DETAIL OF MEASUREMENT

Name of Work:-
Sub Head:-
Sr. Description Nos
No
1 2 3
1 Scarifying the existing bituminous road surface to a depth of 150mm
and disposal of scarified material with a lift upto 3m and lead upto
1000m as per Technical Specification Clause 301.4. 1

2 Earthwork in excavation for structures as per drawing and technical


specifications Clause 305.1 including setting out, construction of
shoring and bracing, removal of stumps and other deleterious material
and disposal upto a lead of 50 m, dressing of sides and bottom and
backfilling in trenches with excavated suitable material.

1
1

3 Providing & Laying concrete for Plain/reinforced concrete in open


foundation complete as per drawing and technical specification
Clause 802, 803, 1202 & 1203 (Nominal Mix 1:4:8). 1

4 Providing and Laying concrete for Plain/reinforced concrete in open


foundation complete as per drawing and technical specification
Clause 802, 803, 1202 & 1203 PCC (Nominal Mix 1:1.5:3)
1

5 Providing and Laying concrete for Plain/reinforced concrete in open


foundation complete as per drawing and technical specification
Clause 802, 803, 1202 & 1203 PCC (Nominal Mix 1:3:6)

Drain Bed
1
1

Outer wall 1
1

Inner wall 1
ASUREMENT

L. B. H/D Qty. Unit

4 5 6 7 8

200.00 3.10 620.00 sqm


Total 620.00 sqm

cum
250 0.8 0.4 80
650 0.8 0.4 104
Total 184 cum

200 4 0.1 80 cum


Total 80.00 cum

200.00 4.00 0.20 160.00 cum


Total 160.00 cum

250.00 0.60 0.20 30.00 cum


650.00 0.80 0.10 52.00

250.00 0.2 0.75 37.50 cum


650.00 0.2 0.6 78.00 cum

250 0.2 0.75 37.5 cum


Total 235 cum
Abstract of Cost
Name of Work:-
Sub Head:-
Sr. NO. Description of Items Qty Rate Unit
1 Scarifying the existing bituminous road surface to a 620.00 6.60 Sqm.
depth of 150mm and disposal of scarified material
with a lift upto 3m and lead upto 1000m as per
Technical Specification Clause 301.4.
2 Earthwork in excavation for structures as per drawing 184.00 128.15 Cum.
and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and
disposal upto a lead of 50 m, dressing of sides and
bottom and backfilling in trenches with excavated
suitable material.
3 Providing & Laying concrete for Plain/reinforced 80.00 2337.20 Cum.
concrete in open foundation complete as per drawing
and technical specification Clause 802, 803, 1202 &
1203 (Nominal Mix 1:4:8).
4 Providing and Laying concrete for Plain/reinforced 160.00 3949.40 Cum.
concrete in open foundation complete as per drawing
and technical specification Clause 802, 803, 1202 &
1203 PCC (Nominal Mix 1:1.5:3)
5 Providing and Laying concrete for Plain/reinforced 235.00 2,928.35 Cum.
concrete in open foundation complete as per drawing
and technical specification Clause 802, 803, 1202 &
1203 PCC (Nominal Mix 1:3:6)
Total
Add 70% for cost index on HPSR 2009
Grand Total
Amount
4092.00

23579.60

186976.00

631904.00

688162.25

1534713.85
1074299.70
2609013.55