 Supply all materials and construct scupper drain including excavation, concrete, 150mm
dia. PVC pipe, connection to kerb and outlet drain, compaction, backfilling, removal and
disposal of all surplus material. m 1,750 55.00 96,250.00 55.00 96,250.00 50.00 87,500.00
2.7.1 Supply, deliver and construct in position of the following concrete extrusion kerb including
excavation, mortar jointing at all joints, concrete base, concrete haunching, backfilling and
compacting of excavated earth, removal and disposal of all surplus material.
a) kerb with opening No. 60 50.00 3,000.00 45.00 2,700.00 45.00 2,700.00
b) kerb without opening m 6,100 35.00 213,500.00 40.00 244,000.00 37.00 225,700.00
-
2.7.2 Extra over item 2.7.1 for reinstatement of road pavement after laying of road kerb. m 2,200 20.00 44,000.00 15.00 33,000.00 8.00 17,600.00
2.8.1 Backfill and compact excavated material in Item 2.1.1 to form islands to receive top soil
turfing m³ 650 1.00 650.00 5.00 3,250.00 2.00 1,300.00
2.8.2 Supply turf of minimum 300mm x 300mm from an approved source, soil and peg in close
turfing to all designated area in road shoulder or other area as directed by S.O. all in
accordance with the Specifications. m² 2,120 3.50 7,420.00 4.00 8,480.00 3.00 6,360.00
2.9 GUARDRAIL
2.91 Untensioned single sided corrugated guardrail including concrete, bolts & nuts, steel post,
base plate, transition packer, 90 degrees twist, ramped terminal treatment etc m 840 130.00 109,200.00 150.00 126,000.00 130.00 109,200.00
2.10 MISCELLANEOUS
2.10.1 Backfill and compact excavated material in Item 2.1.1 to repair the slope to receive top soil
and turfing. m³ 3,000 1.00 3,000.00 10.20 30,600.00 2.00 6,000.00
2.10.2 Supply turf of minimum 300mm x 300mm from an approved source, soil and peg in close
turfing to all designated area in road shoulder or other area as directed by S.O. all in
accordance with the Specifications. m² 2,000 3.50 7,000.00 4.00 8,000.00 3.00 6,000.00
2.10.3
Import approved excavated material from borrow pit provided by PKNS within 2.0km
radius. Rate to included excavation, load, transport, place to form embankment or fill
above existing ground including necessary, benching, compaction up to required road and
platform formation levels all in accordance with the Specification. m³ 5,000 3.70 18,500.00 3.50 17,500.00 3.50 17,500.00
Provisional sum to be expended wholly or in part at the direction of the S.O. for Traffic
Signal Control Installation. Pro Sum 110,000.00 110,000.00 110,000.00
1.0 PRELIMINARIES
1.04 SIGNBOARD.
Provide, erect and maintain in good condition during the course of the
Contract and remove on completion of Works a signboard of size 1.8m by
3.6m overall, and painted and lettered in accordance with the Drawing and to
the approval of the Engineer.
No. 1 2,500.00 2,500.00 3,800.00 3,000.00 3,000.00
Provide for medical services and first aid facilities for Contractor's employees
at site and the S.O.'s site staff. Lum Sum 3,000.00 2,500.00 750.00
Provide for, maintain and remove temporary electrical supply for the purpose
of executing the work including all payment and deposit to the Authorities.
Lum Sum 12,000.00 10,000.00 10,000.00
Provide for, maintain and remove temporary water supply for the purpose of
executing the work including all payment and deposit to the Authorities.
Lum Sum 12,000.00 10,000.00 10,000.00
Provide and submit one ( 1) set intermediate, one (1) soft copy and three (3)
sets paper prints to the Engineer the as-built drawings as specified upon
completion of work. As-built survey submitted shall be carried out by
certified licensed surveyor.
Lum Sum 5,000.00 10,000.00 7,500.00
Provide all temporary works in connection with the works including all
necessary temporary sheet piling, timbering, shoring, cofferdam, bunds, silt
control as per JPS latest manual (Mesra Alam), water trough, temporary road,
sign, safety measures, drainage outlet, pumping etc to maintain the works free
of water and earth slips and ensure safety during the course of construction of
works, and all other works necessary to form and construct permanent work,
including maintenance, dismantling and clearing away on completion.
1.14 SURVEYS
Allow for all necessary survey for setting out and original ground survey by
licensed surveyor. Price should include survey for all construction works and
any other survey requested by the Engineer / S.O. Lum sum 15,000.00 35,000.00 20,000.00
Allow for submission of progress report and photographs in hard and soft
copy according to PKNS MS ISO 9002 format as required by the S.O.
Allow for submission of detailed work programme in hard and soft copy
using Microsoft Project 2000 or Primawira. Lum sum 2,000.00 2,500.00 2,000.00
The contractor is to ensure that the whole site is cleaned and cleared
from any debris, unwanted materials rubbish etc. upon completion of the
project. Temporary building, sheds, site office, unwanted building materials
are to be removed to the the satisfaction of the S.O.
Supply approved safety helmets and safety boots for the sole use of the
Engineer's site staff.
SET 10 240.00 2,400.00 300.00 3,000.00 200.00 2,000.00
1.24 MOTORCYCLE
Provide and maintain one (1) no of new motorcycle of minimum 90cc for the
use of c.o.w. It will be returned to the contractor on completion of contract.
No. 1 6,000.00 6,000.00 6,000.00 6,000.00 - -
Provide traffic management for existing road pavement to ensure safety and
not to cause any nuisance and danger to the road users. The scope of work
shall include the use of traffic signages, barrier and warning light to ensure
safety of road users.
10,000.00 20,000.00 8,000.00
COMPARISON OF BILLS
I BILL NO. 1
Preliminaries, General Items And Provisional Sums 263,900.00 425,800.00 253,666.00
II BILL NO. 2
Road Works 2,544,760.00 3,497,280.00 2,546,190.00
IV BILL NO. 4
Water Reticulation Work 574,332.00 824,340.00 595,905.00
V BILL NO. 5
Sewer Reticulation Works 253,710.00 890,280.00 264,530.00
VI BILL NO. 6
Telephone Infrastructure Service 43,965.00 145,300.00 58,450.00