06.10.22
Advantages of the Ejector
• Increases ROP
replacement
• Easy to handle
Principle of operation
The Ejector
•Installed above a bit and RIH as part of
BHA
When mud flows downward reaching the
Ejector, a small part (20-23 %) of the mud
changes its direction from downward to
upward.
This action creates negative pressure
zone above the Bit.
Receiving suction effect (on the bottom
hole below the bit)
Hardening of the wellbore
Principle of operation
which results in :-
Makes the rock destroying ability of
bit more effective.
The cuttings are milled and chipped
off easier from the rock.
The cuttings are carried out faster
from the bits zone. Hence, no more re-
drilling and milling of cuttings.
The Bit is worn-out less and drills for
longer time.
Principles of the EJECTOR NB
Two principles were used on
designing the EJECTOR NB and are
responsible for its increased efficiency :
•Energy Loss at the Sudden Expansion
of Fluid Flow in Confined Space
•Intersection of two flows
in conventional Ejectors, the kinetic
energy of the jet is converted into the
potential energy of pressure, which
dramatically reduces their efficiency.
In our EJECTOR tool we use only the
kinetic energy of jetting, and therefore
there is no energy loss.
The EJECTOR’s Operational Limits
• ADCO, UAE
• PDO, Oman
• AGOCO, Libya
• Karasu Operating Company, Azerbaijan
يشتكي
• Russia – Gasprom-Burenie, Tatneft, Eurasia
Perm Drilling Co., Podsemburgas, etc.
• LUKOIL Uzbekistan Operating Co.
• ERIELL International Oil Service Group,
Uzbekistan
Drilling Innovations work
in the MENA area
• An EJECTOR job for PDO, Oman.
• EJECTOR, Whipstock, curing losses for ADCO, UAE.
• EJECTOR jobs in AGOCO, Libya.
• Participating in ADIPEC 2008, 2010, 2012
• Participating in the 2011 SPE/DGS Annual Technical
Symposium and Exhibition, Al-Khobar, KSA.
Case Histories in the MENA area
Bit RR,
Oman Yib-516 12 ¼”
PDC 31%. one day saved
12 ¼”
UAE BB-904 PDC 25%. ----
HH100- 8 ½”
Three bits /
Libya Tricone -------
65 two days saved
Case Histories in Russia (drilled with Mud
Motors)
Average Avg.
ROP
CLIENT No. of wells Offset Tornado
Increase
ROP m/hr ROP
Chernogorskoe
6 72 97 34%
Naryanmar-nefte-
gaz 2 40 55 37%
ROP with
EJECTOR
L-79 L-81 L-79 L-81 L-79 L-81 L-79 L-81 L-79 L-81 application, %
7988-8200 7473-7820 GTX-G3 135 GT-20 517 212 347 14 16 15 21,0 43,2
8200-8440 7820-8350 GTX-G3 135 GT-20 517 240 530 21 21 12 25,0 120,6
8440-8717 8350-8390 GTX-G3 135 GT-20 517 277 40 22 3 12,
12,5 13,
13,3 6,7
6,7
8717-8800 8390-8436 CX47MRS 537 GT-20 517 83 46 8 6 10 14,3
14,3 43,0
43,0
8800-8975 8436-8830 CX47MRS 537 GT-20 517 175 394 21,5 21 8 18,7
18,7 133.,8
133.,8
8975-9045 8830-9075 GT-20 517 GT-20 517 70 245 10 18,5 7 13,
13,2 89,2
89,2
9045-9075 GT-20 517 30 3 10
Total:
Total: 1087 1602 99,5 85,5 10,
10,9 18,7
18,7 71,5
Daily ROP Comparison for 8 1/2" drilling
27,0
L81 (NBEU)
24,0 L79 (standard BHA)
21,0
18,0
ROP
15,0
12,0
9,0
6,0
7473 7820 7988 8200 8350 8390 8436 8440 8717 8800 8830 8975 9045 9075
Depth, ft
Application in Oman
Well YIB-512 (standard BHA without EJECTOR) using PDC bit
2-2-HC-A-X-I-WT-
DSR619S-I4 222418 4682 8228 3546 94.25 37.6
TD
0-0-WT-G-X-I-WT-
DSR619S-I4 227434 5623 8310 2687 54 49.8
TD
SPE 149113. Methods of Drilling Rate increase, Near Bit EJECTOR application
06.10.22
Results obtained by various
EJECTOR applications
The main benefits achieved by using the near bit
EJECTOR tool in all the areas drilled were as follows:
- Increased ROP
- Reduced Number of bits
- Decreased Overall drilling time
- Obtained better wellbore condition with no
washouts
API & ISO certification