1 INTRODUCTION
The purpose of this technical specification is to establish the criteria for the design for the civil works,
electrical and communications installations.
The design of the Project shall take into account the environmental condition at the site including but not
limited to temperature, wind, flooding risk, irradiation, grid conditions, altitude and of any other source
which could compromise the operation of the Plant's components.
DC/AC ÿ1.35
4 CIVIL WORKS
The civil works to be undertaken by the developer shall include, as a minimum, the following:
4.2 Access roads, internal roads, parking lots and site laydown
The developer shall design roads, parking lots and any other areas within the site, including a control room cabin equipped as a
work station with a meeting room. The design of these buildings will be provided by Solarpack.
The minimum technical requirements for the roads are (other requirements different than the ones shown below shall be justified
properly):
• Width: 4 m (internal)
• Curvature radius: at least 12 m • Maximum
longitudinal point slope: 10% in straight line and 7% in curves. • Transversal slope: 2% to prevent
to allow the water to drain away.
The surfaces shall be designed in order to enable the circulation of heavy vehicles during both the construction and the operational
phase.
The developer will take into account in the design of the layout:
•
All areas of the project must be accessible for maintenance tasks
• A perimeter separation will be designed between the photovoltaic structures and the fence of 10 m and 15 m from
photovoltaics structures to public roads except for another regulatory requirement..
• A network of main roads will be designated as the one that connects the access with the control center and power stations.
•
In the case of trackers, space will be left between north-south structures for accessibility
•
In the case of fixed structures, every 200m in the east-west direction, a corridor will be left for accessibility between
structures. • Avoid shadows from trees,
buildings, electric lines, etc., as much as possible
• Leave buffers from roads, archeological findings, environmental restrictions, water bodies and every condition according to
the local or national regulations.
• Topograhic study: design the plant on contour lines with a maximum 20 cm spacing
As a general rule, the Plant will be designed to avoid external drainage and internal drainage. For external drainage, the return
period will be of 50 years, and for the internal drainage, the return period will be of 25 years.
Note: However, the consultant must verify that the return period meets the applicable laws, banks and other stakeholders'
requirements.
The drainage system should be designed in line, as a minimum, with the following:
• The conclusions of the flood risk assessment, the site topography, and the site configuration
•
All the applicable laws, regulations, and standards.
The developer shall design the foundations in accordance to the applicable laws, standards, and regulations and their experience.
The developer design the structure foundations in line with the results of the geotechnical study undertaken at the site.
Machine Translated by Google
The gate will be enough to let the most restrictive machinery to enter inside the plant to work properly
during construction and O&M phases.
5 ELECTRICAL WORKS
The developer shall design the electrical system in accordance with the grid code requirements, the
distribution network operator requirements and applicable standards/laws. The design should account
for the environmental conditions at the site.
If it is determined that an isolated ground grid is required for lightning protection, this isolated grid must
be appropriately designed and installed.
5.3 Trenches
The developer will design the ditches deep enough to avoid damage from machinery working on the
crops.
All components must be protected, including the communication and security devices.
6 SECURITY SYSTEM
The developer will design a perimeter security system for the project or islands formed by the fence and
avoiding interference with drainage and roads.