Professional Documents
Culture Documents
1. It should be durable.
1. Mud flooring.
2. Murrum flooring.
6. Terrazo
7. Wooden flooring
Laying
Polishing
Mud Flooring
• In tropical countries, mud flooring is commonly constructed in
villages. Mud flooring are cheap, hard, fairly impervious, easy in
construction and easy in maintenance.
• Mud flooring remain warm in winter and cold in summer and hence
are most suitable for places where the temperature is extreme during
these seasons.
• The method of its construction is very simple. Upon the prepared
bed, a 25 cm thick layer of selected moist earth is evenly spread out
and is rammed well so as to get a consolidated thickness of about 15
cm.
• It is important to note that no water is used during the process of
ramming. In order to prevent the formation of cracks after drying,
chopped straw in small quantity is mixed with the moist earth before
ramming.
• The mud floor is maintained by giving a thin cement cow-dung wash
(1:2 to 1:3) once or twice a week.
Marble flooring
Preparation of sub base: Base coat consisting of cement concrete 1:8:16, 1:5:10 or 1:4:8
should be laid on compacted earth under marble stone flooring.
Laying out of marble stone slabs
The base concrete or RCC slab on which marble stone slabs are laid should be
thoroughly cleaned.
The average thickness of bedding mortar under marble stone slab should be 20 mm
thick and the ratio of cement mortar should be 1:3
The sand used in mortar should be coarse sand.
The thickness of bedding should not be less than 12 mm in any place
The top surface of mortar (bedding) should be leveled correctly by adding fresh
mortar at hollows if any.
The mortar is allowed to harden and cement slurry shall be spread at the rate of 4.4
kg per sq. meter.
Marble stone slab to be paved should then be lowered gently back in position and
tapped with wooded mallet till it is properly bedded and leveled with adjoining slab.
Care should be taken to match the grains of slabs.
All stone slabs should be laid in same manner.
After lying of each slab surplus cement on the surface of slabs should be cleaned.
First Grinding
1. Clean the surface of the slab by removing all loose materials, dust, etc. and wash with
clean water.
2. Provide and lay a screed of C.M. (1:3) over the clean and damp surface including
waterproofing agent mixed with C.M. Total average thickness shall be 20 mm. Lay an
average thickness of 115 mm consisting of brick bat layer laid in random pattern to avoid
continuity of joints and 10 mm thick., bedding, 10 mm thick, jointing with water proof
cement mortar of (1:3). This layer shall be laid to appropriate slopes towards floor drain.
This layer shall be cured for minimum 3 days before taking up the next layer. The surface
which is not taken up for next layer shall be continued to be cured for minimum 10 days.
Final Layer Provide and lay minimum 40 mm thick IPS layer in cement concrete (1:2:4)
with maximum size of aggregate 3 mm to 6 mm, simultaneously with polishing trowel,
using C.M. (1:2) above which floor tiles shall be laid.
water-proofing-coating-of-floor
4. Curing – This layer shall be cured for 21 days by flooding the water to 25 mm depth
in panel of 1M x 1M formed by weak cement mortar bonding.
5. Testing of waterproofing:
Waterproofing of slabs shall be tested by ponding the surface with water to a depth of
25 mm for 24 hours or longer. The waterproofing shall be considered satisfactory, if no
leaks or damp patches show on the soffit.