3.1.7 52.500 m3 Furnishing approved quality gravel , pilling for 783.25 41,120.63
measurements at site spreading & compaction to
the thickness of 100mm by machinery, ( haul
20km )
3.1.8 200.900 m2 Turfing to new earth fill area including watering till 238.50 47,914.65
turf take roots haul 5km .
3.2 Construction of 150mm dia. 4.88 m long turn out structure (Dwg No-CRIP/ID/HAM/NCB/44-3-
4)
3.2.1 1.400 m3 Earth excavation in foundation and spoil to waste as 1083.00 1,516.20
directed.
3.2.2 2.600 m2 Supplying & laying polythene 36/500 gauge (150 50.60 131.56
g/m3)
3.2.3 0.830 m3 1:2:4 (20mm) cement concrete mixing placing 13286.00 11,027.38
compacting & curing excluding formwork
3.2.4 0.700 m3 1:3:6 (25mm) cement concrete mixing placing 11700.00 8,190.00
compacting & curing excluding formwork
3.2.5 10.140 m2 Furnishing, making & fixing plywood formwork 1045.00 10,596.30
each of 6 uses including removing as same once
3.2.6 30.250 kg Furnishing, cutting , bending, placing & binding 200.25 6,057.56
tor steel R/F (As per bar schedule No ) Drawing
No:-CRIP/ID/HAM/NCB/44-3-
3.2.7 4.880 m Furnishing, laying &jointing 150mm dia. R.C.C 2558.00 12,483.04
hume pipe including trenching & back filling
3.2.8 1 Nos Furnishing & installing in 0.225m Ø cast from gate 30959.00 30,959.00
& hoist completed with spindle walle etc.
S. I. Qty. Unit Description Rate. Amount.
3.2.9 Item Allow Backfilling around the structure including watering Sum 1,500.00
& compaction.
Construction of concrete lining along F.C. 85 with drop structures Refer dwg
3.3
CRIP/ID/HAM/NCB/44-3-5 )
3.3.1 9.000 m3 Earth excavation in foundation and spoil to waste as 1,083.00 9,747.00
directed.
3.3.2 90.000 m2 Supplying & laying polythene 36/500 gauge (150 50.60 4,554.00
g/m3)
3.3.3 1110.000 kg Furnishing, cutting , bending, placing & binding tor 200.25 222,277.50
steel R/F (Refer dwg CRIP/ID/HAM/NCB/44
3.3.4 252.000 m2 Furnishing, Making & fixing plywood formwork 1,045.00 263,340.00
each of 6 uses including removing as same.
3.3.5 19.800 m3 1:2:4 (20mm) cement concrete mixing placing & 13,286.00 263,062.80
compacting & curing excluding formwork
3.3.6 46.500 m Providing construction joint using 150mm rubber 2,294.00 106,671.00
water stops. (6m interval)
3.3.7 10 Nos Providing 75 mm height hump at U/S of drop Sum 1,000.00
structures to reduce velocity of flow.
Construction of 2 Nos of 100mm Ø, 2.44m long Farm Turn out at 0+084 and 0+175 (Refer dwg
3.4
CRIP/ID/HAM/NCB/44-3-6
3.4.1 1.772 m3 Earth excavation in foundation & spoil to waste as 1,083.00 1,919.08
directed (manually)
3.4.2 1.140 m2 Supplying & laying polythene 36/500 gauge (150 50.60 57.68
g/m3)
3.4.3 0.859 m3 1:3:6 (25mm) cement concrete excluding formwork 11,700.00 10,044.45
3.4.4 6.489 m2 Furnishing & fixing plywood formwork each of 6 1,045.00 6,780.57
uses removing as same.
3.4.5 4.880 m Furnishing laying, jointing 100mm Ø RCC pipes 2,005.00 9,784.40
trenching & back filling as directed.
3.4.6 Item Allow Back filling over & around the structure including Sum 2,000.00
watering & placing, compaction. ( 2 structures) by
manually.
Construction of 2 Nos of 100mm Ø, 4.88m long Farm Turn out at 0+075 and 0+170 (Refer dwg
3.5
CRIP/ID/HAM/NCB/44-3-6
m3 Earth excavation in foundation & spoil to waste as
3.5.1 1.772 1,083.00 1,919.08
directed (manually)
m2 Supplying & laying polythene 36/500 gauge (150
3.5.2 1.140 50.60 57.68
g/m3)
m3
3.5.3 0.859 1:3:6 (25mm) cement concrete excluding formwork 11,700.00 10,044.45
3.6.8 Item Allow Splitting & parting of flat iron locking device to Sum 2,000.00
form "y" shape to avoid yielding out of concrete.
Prepared By E.K.P.S.Maheera EA
Submiited by
Checked By Eng.K.H.N.S.Kumara
Divisional Irrigation Engineer,
Weeraketiya.
3
Bill no 3. - Improvemints to FC 85-D7 Muruthawela Tract III - Quantity sheet
T D S Description
S.I. 3.1 Earth works
S.I. 3.1.1
Secondary growth clearing along canal trace from 0m to 175m
1/ 175.00
4.000 700.0 m2
Say
0.07 ha
S.I. 3.1.2
Earth excavation in canal , cut 1.5m lift up to 1.5m and haul 500m as directed.
(Refer cutting sheet)
15.800 m3
S.I. 3.1.3
Stripping top soil to a thickness of 100 m spoil to waste lift up to 1.5m haul 500m along the
canal as directed
89.200 m3
S.I. 3.1.4
Borrow earth from selected borrow area & bund filling at R/B , earth cutting by machinery
& placing, watering & compaction by manually haul 5.0 km .
34.300 m3
Say as =
180.00 m3
S.I. 3.1.5
Borrow earth from selected borrow area & bund filling at L/B, earth cutting , placing,
watering & compaction by machinery haul 5.0 km.
257.800 m3
Say as =
257.80 m3
S.I. 3.1.6
Grading bund road by motar grader be fore spreading of gravel
0.175 km
S.I. 3.1.6
Furnishing approved quality gravel , pilling for measurements at site spreading &
compaction to the thickness of 100mm by machinery, ( haul 20km )
175.00
3.00
0.10 52.50 m3
S.I. 3.1.8
Turfing to new earth fill area including watering till turf take roots haul 5km .
200.900 m2
S.I. 3.2
Construction of 150mm dia. 4.88 m long turn out structure for FC 85
(DR No-CRIP/ID/HAM/NCB/44 -3- )
S.I. 3.2.1
Earth excavation in foundation & spoil to waste as directed
1 1.200
0.225 0.15+0.075 = 0.225
0.450 0.122
1 x 1/2 2.100 U/S basing
0.600 1.2+0.9 = 2.1m
0.150 0.095
1 0.900 U/S cut off wall
0.225
0.600 0.122
1 4.880 For hume pipe
0.250
0.450 0.549
1 0.300 For collers
0.300
0.150 0.014
1 0.900 D/S head wall-cut off wall
0.225
0.600 0.122
1 1.000 D/S basin
0.900
0.100 0.090
1 1.800 D/S cut off wall (with working space)
0.250
0.625 0.281
1.393 Say as =
1.40 m3
S.I. 3.2.2
Supplying & laying polythene 36/500 gauge (150 g/m3)
2.60 m2
S.I. 3.2.3
1:2:4 (20mm) cement concrete mixing placing compacting & curing excluding formwork
S.I. 3.2.4
1:3:6 (25mm) cement concrete mixing placing compacting & curing excluding formwork
1 0.300 collar
0.300
0.375 0.034
π 0.075 ddt (hume pipe) (0.225 + 0.15 = 0.375)
0.075
0.375 0.007
0.662 Say as =
0.70 m3
S.I. 3.2.5
Furnishing, making & fixing plywood formwork each of 6 uses including removing as same
once
4 0.600
0.300 0.720
2 0.375
0.150 0.112
2 0.150
0.300 0.090
10.135
Say as =
10.14 m2
S.I. 3.2.6
Furnishing, cutting , bending, placing & binding tor steel R/F (As per bar schedule No 1 )
1 30.250 30.250 Drawing No:-CRIP/ID/HAM/NCB/44-2-4
Say as =
30.25 kg
S.I. 3.2.7
Furnishing, laying &jointing 150mm dia. R.C.C hume pipe including trenching & back
filling
1 4.880 4.880 Say as =
4.88 m
S.I. 3.2.8
Furnishing & installing in 0.225m Ø cast from gate & hoist completed with spindle walle
etc.
Prepared by E.K.P.S.Maheera E.A.
Checked by d'man
T D S Description
1 No Say as =
1.00 Nos
S.I. 3.2.8
Backfilling around the structure including watering & compaction.
Item Allow
Construction of concrete lining along F.C. 85 with drop structures Refer dwg
CRIP/ID/HAM/NCB/44-3-
length of canal = 180 m including drop structures
S.I. 3.3.1
Earth excavation in foundation and spoil to waste as directed.
1/ 180.00
0.50
0.10 9.000 m3
S.I. 3.3.2
Supplying & laying polythene 36/500 gauge (150 g/m3)
1/ 180.00
0.50 90.000 m2
30 37.00 1110.00 Kg
S.I. 3.3.4
Furnishing, Making & fixing plywood formwork each of 6 uses including removing as
2 180.00 same.
0.40 144.00
2 180.00
0.30 108.00
252.00 m2
S.I. 3.3.5
1:2:4 (20mm) cement concrete mixing placing & compacting & curing excluding formwork
1 180.00
0.50
0.10 9.00
2 180.00
0.10
0.30 10.80
19.80 m3
S.I. 3.3.7
Providing 75 mm height hump at U/S of drop structures to reduce velocity of flow.
10 Nos
S.I. 3.4
S.I. 3.4.1
Earth excavation in foundation & spoil to waste as directed (manually)
2 0.600 Basin
0.500
0.100 0.060
2 0.500 Cut-off wall end
0.100
0.050 0.005
2 4.880 Pipe trench
0.250
0.600 1.464
1.772 m3
S.I. 3.4.2
Supplying & laying polythene 36/500 gauge (150 g/m3)
2 0.600 D/S sill
0.500 0.600
2 0.900 D/S Head wall
0.300 0.540
1.140 m2
S.I. 3.4.3
1:3:6 (25mm) cement concrete excluding formwork
4 0.900 Head wall
0.230
0.500 0.414
2 0.900
0.300
0.450 0.243
2 0.500 Sill of Basin
0.500
S.I. 3.4.4
Furnishing & fixing plywood formwork each of 6 uses removing as same.
8 0.90
0.50 3.60
8 0.23
0.50 0.920
4 0.10
0.50 0.200
2 0.35
0.40 0.280
8 0.25
0.40 0.800
8 0.15
0.35 0.420
4 0.50
0.15 0.300 Side wall
4π 0.05
0.05 0.031
6.49 m2
S.I. 3.4.5
Furnishing laying, jointing 100mm Ø RCC pipes trenching & back filling as directed.
2 2.44 4.88 m
S.I. 3.4.6
Back filling over & around the structure including watering & placing, compaction.
(3 structures) by manually.
Item Allow
S.I. 3.5
S.I. 3.5.2
Supplying & laying polythene 36/500 gauge (150 g/m3)
2 0.600 D/S sill
0.500 0.600
2 0.900 D/S Head wall
0.300 0.540
1.140 m2
S.I. 3.5.3
1:3:6 (25mm) cement concrete excluding formwork
4 0.900 Head wall
0.230
0.500 0.414
2 0.900
0.300
0.450 0.243
2 0.500 Sill of Basin
0.500
0.100 0.050
S.I. 3.5.4
S.I. 3.5.5
Furnishing laying, jointing 100mm Ø RCC pipes trenching & back filling as directed.
2 4.88 9.76 m
S.I. 3.5.6
Back filling over & around the structure including watering & placing, compaction.
(3 structures) by manually.
Item Allow
S.I. 3.6
Furnishing, Making & fixing F.T.O. gate (4 nos)
Drw No : CRIP/ID/HAM/NCB/44
S.I. 3.6.1
Furnishing & cutting, fixing, 4.5mm thick M.S. sheet including local transport & wastage as
4 0.300 directed.
0.360 m
2
0.300
S.I. 3.6.2
Furnishing cutting & fixing 25mm x 6mm flat iron.
4 0.600 2.400 m
S.I. 3.6.3
Furnishing cutting & fixing 25mm x 6mm angle iron as directed.
S.I. 3.6.5
Welding runners to steel plate flat iron, & angle iron as directed.
Item allow
S.I. 3.6.6
Applying two coats of anti corrosive paint on steel gates including preperation of surface.
Item allow
S.I. 3.6.7
Furnishing making & fixing locking arrangements .
Item allow
S.I. 3.6.8
Splitting & parting of flat iron locking device to form "y" shape to avoid yielding out of conc
Item allow
CHAINAGE
DISTANCE
M/ M/ M/ VOL. VOL.
AREA AREA VOL. AREA AREA(m² VOL. AREA AREA(m² VOL. AREA (m³) AREA (m³) AREA
(m²) (m³) (m²) LB (m³) (m²) RB (m³) LB(m) M/L(m) RB(m) M/L(m) L(m) M/L(m)
(m²) ) ) (m2) AREA X (m2) AREA X (m2)
0.0 0 0.075 - - 0.190 1.400 - - 1.100 0.15 5.600 0.15 1.140 - -
30.0 30.0 0.070 0.073 2.175 0.065 0.128 3.825 0.860 1.130 33.900 0.550 0.825 24.750 2.475 3.800 4.700 141.000 14.100 0.600 0.870 26.100
30.0 0.0 0.200 0.135 0.000 0.000 0.033 0.000 0.760 0.810 0.000 0.000 0.275 0.000 0.000 4.300 4.050 0.000 0.000 2.300 1.450 0.000
60.0 30.0 0.000 0.100 3.000 0.390 0.195 5.850 0.850 0.805 24.150 1.500 0.750 22.500 2.250 3.750 4.025 120.750 12.075 0.480 1.390 41.700
60.0 0.0 0.100 0.050 0.000 0.100 0.245 0.000 0.812 0.831 0.000 0.870 1.185 0.000 0.000 3.800 3.775 0.000 0.000 0.750 0.615 0.000
90.0 30.0 0.000 0.050 1.500 0.175 0.138 4.125 0.630 0.721 21.630 1.500 1.185 35.550 3.555 3.900 3.850 115.500 11.550 0.000 0.375 11.250
90.0 0.0 0.090 0.045 0.000 0.054 0.114 0.000 0.648 0.639 0.000 0.635 1.068 0.000 0.000 4.100 4.000 0.000 0.000 1.040 0.520 0.000
120.0 30.0 0.070 0.080 2.400 0.032 0.043 1.290 1.580 1.114 33.420 0.390 0.513 15.375 1.537 4.400 4.250 127.500 12.750 1.930 1.485 44.550
120.0 0.0 0.310 0.190 0.000 0.000 0.016 0.000 1.500 1.540 0.000 0.000 0.195 0.000 0.000 4.600 4.500 0.000 0.000 1.900 1.915 0.000
150.0 30.0 0.000 0.155 4.650 0.260 0.130 3.900 0.950 1.225 36.750 1.475 0.738 22.125 2.213 4.150 4.375 131.250 13.125 0.980 1.440 43.200
150.0 0.0 0.165 0.083 0.000 0.020 0.140 0.000 0.980 0.965 0.000 0.400 0.938 0.000 0.000 4.450 4.300 0.000 0.000 1.105 1.043 0.000
175.0 25.0 0.000 0.083 2.063 0.020 0.020 0.500 1.700 1.340 33.500 1.800 1.100 27.500 2.750 4.200 4.325 108.125 10.813 1.625 1.365 34.125
15.788 19.490 183.350 14.780 74.413 200.925
Prepared by : E.K.P.S.Maheera EA
Checked by :
S.I. no 3.2 - Construction of 150mm dia. 4.88 m long turn out structure FC 85
0.15
1.7
300 2 Y 10 1 7 7 1.70 11.90
1.7
300 3 Y 10 2 7 14 0.85 11.90
0.850
0.250
1.150
ave 0.3
LENGTH TOTAL
BAR TYPE NO. IN TOTAL
PITCH NO. OF OF EACH LENGTH
MAR & EACH NO. OF SHAPE & BENDING DIMENSIONS.
(mm ) UNITS BAR
K SIZE UNIT BARS
(m) (m)
0.45
300 2 Y 10 1 5 5 6.00 30.00
6.0
24