Detail of Measurment

Name of Work:- C/O Bainsh Bangera Ambulance road km. 0/00 to 3/00 (SH:- C/O R/wall at R.D at 0/468.50 to 0/472 )
Sr.No RD L Ht Cutting Excavation CC 1:4:8 Boulder filling weep holes P.V.C PIPE
From TO Area Qty Area Qty Area Qty Area Qty. NO. L Qty
Retaining Wall
3 1.10 3.3
2 0.90 1.8
3 0.80 2.4
1 0/468.50 0/472 3.50 4 0.90 3.15 2.27 7.95 5.67 19.85 1.14 3.99

Total 3.15 7.95 19.85 3.99 7.5


Cum Cum Cum Cum Rmt
ABSTRACT OF COST.
Name of Work:- C/O Bainsh Bangera Ambulance road km. 0/00 to 3/00 (SH:- C/O R/wall at R.D at 0/468.50 to 0/472 )

Sr.No. Description of items. Quantity. Rate. Unit. Amount


1 2 3 4 5 6
1 Excavation in Hilly Area in soil manual means. Excavation in soil in Hilly 3.15 233.40 P.cum. 735
Area by manual means including cutting and trimming of side slopes and
disposing of excavated earth with a lift uptop 1.5 m. and a lead upto 20 m.
as per drawing and Technical Specification Clause 1603.1 including
carriage of materials upto all leads and lifts.

2 Earth work in excavation for structures as per drawing and technical 7.95 356.50 P.cum. 2832
specifications Clause 305.1 including setting out, construction of shoring
and bracing, removal of stumps and other deleterious material and disposal
upto a lead of 50m. Dressing of sides and bottom and back filling in
trenches with excavated suitable material including carriage of materials
upto all leads and lifts.

3 Providing and laying concrete for plain/reinforced concrete in open 19.85 4600.00 P.cum. 91287
foundations complete as per drawing and technical specification clause
802,803,1202 & 1203.(i) 1:4:8( 20 mm)
4 Back filling behind abutment, wing wall and return wall complete as per 3.99 841.80 P.cum. 3359
drawings and technical specification Clause 1204.3.8 including carriage of
materials upto all leads and lifts. (i) Granular material.
5 Provinding Weep Hole with PVC 100mm dia pipe 7.50 170.00 Prmt 1275
Total:-Rs. 99488