DETAILED ESTIMATE
PLATFORM CONSTRUCTION ( MAHARANA PRATAP STATUE)
AND BEAUTIFICATION WORK AT ROAD JUNCTION (TIRAHA) JIRAPUR DISTRICT RAJGARH.
UADD SOR
SN PARTICULARS NO LENGTH WIDTH DEPTH QTY RATES UNIT AMOUNT
STATUE BEAUTIFICATION
PORTION
612 SQM
PAVER BLOCK AREA AROUND
STATUE 71.01 43458.12
FOOTING
PCC 10x4 1 0.15 6
STEP 1 10x4 0.8 0.2 6.4
STEP 2 10x4 0.5 0.15 3
COLUMN 10x4 1.5 0.3 18
Platform footings
PCC 1X4 1 0.15 0.6
FOOTING STEP 1 4X4 0.8 0.2 2.56
FOOTING STEP 2 4X4 0.5 0.15 1.2
COLUMN 4X4 1.5 0.3 7.2
366 EACH
TOTAL 10 3660
SANITARY FITTINGS
(INCLUDING DI PIPES, VALVES,
SPRINKLER NOZZELS,WATER SEALS,
ETC.) LUMP SUM 50000
FOUNTAIN STRUCTURES
ORNAMENTS, INSTALLATION
CHARGES, INCLUDING LABOUR
AND INSTRUMENTS, ETC. ( LUMP
SUM) 250000
TOTAL 2080211.808
18% GST 374438.1254
GRAND TOTAL 2454649.933