The Engineer: Employer/Developer PMC/Employer's Representative The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments

Ref.No. SAJ-P0-CGC-MST-PL-0002-01
Technical Submittal Rev.No. 1
Date: 10/7/2023

Reqd. By: 18/7/2023

Subject of Submittal: INSTALLATION OF ABOVEGROUND DRAINAGE PIPES AND VENT PIPING SYSTEMS

Enclosure: Pre-Qualification of Subcontractor Method Statement Guarantee Certificate Test Results

Operation & Maintenance Manual Project Quality Plan HSE Plan Calculation Survey Others (Specify……....)

ARCO MEP Sign: Date: 10/7/2023

CGC Contractor's Sign: Date:

Ref No 5214483/R11-

ATKINS Engineer's Comments:

Reviewed By: Date:

ATKINS Resident Engineer's Comments


Code A - Approved

Code B - Approved As Noted

Code C - Revise and Resubmit

Code D - Information, Record

Code E - Incompleted, Resubmit

ATKINS RE Sign: Date:

Ref.No 5214483/R10-

Contractor Received Sign: Date:


Corrections or comments made relative to submittals during this review do not relieve the contractor from compliance with the contract requirement and specifications.
This check is only for review of general conformance with the design concept of the project and general compliance with the i nformation given in the contract documents.

SITE OPERATIONS Form No.SQP10/FM/006, Rev 00


The Engineer: The Employer: The Main Contractor/
MEP Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Rev.
SAJ-P0-CGC-MST-PL- METHOD STATEMENT FOR Date 10 / 07
INSTALLATION OF ABOVE GROUND /2023
0002-01 DRAINAGE AND VENT PIPING
SYSTEMS Page Page: 1 / 1

COMMENTS REPLY SHEET


SAJ-P0-CGC-MST-PL-0002-00

SR.
CONSULTANT COMMENTS COMPLIANCE/REPLY
NO.
1. Revise the Risk Assessment Compiled/ Revised

2. Revise the ITP as Commented Compiled/Revised

3. Construction Manager Responsibility Compiled, included in


Section - 7
5. Manufacturer recommendation of material storage and handling should be Compiled, included in sec-10
add.
6. Material submittal reference and status should mention Compiled , Included in Sec- 9

7. Coordination and clearances required during activities Noted

8. Installation procedures inside risers to be add Noted, sec-10

9. Floor trap, clean out to be add in installation procedures Compiled Sec-10

Mr. Abdel Rahman Banat, Sr. Mechanical Engr


JULY 10, 2023
Company Name: Arco Electromechanical

Page 1 of 1
The Engineer: Employer/Developer PMC/Employer's Representative The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments

Ref.No. SA-P0-CGC-MST-PL-0002-00
Technical Submittal Rev.No. 00
Date: 21/5/2023

Reqd. By: 3/6/2023

Subject of Submittal: INSTALLATION OF ABOVE GROUND DRAINAGE PIPES AND VENT PIPES
Enclosure: Pre-Qualification of Subcontractor Method Statement Guarantee Certificate Test Results

Operation & Maintenance Manual Project Quality Plan HSE Plan Calculation Survey Others (Specify……....)

Contractor's Sign: Date: 21/5/2023

ATKINS Received Sign: Date:

Ref No 5214483/R11-

ATKINS Engineer's Comments:

Reviewed By: Date:

ATKINS Resident Engineer's Comments


Code A - Approved

Code B - Approved As Noted


Code C - Revise and Resubmit

Code D - Information, Record

Code E - Incompleted, Resubmit

ATKINS RE Sign: Date:

Ref.No 5214483/R10-

Contractor Received Sign: Date:


Corrections or comments made relative to submittals during this review do not relieve the contractor from compliance with the contract requirement and specifications.
This check is only for review of general conformance with the design concept of the project and general compliance with the i nformation given in the contract documents.

SITE OPERATIONS Form No.SQP10/FM/006, Rev 00


The Engineer: The Employer: The Contractor:

Project: 5214483‐LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
Date 10-07-2023
SAJ-P0-CGC-MST-PL-0002-01 Method Statement For Installation Of Above
ground Drainage and Vent Piping Systems

Method Statement for Installation of Above Ground Drainage and


Vent Piping Systems

SOUK AL JUBAIL TOWN CENTRE & APARTMENTS


JUBAIL ISLAND -ABU DHABI (UAE)

REV
PREPARED&REVIEWED BY REVIEWED & ENDORSED BY APPROVED BY STATUS
NO

0 10‐07‐2023

Mr. Monish T Mr. Abdelalrahman Banat Mr. Hussein Gewilly


QA/QC‐Engineer‐Mechanical Sr. Mechanical Engineer Project Manager
ARCO Electromechanical ARCO Electromechanical ARCO Electromechanical
PROJECT AUDIT RECORD QUALITY PROCEDURE
SQP19

CATEGORY: Section SQP19 PROJECT: PERSONNEL INTERVIEWED:


5214483-LEAD - SAJ TOWEN CENTRE
Quality Assurance - All Discipline RESULT
AND APARTMENTS PROJECT Site Resident Engineer

Yes / No
No. Questions Documents Examined Comments
/ NA
D Method Statement, ITP, Risk Assesment

Check and verify the completeness and correctness of the listed particulars/documets (which ever applicable)


1 Purpose/Scope of Document


2 Scope of Work


3 Description of Work


4 Reference to Specification or Drawing


5 Key Personnel and Responsibility


6 HSE Requirements


7 Quality and Safety procedures


8 Plant, Tools and Equipment List


9 Approval of Material(s)


10 Checklists


11 Forms and Formats

Requirement in ITP in line with the √


specification/authority requirements
12
(which ever is on the higher side)
crosscheck with specification

13 Risk Assessment

Approval/Clearance to proceed with √


14
work and required coordination

15 Quality of Comments

16 Any Other Observation(s)/Comments

Page 4 of 6
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 1
DRAINAGE AND VENT PIPING SYSTEMS

METHOD STATEMENT
Aboveground Drainage & Vent Piping
Systems Installation
PROJECT NAME 5214483-LEAD SOUK AL JUBAIL APARTMENTS
PLOT NO 2-AP-001-1-BLD / 2-AP-001-2-BLD
PROJECT LOCATION SECTOR: JS JUBAIL ISLAND DEVELOPMENT, ABU
DHABI, UAE
CONSTRUCTION, COMPLETION AND 12 MONTHS
MAINTENANCE OF (06 NOS OF G+4 BUILDINGS,
SCOPE OF WORKS
TOWNHOUSE APARTMENTS, GYM & COMMUNITY
CENTER INCLUDING EXTERNAL WORKS.)
JUBAIL ISLAND INVESTMENT – SOLE
THE EMPLOYER / PROPRIETORSHIP LLC P O BOX 39294 ABU DHABI,
CLIENTS UAE, LEAD DEVELOPMENT AND PROJECT
MANAGEMENT CONSULTANTS
THE ENGINEER/
ATKINS ENGINEERING CONSULTANT
CONSULTANT
CONSTRUCTION GENERAL CONTRACTING HOUSE
MAIN CONTRACTOR
LTD
MEP SUB
ARCO ELECTROMECHANICAL L.L.C
CONTRACTOR
ALL OTHER DEFINITIONS AS PER CONTRACT NO. 5214483

Page 1 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 2
DRAINAGE AND VENT PIPING SYSTEMS

CONTENTS
1. ACTIVITY
2. SCOPE
3. DEFINITIONS AND ABBREVIATIONS
4. PROJECT DETAILS-PROJECT NAME AND STAKE HOLDERS
5. REFERENCES
6. TOOLS, TACKLES AND EQUIPMENTS
7. EMPLOYEES INVOLVED & RESPONSIBILITY
8. SAFETY HAZARDS AND CONTROL MEASURES
A. Training
B. House keeping
C. Emergency Arrangements
9. MATERIALS AS PER THE SPEC AND APPROVED MATERIAL
SUBMITTAL:
10. PROCEDURE ERECTION AND INSTALLATION OF UNDERGROUND
DRAINAGE AND RAINWATER SYSTEMS
A. Handling/Storage of Materials
B. Sequence of Work
11. Environmental and Sustainability Requirements

A. Waste Management

B. Hazardous Substances Management

12. ATTACHMENTS
Appendix 1 – Method Statement Briefing
Appendix 2- Risk Assessment & Control Measure.
Appendix 3 – Specification- SECTION 221316: SANITARY WASTE AND
VENT PIPING
Appendix 4 – ITP
Appendix 5 – Checklist
Appendix 6 – Organization Chart

Page 2 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 3
DRAINAGE AND VENT PIPING SYSTEMS

1.0 ACTIVITY:

This Method Statement is to provide and maintain effective quality control procedures
and standardized Installation and Gravity test of Aboveground Drainage & Vent Pipe
works to ensure compliance with the conditions of contract and project specifications.

2.0 SCOPE:

The scope of work covered by this method statement is everything related to the
Installation and Gravity test of Aboveground Drainage & Vent Pipe works for the
buildings and all proposed utilities Also, this method statement discusses all safety
related issues including but not limited to safety working methods

3.0 DEFINITIONS AND ABBREVIATIONS

3.1 DEFINITIONS

JUBAIL ISLAND INVESTMENT – SOLE PROPRIETORSHIP


THE
EMPLOYER / LLC P O BOX 39294 ABU DHABI, UAE, LEAD DEVELOPMENT
CLIENTS AND PROJECT MANAGEMENT CONSULTANTS

Project 5214483-LEAD SOUK AL JUBAIL APARTMENTS

Consultant ATKINS ENGINEERING CONSULTANT

Contractor CONSTRUCTION GENERAL CONTRACTING HOUSE LTD

Sub-Contractor ARCO ELECTROMECHANICAL LLC

Page 3 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 4
DRAINAGE AND VENT PIPING SYSTEMS

3.2 ABBREVIATIONS

QA - QUALITY ASSURANCE is the planning and organizing of a system or


program to maintain a required level of quality or reliability. This includes
auditing the system’s operation and related controls to assure that they are being
executed properly and functioning as expected. Quality shall be assured by
Contractor/Client.

QC – QUALITY CONTROL is a part of Quality Assurance, implements the


latter by examining physical characteristics and comparing them to established
and acceptable Quality Documents as stated in the quality assurance program or
plan.
Quality shall be controlled by Sub-Contractor in accordance with the Quality
Documents.

ITP - INSPECTION & TEST PLAN means the document which contains
sequence of activities in a process, highlights the applicable Quality Documents, and
inspection criticalities.

PA - PREVENTIVE ACTION means to eliminate the causes of a potential


nonconformity or other potentially undesirable situation.
CAR - CORRECTIVE ACTION means to eliminate the causes of a detected non-
conformity or other undesirable situation.

QUALITY DOCUMENTS mean drawings specification, procedure, record


formats, codes and standards specified in the documents issued by the
Contractor/Company to the Subcontractor.

SITE means the place, designated by Client for further development, where the
construction activities shall be carried out by Sub-contractor.

PROCEDURE describes how a process is performed.


TPI - Third Party Inspection

RA – Risk Assessments

Page 4 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 5
DRAINAGE AND VENT PIPING SYSTEMS

4.0 PROJECT DETAILS-PROJECT NAME AND STAKE HOLDERS

5214483-LEAD-SOUK AL JUBAIL TOWN CENTER AND APARTMENTS PROJECT

EHAF CONSULTING ENGINEERS

ARCO ELECTROMECHANICAL

Page 5 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 6
DRAINAGE AND VENT PIPING SYSTEMS

5.0 REFERENCES:

Approved shop, coordination drawings


Project IFC drawings
Project specification:-Sanitary waste and vent piping Section 22 13 16

6.0 TOOLS, TACKLES AND EQUIPMENTS:

• Portable hand tools


• Measuring tape and setting out markers
• Hacksaw frame with blade, Punch
• Electric Drill Machine
• Tape measure, Plumb bob, Chalk line
• Pressure pump
• Hose pipe
• Testing plugs, End caps
• Temporary hoses
• Spirit level
• Water level
• Wire cutter
• Pipe fitters Tool Box
• Lubricants, Cleaners
• Scaffolding with platform / Step Ladder
• Activities Equipment – masking tape, nail, steel wires
• Necessary lighting.

7.0 EMPLOYEES INVOLVED AND RESPONSIBILITY:

Project Manager
• Overall site Management, Quality and Safety.
• Has full authority and overall responsibility to manage, supervise, and control
the works.

Page 6 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 7
DRAINAGE AND VENT PIPING SYSTEMS

Project Engineer/ Discipline Engineer


Overall site supervision shall be the responsibility of the Discipline Engineer, who
will over-see all works appertaining to the ascribed method statement. The
Discipline Engineer will be responsible for preparing the ‘works’ for inspection in
co-ordination with QA/QC department.
• The Project Engineer is responsible to carry out the work as per the Method
Statement, Specification and Approved Drawings.
• The Project Engineer shall ensure that the resources are available to carry out
the works as scheduled.
• The Project Engineer shall be available at site full time for the execution of
works as per schedule & specifications.

Construction Manager/Project Engineer


• Responsible for Site Foreman, Engineers, Area Package Managers, Direct
Labour and Subcontractors performance.
• Responsible for all construction and site activities in accordance with the
program and in compliance with the quality specified.
• Coordination with the Sub-contractors.
• Implementing of the Contract requirements on site.
• Site Safety and liaison with Safety Engineer.
• Produce weekly short-term programs with the Planning Department.
• Holding Weekly Coordination Meetings with sub-contractors, liaison with the
staff.
• Issuing Daily Labour& Plant records to the client representative and the
project management team.
• Compiling Site Diary for recording:
• Work being done
• Recording Variation Work
• Recording delays on site
• Record contra changes
• Progress against program
• Weather conditions.
• Action all method statements issued by subcontractors.

QA/QC Engineer (MEP)


• Ensuring that this work activity is according to the Project Specifications.
• To ensure full compliance with contract documents, specifications and this
method statement duly approved by Client.
• To carry out required inspections as notified for all the works.
• To maintain all required quality records .

Page 7 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 8
DRAINAGE AND VENT PIPING SYSTEMS

• Shall check the site activities with the approved method statement and
contract specifications.

Site Foreman
• To ensure that the work crew is familiar with the safety requirements of this
activity.
• To ensure that execution is carried out properly and according to instructions
received from the site engineer.
• To ensure that he has adequate resources of machinery, labor and materials to
carry out all the activities efficiently and to discuss with the site engineer.

Civil Supervision Team & Traffic Control


• The supervisory team, with the assistance of the HSE officer, shall coordinate
the transportation of the permanent and temporary works materials by means
of truck through the site from the stores area to the location of the works
following the directions and notice boards display at site.
• The maximum speed at the working area shall be restricted to Site Safety
Limits.
• The supervisory team shall enforce the application of mounted crackdown for
controlling traffic flow inside the site, consisting of deploying directive signs
at potentially hazardous locations such as the main entrance, exits, etc...
safety boards and notices, flagman, and the necessary staff to conduct the job
safely without compromising the welfare of personnel, property and material.

Workers
• Shall carry out the proper handling and storage of materials
• Shall execute the work according to approved shop drawings as per Forman or
Engineers instructions
• Shall ensure that all safety precautions are properly executed while the works
in ongoing.
• Shall coordinate with the Site Foreman for any problem irises at site or with
other trades to avoid conflicting installations

MEP HSE officer


• Supervising the works to ensure full compliance with HSE requirements and
procedures.
• Will ensure implementation of all HSE procedures related to the nature of the
works being carried out.

Page 8 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 9
DRAINAGE AND VENT PIPING SYSTEMS

MEP Safety Officer: will advise and assist in ensuring that:

• All the requirements described in the HSE plan are implemented.


• Plant & equipment to be used is in good working order and has the correct up to
date certification, where necessary
• Required permits are in place before works commence
• Safe access is provided to the working area.
• Accident/incidents and near misses are reported promptly.
• There is suitable provision of first aid.
• There are suitable measures for the prevention and control of fire.
• Site safety inspections are carried out and reported to project management
• Perform toolbox talks and trainings as per project requirement.

Civil Surveyor
• For checking of level, adjustment before & after activities.
• He shall ensure the level is correct.

8.0 SAFETY HAZARDS AND RISK CONTROL MEASURES:

• Prior to the commencement of any activities, the workforce will receive an


induction talk on the project site safety requirements. This induction talk will
include both activity safety issues, as well as general safety requirements.
• Where possible hazards may arise from Installation and Gravity test of u-PVC
Drainage & Vent Pipe works, the necessary safety measures will be taken to
prevent accident or injury at all times. This may include barriers, warning
tape/net, Dry chemical powder Extinguisher.
• HSE officer will ensure that Personal Protective Equipment is worn by site
personnel at all times during activities.
• Provisions of adequate cool drinking water, shade, and salt tablets will be in
place.
• For HSE plan, safety requirements as defined in Project Specification, will be
implemented. Specific safety training will be provided to personnel for
Installation and Gravity test of Drainage & Vent Pipe works activity.
• Risk Assessment (Attached)

a) Training
Toolbox talks will provide general training and awareness for each activity and also in
Health & Safety matters and precautions.

Page 9 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 10
DRAINAGE AND VENT PIPING SYSTEMS

b) House keeping
All work places where Arco personnel are working will be cleaned from the scrap
material derived from their work ensuring clean and healthy work environment as well
as to maintain free access and egress in the event of emergency.

c) Emergency Arrangements
General: Site general safety procedures will be followed. In case of emergency the
Safety Officer or the most senior employee present will stop the work, and make the
necessary emergency arrangements and report to the assembly points as described
during Site Induction Course.

Fire Precautions: No significant fire risks associated with this activity but general fire
precaution measures will be taken as per general site rules

Communication from site areas to Site Office via mobile phones.

9.0 MATERIALS AS PER THE SPEC AND APPROVED MATERIAL


SUBMITTAL:

Proposed materials as per the project specifications are - RAUPIANO PLUS (SAJ-PO-
CGC-MAR-PL-0018) – Above ground drainage and rain water system - UR
Sound-insulating waste water system suitable for gravity drainage system in accordance
with DIN EN 12056, DIN EN 752 and DIN 1986-100 in buildings and for underground
installation inside and outside the building structure

Upvc Pipes for Vent system, material as per the submittal reference- SAJ-PO-CGC-
MAR-PL-0001-01

1.0 PROCEDURE ERECTION AND INSTALLATION OF ABOVEGROUND


DRAINAGE AND VENT PIPE SYSTEMS:

Preliminary

• Ensure all required documents such as shop drawings, method statement and
risk assessments have been approved and checked by Engineer prior to start of
activity.
• Ensure all the materials are inspected and approved as per QA/QC inspection
and Material Inspection request and are not damaged and defective.
• Ensure all drainage pipes and fittings were cleaned by approved cleaning
agent before start of work.
• All the risks and hazards involved in the activities has been identified and
assessed in the risk assessment. Refer to Attached Risk Assessment
• Ensure sufficient lighting is in place prior to starting the activity.

Page 10 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 11
DRAINAGE AND VENT PIPING SYSTEMS

• Ensure proper access and egress has been maintained throughout the progress.
• All open trenches, pits shall be cordoned by means of safety cones, warning
tape, warning signs and warning flashers in the night.
• All operatives involved in the activity shall be briefed with the risk assessment
and tool box talks to be held.
• All the operatives of the tools must be trained and certified.
• Client waste management guidelines shall be adhered in disposing all the
waste
• Work place shall be cleaned/cleared from all other unwanted materials and
debris prior to start work

A. Handling / Storage of Materials

• Upon receipt of material at site, all material is stored in a safe and secured
manner as per manufacturer’s recommendations.
• All site & store materials must be secured & located in a safe designated
location.
• Correct storage is vital for all materials (indoor & outdoor) as per
manufacturer recommendations. Reasonable care should be used at all times
and when off-loading. Pipes and fittings including supports should be lowered
to the ground and not dropped to the ground. All materials and items must be
covered by polythene or plastic sheet from water, or any site de-bris
• Protecting pipes and fittings from direct sunlight and soiling by covering with
tarpaulins with proper ventilations.
• Stack no more than four wood crates on top of one another.
• Ensure that the wood frames are aligned squarely when stacking.
• Store pipes in such a way that no objects are placed on top of the sockets
• Do not place any other materials over the pipes to avoid damages.
• Only the required quantity of pipes and fittings, anchors and materials for the
specific task will be transported from store to the work place.
• When fork lifts are used to off-load the materials, precautions shall be taken
care as per project HSE plan and safety procedures.

B. Sequence & Method

• Preparatory installation requirements

• Prior to installation of drainage and vent piping works, the supervisor and foreman
will verify and ensure that all the safety requirements have been complied with and
are in place.
• Prior to start the work plumbing engineer and teams should verify all the relevant
construction drawings are available at site and also approved.

Page 11 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 12
DRAINAGE AND VENT PIPING SYSTEMS

• The supervisor will verify that all relevant approved latest revisions of coordination
drawings, shop drawings, technical submittals, inspection and test plans are in the
work place for installation reference. This also includes installation procedures.
• The supervisor and foreman will inspect all the materials delivered to the work place
and ensure that these are the required materials and also for damage or defect.
Materials found not to be as per requirement or with damage or defect will be set
aside. These will be properly labeled and returned to the warehouse. These will also
be reported in a Non-Conformance Report to the QA/QC Engineer.
• The supervisor and foreman will orient and familiarize all the plumbers and labors
involved in the installations regarding the relevant approved shop drawings, technical
submittals, installation procedures and details, acceptance criteria and safety
requirements.
• The supervisor and foreman will examine surfaces to receive drainage and vent pipe
works for compliance with installation tolerances and other required conditions, as
described in the installation requirement. Installation will not proceed until
unsatisfactory conditions have been corrected.
• Before commencing each activity make sure necessary clearances and coordination’s
are obtained from civil side.

• Soffit Mounted Installation

• Checked that the scaffolds are finalized with approved scaffolding tags.
• Transfer the pipes from the stores to the areas which it is to be installed
• Lift tools to the scaffolds using rope
• Move the scaffold into the position and checked that all wheels are locked and
outrigger stabilizer are extended to correct position. Only scaffolds that have been
duly inspected, certified and tagged shall be used
• All routes shall be carefully marked utilizing markers and care shall be taken over to
proceed.
• All the fixing lines shall be marked out on the soffit of the slabs from the bench
marks, marked by the Main Contractor, above finished floor levels in coordination
with other services as per the approved shop drawings/ coordinated drawings
• Install all piping parallel to building wall. Arrange and install to obtain maximum
head room avoiding structural interference.
• Multiple run piping should be installed parallel to each other and spacing should be
maintained to such a distance so as to permit the installation if it is required.
• Make all change in direction and reduction in pipe size using the standard fitting.

Page 12 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 13
DRAINAGE AND VENT PIPING SYSTEMS

• Mark out vertical support threaded rod, channel position from grid lines, marking
provided by the surveyor. Locations will be based on the approved shop drawings
• Check the dimensions to the finished face of the wall and / or column, report any
discrepancy to Arco Concern Engineer
• Secure the first section of vertical support to the soffit as-per the shop drawing detail
• Clean thoroughly the pipes, so that all dust is removed
• Lift the pipes, to the scaffold using lifting machine or chain blocks Fit the bracket
support to the pipe. Note that this operation may be carried at scaffolding level and
the prefabricated assembly lifted into place.
• Check the correct elevation of support brackets from the datum provided by the
surveyor. Do not assume that the floor is at the correct FFL
• Check the tightness of all the bolts
• When sufficient numbers of support brackets are fixed, the pipes can be lifted into the
position and secured to the brackets
• Adjacent length of pipes shall be joined using the above method
• Fittings for the change of direction or elevation shall be selected and installed as-per
the approved shop drawings
• Tools and loose materials to be placed safely
• Pipe work testing shall be undertaken in accordance with ITP

• Wall Mounted Installation

• Move the scaffolding into position and check that all wheels are locked and the
outrigger stabilizers are extended to the correct position.
• Mark out center line of wall brackets position, check the center line is plumb, if using
cast-in channel, check that channel is plumb
• Mark out elevation of wall brackets using datum provided by surveyor. Do not
assume that floor is at correct FFL
• Fit the wall brackets as shown in the approved shop drawing details
• Check tightness of all the bolts
• When sufficient numbers of supports brackets are fixed the pipes may be lifted into
positions and secured to the wall brackets
• Adjacent lengths of pipes shall be joined by using the same method

Page 13 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 14
DRAINAGE AND VENT PIPING SYSTEMS

• Fittings for change of direction or elevation shall be selected and installed as-per the
approved shop drawings
• Tools or loose materials to be placed safely
• Pipe work testing shall be undertaken in accordance with ITP
• Drainage pipes joining methods

• For pipes size 75mm and above, jointing of pipes are carried out by Push-fit joining
method.
• Pipe size 50mm and below are joined together by solvent weld method. The solvent
and glue normal used are Parabond P14.
• Above ground drainage pipes

• All pipe works shall be adequately supported in such a manner as to permit free
movement due to expansion contraction, vibration or other changes in the system.
• All above ground drainage pipes are joined using either Push-fit or solvent weld
jointing method.
• Supporting of pipes shall be arranged as near as possible to joints and changes in
direction. For supporting of pipes, Galvanized steel Split clamps shall be used.
• All vertical pipes (160mm dia. and below) shall be supported using split clamps
screwed to the wall using threaded rods, diameters of which shall be according to the
clamps manufacturer recommendations.
• Where soil and vent pipes are suspended from the underside of the slab, they shall be
held rigid in position. Based on the pipe diameters, Single or double iron supports
shall be used, as required.
• Pipe supports shall be provided at intervals as per Specification Standards.
• Installation shall be started from the base of the stack and worked up. Vertical stacks
shall be adequately supported at the base to stand the total weight of the riser.

• Installation in Risers

• Ensure that the required provision for maintenance of shaft piping is provided in the
block/drywall work as per approved shop drawing and sketches.
• Make sure that proper working platforms certified by authorized safety personal are
made for safe working inside the shaft
• Make the location of the vertical riser and fix the supports (as per approval} at
intervals as specified in approved shop drawings.

Page 14 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 15
DRAINAGE AND VENT PIPING SYSTEMS

• Fix the pipe fittings on the outlets pipes protruding from the slab opening and align to
the plumb of vertical riser.
• Fix the clamps (as per approval} to vertical riser pipes at specified intervals as per
approved drawings or manufacture's recommendations.
• Ensure that the pipes are cut square before they are joined as per manufacture's
recommendation.
• Use cleaning fluid on both surfaces to be joined. This removes all dirt, failure to do
this can result joint failure.
• Apply solvent cement evenly on mating surfaces of both pipes and socket.
• Insert pipe into socket with slight twisting action and full socket depth.
• Surplus cement should be removed with a cloth.
• The joint should be firm enough to handle in 5 minutes.
• The spigot and socket to be joined should be carefully examined for any damage
which would impair the jointing procedure.
• The spigot insertion depth should be measured as the depth from the mouth to the
shoulder of the socket.
• The Spigot and socket should be thoroughly cleaned. All grease, dirt, swarf and other
foreign matter should be removed from the sealing areas.
• The spigot end and the triple seal portion of the sealing ring should be thoroughly
lubricated. The spigot should be lubricated to the full insertion depth and around its
complete circumference. The triple seal should be lubricated around its complete
circumference.
• Immediately after lubrication, the spigot should be brought into contact with the
socket. The spigot pipe and parent joint should be accurately aligned so that the axis
of the pipe is precisely inline
• Adjacent lengths of pipes shall be joined by using the same method.
• Tools and loose materials to be placed safely.
• Floor clean out shall be provided as per the location on drawings, depending upon the
connection, it may be 45-degree Roding eye or straight Roding eye.
• Each floor drain shall be installed with proper water seal, and shall be fitted with
access for cleaning purpose

• Inspection and Pressure Testing

• Pressure testing shall be undertaken in accordance with the Inspection Test Plan.

Page 15 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 16
DRAINAGE AND VENT PIPING SYSTEMS

• Notice of inspection shall be advised to MAIN CONTRACTOR and to the consultant


for their discretionary attendance and witnessing. Notice shall be advised at least 24
hours prior to date of inspection.

• Drainage Piping Test:


• Close openings in piping system and fill with water to point of overflow, but not less
than 30kPa. Water level must not drop 15 minutes before inspection starts through
completion of inspection. As per the manufacturer recommendations.
• Inspect all joints for leakage.
• 30 min of air test also to be done.
• Testing of all the horizontal completed pipes:
For Soil, Waste Pipe and Vent Pipes
• One end of the Pipe line to be raised by 1.5 Mt and all other ends to be plugged with
testing plugs for every floor.
• Line to be filled with clear water to be raised up by 1.5 mtr. height and leave for 4
hours. If any leak was noticed that relevant fittings pipes to be removed and replaced.
Then the test will be re-conducted as mentioned above for 4 hours for Consultant’s
approvals.
• After the approval of the test all the pipes ends shall be closed/ plugged to avoid any
debris going inside the line.
• Wherever the habitants are present the drainage pipes shall be provided with acoustic
insulation.
• Testing of all the vertical completed pipes:
Main Stack & Sub Stack
• Testing to be done by extending one end of each line to 1.5 mtr. Height and plugging
other end for main stack and sub stack for every floor.
• Clear Water shall be filled in the line and Leak test shall be conducted for 4 hours to
be inspected by Consultant.
• After approval of the consultant remove plug in closed all pipe ends and continue for
the next fix.
• Part by part installation & leak test to be done/witnessed by the Main Contractor and
arrange for Inspection with the Consultant.
Condensate Drain Piping
• The material for condensate drain piping shall be uPVC in all areas except in the plant
rooms & roof where the material used shall be GI steel pipe.

Page 16 of 17
The Engineer: The Employer: The Contractor:

Project: 5214483-LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 01
METHOD STATEMENT Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-
INSTALLATION OF ABOVEGROUND
01 Page 17
DRAINAGE AND VENT PIPING SYSTEMS

• The condensate drainage piping shall be installed as per the approved shop drawings.
• The joining of uPVC pipes shall be carried out using solvent cement as per
manufacturer’s recommendation.
• The joining of GI pipes to the uPVC pipes shall be carried out using threaded
connection.
• During installation all straight runs of pipes shall be insulated leaving the joints using
approved insulation as per material submittal.
• Upon completion of installation of sections of condensate drain piping, the same shall
be flow tested.
• All joints shall be insulated upon successful completion of flow test.

7. Environmental and Sustainability Requirements

ARCO Electromechanical will comply with; Federal Law, ‘Concerning


Environmental Protection and Development’ & On the Environment Protection
Regulations in the Emirate of Abu Dhabi.

All works to be conducted in accordance to the project specification and CEMP


(Construction Environmental Management Plan).

A. Waste Management

All waste generated shall be disposed off in accordance with ADEPA (Abu Dhabi
Environmental Policy Agenda) the ’Construction waste management plan”, which
comes under main contractor scope and M/s Arco will follow the same.

B. Hazardous Substance Management

ARCO Electromechanical will deliver, store and use all hazardous substances in
accordance with “Environmental Management Plan” and associated Risk
Assessments. MSDS “Material Safety Data Sheets” shall be provided for all
hazardous sub-stances being used at project site.

Page 17 of 17
Appendix 1
The Engineer: The Employer: The Contractor:

Project: 5214483‐LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 1
Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-01 MS BRIEFING SHEET

METHOD STATEMENT BRIEFING SHEET

Area / Bldg /Location:

Date: Title of Method statement: Method Statement for Aboveground drainage

and Vent piping works

Name of Responsible Site Engineer:

Name of sub‐contractor & Responsible Engineer:

Review (approved / Available / prepared & Explained):


Material list Plant & equipment list Mock up details
Yes / No / NA

Site planning with material


stacking sketch
Yes / No / NA

Risk Assessment plan


Yes / No / NA

Orientation / Briefing including work method, Inspection Test Plan, HSE requirements to
Engineers / Supervisors / Foreman / Key workmen /Operators

S. NO NAME OF EMPLOYEE CATEGORY / ROLE SIGNATURE

1.

2.

3.

4.
The Engineer: The Employer: The Contractor:

Project: 5214483‐LEAD Souk Al Jubail Apartments


Document Number Document Title Rev. 1
Date 10/07/2023
SAJ-PO-CGC-MST-PL-0002-01 MS BRIEFING SHEET

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

Briefing conducted by
Appendix 2
PROJECT TASK SPECIFIC RISK ASSESSMENT Risk Assessment Ref: SAJ-P0-CGC-MST-PL-
0002-01
Project Name: Souk Al Jubail Town Centre & Apartments
Rev No: 01
Activity: INSTALLATION OF ABOVEGROUND DRAINAGE & VENT PIPING Date: 10/07/2023
SYSTEMS
Page 1 of 7

Risk Classification Responsible Person Revised Risk Classification


Risk
Residual
Significant Potential Level
Activity Risk Action to be Taken to Reduce Risk Risk risk
S/N Hazards & Rating
Low/ Rating
Element PROBABI Severity PROBABILITY Severity Low/
Consequences LITY (P) (S) (R) Medium/ (P) (S) (R)
Medium/
PXS High PXS
High
1. The General Unplanned work 4 4 16 High • Comply with legal, contract, local, authorities and method of statement Project Manager 1 4 4 Medium
Requirements, execution without requirements along with manufacturer recommendation of tools.
Prior to start adequate safety • Reduce the human involvement for all tasks ALARP Engineers
the activity. arrangement • 6-point mandatory PPE such as helmets, high viz jacket, coverall, gloves,
goggles, safety, safety shoe and face mask (EN/CE standard) and to be Supervisors
Injuries due to unsafe provided for all site personnel, and specific to task to be provided for
work execution or concerned personnel Site Workers
unsafe site condition • Do not use any homemade tools/platforms/unauthorized connections
• Only well trained, skilled labour and new personnel (shall be trained first)
are allowed to perform the works
• All works shall be carried out fulltime under supervision of supervisor or
foreman
• Training/TBT to be given to all involved personnel regarding (RA, MS,
Chemical MSDS and PPE) and to be recorded through the site
foreman/engineer in presence of HSE rep.
• All tools, equipment, plant shall possess valid documentation as per local
authority
• Comply with any instructions from client/engineer/contractor HSE rep
• Emergency contact details shall be posted at work locations
• Adequate signage shall be posted at work locations and to be in adequate
languages
which can be understood by workforce
• Ensure that all works evolving in any ignition source – hot works are
running through adequate PTW
• MSDS shall be available for all chemicals at store, HSE documentation,
workplace and first aid centre
• During unfavourable weather condition (Humidex exceeding 54 degrees
Celsius {TWL less than 115} / wind speed exceeding 38 kmph / Visibility
less than 50 m / heavy rains etc.) work shall be suspended
• OSHAD CoP shall be complied for all activities performed on
site.
• PTW shall be apply for all high-risk Activity.
• Housekeeping to be done and workplace to be made safe prior to leaving
the workplace
• All workers shall comply with site HSE rules & regulation. Project team
has to comply to project HSE plan.
• Emergency contact numbers to be displayed in prominent places
• Emergency preparedness shall be ensured

2. Site Traffic Vehicular movement on 4 4 16 High • Vehicles and plants on site shall be driven by authorised persons with Project Manager 1 4 4 Medium
site, pedestrian valid documents (licence appropriate to the vehicle driven, 3rd party
crossing/movement near certificates for operating plants etc.) Engineers
site haul road, run over by • All vehicles and plants operated on site shall have valid documents
vehicles, collision, (registration, 3rd party test certificates) Supervisors
overturning vehicles, • Pre-deployment inspection to be done by authorised person, pre-use
poorly maintained site inspection by the operator/driver including walk around inspection before Drivers
roads, unauthorised starting the movement first time and any time after stopped for long time.
Page 1 of 7
SUK-HSE-06/2023
PROJECT TASK SPECIFIC RISK ASSESSMENT Risk Assessment Ref: SAJ-P0-CGC-MST-PL-
0002-01
Project Name: Souk Al Jubail Town Centre & Apartments
Rev No: 01
Activity: INSTALLATION OF ABOVEGROUND DRAINAGE & VENT PIPING Date: 10/07/2023
SYSTEMS
Page 2 of 7

driving, over speeding, • All systems (horn, brakes, reverse horn, mirror, turn indicators, brake
poorly maintained lights etc..) shall be in proper working condition all the time.
vehicles, faulty safety • Traditional dressing / loose clothing shall not be allowed while working
systems (brakes, lights or driving on site. Company uniforms or work wear or proper pants and
et.), severe weather (fog, shirt / T-shirt shall be worn.
sand storm, rain, high • All plants and vehicles shall be parked in safe position in authorised
humidity etc.), leakage of parking area and the cabins to be locked after turning off the engine, keys
fuel or oil, waste dumped shall not be left on the vehicle.
after vehicle maintenance • Site haul roads shall be properly prepared with sufficient width and
on site. maintained including signage, watering for duct suppression, barricading
as far as possible.
Fatality or serious injury, • Pedestrian walkway and crossing to be demarcated and maintained.
minor injury, land • Speed limit shall be imposed with signage and speed humps, over
contamination, fire, speeding to be checked
property damage • Reversing to be restricted to minimum, reverse alarm shall be fitted on all
site vehicles
• Flagman shall be provided to control movement of site vehicles and
plants.
• No major maintenance allowed on site.
• Use drip trays during fuelling and minor maintenance.
• Fire extinguisher shall be available on all plants and vehicles. Drivers
should be trained on basic firefighting techniques during induction.
• Emergency procedures (actions in the event of an accidents, fire or any
such emergency) should be briefed to all operators and drivers.
• All plant operators and drivers shall undergo Occupational Health
Screening as per OSHAD SF CoP 5.0
• Any spillage shall be immediate cleaned up and contaminated soil to be
removed from the area.
• No waste products from vehicle or plant maintenance shall be disposed
off in open area.

3. Working in hot Heat related illnesses Heat 4 4 16 High • Provision of safe working system, Information, instruction, supervision. Project Manager 1 4 4 Medium
and humid stroke, Nausea, head ache • Acclimatization of employees prior to work commencement
climate and even fatality. Heat • Arrange job rotation, adequate rest should be provided, provide adequate Engineers
exhaustion due to loss of cold water to drink.
body fluids, heat Heat • Provision of task specific and mandatory PPEs and its proper usage. Supervisors
cramp, Heat rashes • Electrolyte solutions should be provided
• No works shall be allowed under direct sunlight during June 15 to Sep 15 Site Workers
from 12.30 pm to 3 pm.
• Comply with OSHAD CoP 11.0 Safety in Heat
• Specific summer working plan to be developed, approved from MML and
to be followed strictly and no lone working allowed.
• Provide shelter / umbrellas near the work area for taking short breaks
between the work
• Ensure the continual monitoring and proper supervision.
• Make sure there is heat stress safe work plan with reasonable working
hours and communicated to all.
• Ensure provision of first aid facility and arrange adequate supervision
• Identify early symptoms of heat illness and take preventive measures
• Educate workers to monitor urine colour by individuals, dark colour
indicates dehydration

4. Shifting, Injury or health issues 4 3 12 High • Ensure clear access and egress to the work spot for shifting the material Project Manager 1 3 3 Low
loading/unloa may occur due to: Slips/ • Safe Manual technique to be used for material shifting activities
ding of trip/ falls Poor manual • Appropriate vehicle shall be used for shifting the pipes and fittings Engineers
material handling Improper vehicle • Ensure the pipes bundles are secured properly at vehicle or telehandler
movement Unsecured load Supervisors
Page 2 of 7
SUK-HSE-06/2023
PROJECT TASK SPECIFIC RISK ASSESSMENT Risk Assessment Ref: SAJ-P0-CGC-MST-PL-
0002-01
Project Name: Souk Al Jubail Town Centre & Apartments
Rev No: 01
Activity: INSTALLATION OF ABOVEGROUND DRAINAGE & VENT PIPING Date: 10/07/2023
SYSTEMS
Page 3 of 7

falling from pickup bed at • Follow the safe site speed limit by driver during shifting the pipes and
back Cut/tripping injury fittings Site Workers
Poor storage of material • Adequate wedges or support shall be placed for pipes storage at site
Injury due to lack of • Team lifting/ mechanical aids to be adopted if the material is heavy
attention Falling/tipping • Ensure the work area and access free from tripping/slipping objects
of door Topple of Fork lift • All pipes material shall be stored properly at the designated storage place
or telehandler material • Ensure the safe telehandlers and fork lifts for pipes loading unloading
due to poor handling works with good condition
Property damage • Operators to be trained adequately by 3rd party for handling the
equipment
• Follow the SWL and radius, capacity while lifting and extending the pipes
bundle
• Adequate attention to be maintained by all about surrounding activities,
hazardous workplace, unsafe conditions
• Wear appropriate PPEs by all employees at the site during material
shifting
• Close supervision and monitoring are mandatory for all activity by
competent personnel

5. Preparations Injury or health issues 3 3 9 High • Access and egress to the workplaces shall be suitable and safe for Project Manager 1 3 3 Low
(cutting may occur due to: personnel movement
shaping) of Slip/trip/fall Strikes from • All material to be stored and preparation to be made by only the allotted Engineers
pipes and the pipes whilst carrying area
fittings for Struck with pipes sharp • TBT shall be given to the employees by the foreman prior to starting the Supervisors
installation edges Cut Injury while activity
using hand tools • Foreman to ensure there are no obstructions in the access leading to the Site Workers
workplace
• Personnel carrying the pipes shall be guided accordingly to avoid strikes
to personnel
moving in proximity
• Activity shall be carried out under close supervision
• Good housekeeping practice to be ensured regularly

6. Hand tools Slip/trip/fall Faulty hand 3 3 9 High • Ensure all hand tools are free from any damage. 1 3 3 Low
(Hacksaw tools lead to injury Cut • Pre-use inspection to be conducted by all operatives before using any Engineers
frame with injury due to the use of hand tools
blade, customized hand tools • Homemade /customized hand tools shall be avoided at the workplace Supervisors
Steel/Wire Finger injury while using • All hand tools shall be inspected and maintained properly by authorized
Cutter) usage cable puller Eye, and face store personnel before use Site Workers
for marking, injury due to mushroom • Hand gloves are mandatory while using the cable puller
aboveground head chisel, Injury due to • Appropriate PPEs for face, and eye protection must be worn by all
drainage and lack of attention while operatives
rainwater using hand tools Lack of • Close supervision and monitoring are mandatory for all activities
system PPE usage
installation
7. Portable Injuries as a result of 4 3 12 High • Trained operators only allowed to operate power tools Project Manager 1 3 3 Low
Power tools Flying objects while • All tools shall have valid inspection tags and colour coding where
operation for drilling Entanglement applicable Engineers
Aboveground Contact an electric supply • Double insulated tools are preferable to avoid electrocution as a result of
drainage Slip and fall of material or any malfunction of the power tool Supervisors
system tool onto the person using • Proper insulation of all cables to be ensured
installation it Noise, Vibration, dust • DBs/Generators used for power tools shall be equipped with a 30mA RCD Site Workers
Poor supervision device.
Untrained personnel using • All power tools shall be inspected daily, and the monthly color-coding
the drill machine system shall be implemented.
• Electrical power tools shall be implemented with PAT on a quarterly
basis.
Page 3 of 7
SUK-HSE-06/2023
PROJECT TASK SPECIFIC RISK ASSESSMENT Risk Assessment Ref: SAJ-P0-CGC-MST-PL-
0002-01
Project Name: Souk Al Jubail Town Centre & Apartments
Rev No: 01
Activity: INSTALLATION OF ABOVEGROUND DRAINAGE & VENT PIPING Date: 10/07/2023
SYSTEMS
Page 4 of 7

• Disconnect when not in use


• Store in a safe manner after use
• Trailing cables routed in a safe manner to avoid cable damage and trip
hazard
• ELCB/RCD in the circuit
• Task-specific PPEs shall be used to be safe from flying debris/objects.
• Fire extinguishers available in the area
• Disconnect power when changing drill bits as it could result in
entanglement risk
• No repair allowed on tools unless personnel are competent
• Damaged tools are not allowed to be used on-site, return them to the
store.
• Close supervision to be ensured for such activities
• Access and egress to the workplace shall be safe
• Workplace shall be kept organized to avoid slips/trip hazards
• Tools shall be secured suitably to avoid slipping tools from the hands of
the personnel using it

8. COSHH Use of chemicals may lead 4 3 12 High • Risk of dermatitis or cement burns and precautions explained to all Project Manager 1 3 3 Low
material usage to inhalation of fumes, workers.
for ingestion, contact with • Use cement or cement-containing products within the use-by date. Engineers
Aboveground skin or eye. Eye injury, • Direct skin contacts to be avoided, CE marked PVC gloves used when
drainage allergies, itching or direct handling mortar. Supervisors
system skin contact with the • Good washing facilities on site, with hot and cold water, soap, and basins
installation mortar could also cause large enough to wash forearms. Site Workers
system bricklayer contact • Principal contractor’s first aid includes emergency eyewash.
installation dermatitis and burns • Hazardous / flammable substances shall not be decanted into unmarked
(solvents, containers particularly water bottles or unmarked buckets. Containers
cleaner etc.) shall be clearly labelled with relevant warning symbols
• Adequate PPE to be worn as specified in the MSDS
• Training has to give treat exposure to be given to all operative.
• Supervisor has to be aware of anyone with early signs of dermatitis.
• SDS shall be available for all chemicals
• COSHH assessment shall be conducted
• COSHH training shall be provided to all handling chemicals
• SDS requirements shall be followed for storage, transportation and
disposal of chemical waste.
• All chemical such as flammable materials shall be stored in specific
storage containers with temperature control, monitoring and firefighting
arrangements

Page 4 of 7
SUK-HSE-06/2023
PROJECT TASK SPECIFIC RISK ASSESSMENT Risk Assessment Ref: SAJ-P0-CGC-MST-PL-
0002-01
Project Name: Souk Al Jubail Town Centre & Apartments
Rev No: 01
Activity: INSTALLATION OF ABOVEGROUND DRAINAGE & VENT PIPING Date: 10/07/2023
SYSTEMS
Page 5 of 7

Risk Grading Matrix


SEVERITY
PROBABILITY
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)

Rare (1) 1 2 3 4 5

Possible (2) 2 4 6 8 10

Likely (3) 3 6 9 12 15

Often (4) 4 8 12 16 20

Frequent/Almost Certain (5) 5 10 15 20 25

Absolutely Unacceptably High


15 - 25 Extreme Risk Activity or process should not proceed in current form
Unacceptably High
8 - 12 High Risk Activity or process should be modified to include remedial planning and action and be subject to detailed EHS risk assessment

Acceptable but must be managed at “As Low As Reasonably Practicable” (ALARP) Activity or process can operate subject to
4–6 Moderate Risk management and / or modification
Acceptable without required further action
1 -3 Low Risk
No action required unless escalation of risk is possible

Hierarchy of Control (Controls identified may be a mixture of the hierarchy in order to provide minimum operator exposure):

Elimination Eliminate the hazard.

Substitution Provide an alternative that is capable of performing the same task and is safer to use.

Engineering Controls Provide or construct a physical barrier or guard or technical measures

Administrative Controls Develop policies, procedures practices and guidelines, in consultation with employees, to mitigate the risk. Provide training, instruction and supervision about the hazard.

Personal Protective Equipment Personal equipment designed to protect the individual from the hazard.

Page 5 of 7
SUK-HSE-06/2023
PROJECT TASK SPECIFIC RISK ASSESSMENT Risk Assessment Ref: SAJ-P0-CGC-MST-PL-
0002-01
Project Name: Souk Al Jubail Town Centre & Apartments
Rev No: 01
Activity: INSTALLATION OF ABOVEGROUND DRAINAGE & VENT PIPING Date: 05/07/2023
SYSTEMS
Page 6 of 7

Date of next review (If applicable): Annual Basis or in the event of serious incident
Prepared By Prepared By

Name; Mr.Hussein Gewily Name; Mr. Hussain Zain Al Abdeen

Designation; – Project Manager-ARCO Electromechanical Designation; – MEP Coordinator

Signature; Signature;

Date;
Date; 10/07/2023
Reviewed & Endorsed By Approved By

Name; Mr. Hardeep Name; Mr. Khalid Darwish

Designation; HSE Manager – CGC House Ltd Designation; Project Manager – CGC House Ltd

Signature; Signature;

Date; Date;

Principal Contractor Project Stamp: Task Specific Subcontractor Company Stamp (If Task Lead by
Subcontractor)

Name: M/s CGC House Ltd Name: M/s ARCO

Stamp: Stamp:

Page 6 of 7
SUK-HSE-06/2023
Risk Assessment Ref: SAJ-P0-CGC-MST-PL-
PROJECT TASK SPECIFIC RISK ASSESSMENT
0002-01
Project Name: Souk Al Jubail Town Centre & Apartments Rev No: 01
Activity: INSTALLATION OF ABOVEGROUND DRAINAGE & VENT PIPING Date: 10/07/2023
SYSTEMS Page 7 of 7

Risk Assessment Attendance Sheet


Prior to commencing the activities covered in this safe system of work document all personnel are to sign below to confirm that a clear briefing explaining the job has been given and is understood:

Date Name Designation Signature Emirates ID Number

Page 7 of 7
SUK-HSE-06/2023
EMERGENCY RESPONSE/PROCEDURES

MINOR CASES: MAJOR CASES:


Ensure area operation
Ensure area operation stoppage.
stoppage. SITE INCIDENT
M CONTROLLER Call the operation area first aider,
Call the operation area first
Alert/Assist Male nurse
aider, Alert/Assist Male nurse
PROJECT MANAGER CGC
Inform the HSE officer/Eng. and
Inform the HSE officer/Eng.
assist the external emergency team

ENERGENCY CONTACT

CGCH MALE NURSE ACTION TAKEN:


ACTION TAKEN:
Coordinate with HSE officer/Eng.
Nurse will treat, advice
and report to HSE Coordinate with Male nurse, Inform
Officer/Engineer the authority emergency team and
direct them in location

ACTION:
ACTION: PM Role for Major
HSE Officer/Eng. investigate Project Manager/ HSE officer/ Cases.
the incident and prepare
report
HSE Eng Lead the operation, coordinate with
Mr. Hussain Sawaleh- emergency team for proper rescue
0569021133 events, provide adequate supports
for the other members.

For Major Emergency Role Of HSE/Fire Warden

ACTION: - Manager/ Site incident ACTION: - HSE Manager/ Engineer ACTION: - Fire warden
controller.
1. Coordinate with Emergency 1. Take immediate action as
1. Coordinate with HSE contact to reach out the per his training to fight fire.
2. Organize provisions for location. 2. Evacuate Personnel’s in
other personnel if 2. Rush to the incident area case of fire in safe manner.
required. with his crew member and 3. Provide information to HSE
3. Provides additional necessary rescue elements. manager/Eng.
supports for rescue team. 3. Coordinates and assist PM 4. Acts quickly if requires
4. Based on the severity during rescue effort. assistance from external
additional facilities such as 4. Investigates and provide a help.
transportation, proper total incident/Accident 5. Proper investigation and
alerts to the other report. further reports will submit
members who were in 5. Meeting with PM and to PM.
during the incident. discuss about implementing 6. Discuss and Meet with HSE
5. Meeting with concern further safety officer for implementing
teams for the measurements for proper further safety precautions
investigation and proper work progress. in order to avoid such
reports. incidents.

1. PM/HSE Declares ‘All Clear’ after coordinating with safety teams HSE
officers and concern site engineer, who were during the incident.
2. HSE officer/ Engineer to investigate and submit proper report regarding the
incident.
Project ERT Contact Number
Souk Al Jubail Project – Jubail Island – Abu Dhabi Project Emergency Number # 0503260589

EMERGENCY CO-ORDINATORS आपातकालीनसम वयक জরুরীবিআইডবিস্নউটিএ ‫تنسيق الطوارئ‬


Mr. Khalid Darwish Project Manager 0504113057
Mr. Hardeep Project HSE Manager 0503260589
Mr. Hanny Logistic & Emergency Manager 0545864645
Mr. Anand Construction Manager 0553087654
Mr. Wasim Akram Emergency Coordinator 0557688191
Mr. Baljinder First Aider 0561832279
TBA Male Nurse TBA
Nearest Hospital Ahalia Hospital - Hamdan Street 02 6262666

EMERGENCY SERVICE PROVIDERS आपातकालीन सेवा दाता জরুরীপরিষেবা


প্রদানকারী ‫تقديم خدمات الطوارئ‬
Civil Defense Ambulance Police
997 998 999
Project Electrical Team
Mr. Belal Hossin Electrical Supervisor 0545864677
Project Mobilization Manager Heavy Equipment Operator
Mr. Nasir 0507818920 Mr. Gurdeep 0524380413
Appendix 3
Appendix 4
The Engineer: The Employer: The Contractor:

INSPECTION AND TEST PLAN FOR ABOVEGROUND DRAINAGE AND VENT PIPING WORKS

Client:-Jubail Island Investment Company (JIIC) Project:- 5214483-LEAD - SOUK AL JUBAIL TOWEN CENTRE AND APARTMENTS
PROJECT MANAGEMENT:-LEAD Development and Project Management Discipline:- Mechanical
Engineer:-ATKINS MEMBER OF SNC-LAVALIN GROUP ITP serial No:-MST-ITP-PL-002
Contractor:-CONSTRUCTION GENERAL CONTRACTING HOUSE LTD Date:-10/07/2023
RESPONSIBILITY
STAGE OF
SR REFERENCE ACCEPTANCE QA/QC RECORD TO BE USED CONTROL
CONSTRUCTION INSPECTION METHOD
.NO DOCUMENTS CRITERIA/Norms. TO VERIFY DOCUMENT DATA/FORMS ATKINS/
ACTIVITIES ARCO CGCH THIRD PARTY
ENGINEER
1 Preparation works before Construction
As per approved IFC drawings
& Approved material
Engineers approval Approved Method
A Method Statement Prior to start Work submittal. Project NA P H H NA
Statement
Specification & Contract
Documents.
All Document have a As per approved IFC drawings
minimum approval & Method statement. Project Approved
B Shop Drawings Prior to start Work NA H H H NA
status "B" Approved Specification & Contract Shop Drawings
as Noted Documents.

All Document have a As per approved IFC drawings


Approved
Material Submittal, minimum approval & Method statement. Project
C Prior to start Work Material Submittal, PQP P H H NA
Prequalification. status "B" Approved Specification & Contract
Prequalification.
as Noted Documents.

All Document have a As per approved IFC drawings Approved


Material delivery & minimum approval & Method statement. Project Material H/
D Prior to start Work PQP NA S NA
handling status "B" Approved Specification & Contract Inspection PE/QC
as Noted Documents. (MIR)
As per approved IFC,Shop
Proper Storage &
Compliance to drawings & Method
Protection of Approved H/
E Prior to start Work approved shop statement. Project Checklist PQP H S NA
Materials delivered at PE/QC
drawing / IFC Specification & Contract
site
Documents.
2 SEQUENCY OF WORK

As per approved material


Material submittsl/ MIR to be As per approved material H/
A Material Inspection Prior to start activity Approved MIR submittal/MIR/sample NA W NA
B status submittal/MIR/sample tag PE/QC
tag
Work execution and As per the Approved Shop Approved Shop
B Approved Shop drawing/MOS As approved MOS E/H H S NA
Implementation specification drawing/MOS drawing/MOS

Drainage and Vent Pipe As per the Approved Shop Work inspection/ check Work inspection/ check
C Approved Shop drawing/MOS E/H H H H
installation specification drawing/MOS list list
As per the Under ground piping Approved Shop
D Pipe invert level, survey Approved Shop drawing/MOS As per specification H H W NA
specification Specifications drawing/MOS
Visual/practical internal As per the Under ground piping Approved Shop
E Approved Shop drawing/MOS As per specification H S NA NA
inspection specification Specifications drawing/MOS
Actual Inspection by As per the Approved Shop As per approved
F Approved Shop drawing/MOS WIR H H H H
Engineer specification drawing/MOS drawings
As per the Approved Shop Approved Shop
G Gravity Test Test reports WIR H H H H
specification drawing/MOS drawing/MOS/WIR
H -Hold Point
Inspection point

E -Execaution
S -Surveillance
w-witness
R-Review
P- prepare
Appendix 5
CHECK LIST
Project Name 5214483-LEAD SOUK AL JUBAIL APARTMENTS
JUBAIL ISLAND INVESTMENT – SOLE
PROPRIETORSHIP LLC P O BOX 39294 ABU ATKINS ENGINEERING
Client/Employeer The Engineer/Consultant
DHABI, UAE, LEAD DEVELOPMENT AND CONSULTANT
PROJECT MANAGEMENT CONSULTANTS
The Contractor CONSTRUCTION GENERAL CONTRACTING HOUSE LTD
MEP Sub
ARCO Electromechanical LLC
Contractor

Checklist Title: Inspection Check List For Installation of Above ground Drainage & Vent Pipe Checklist No.
work
Works Location: As per attached highlighted drawing Related ITP # MST-ITP-PL-002
Related Drawing(s) As attached Related MS #
Status - Acceptable
SN Description of checking to be carried out Remarks
Arco/CGC ATKINS

1 Pre Construction Stage

Approved material submittal is attached

Approved related drawings are attached

2 Construction Stage

Material inspection request approval is attached

Material used is per approved brand

No visible damaged seen on installed pipes

Check that pipes and fittings are damage free prior to installation

Check and verify that the installation details are approved by the engineer

Check the jobsite is ready for activity to commence

Check the civil work/bedding are ready for Drainage pipes installation

Check the joints, adaptors and couplers of pipe installation are properly applied with
approved adhesive/glue for rigidity

Check the supports for pipe used for specific system

Check the Elevation and orientation are correct

Check the installation is perpendicular or Horizontal to wall in neat manner

Check the pipe work for not obstructing or clashing with other services

All cut portions of the pipes is properly smoothened to avoid sharp edges and leakage.

Gravity Testing is done and no leak is found

3 Post Construction Stage

System final connection to equipment / sanitary fixtures completed

System pre testing and commissioning completed

System testing and commissioning completed

Snagging list rectified and completed

Remarks:

Accompanying document :
For Contractor Arco / CGC
For Supervision Consulatnt (Engineer)
Quality Engineer
Name
Designation
Date
GRAVITY TEST REPORT OF ABOVEGROUND DRAINAGE & VENT PIPE
WORKS
Project Title 5214483-LEAD SOUK AL JUBAIL APARTMENTS Checklist No.

JUBAIL ISLAND INVESTMENT – SOLE PROPRIETORSHIP LLC P O BOX


Client/Employeer 39294 ABU DHABI, UAE, LEAD DEVELOPMENT AND PROJECT Date: 10/07/2023
MANAGEMENT CONSULTANTS
The
ATKINS ENGINEERING CONSULTANT
Engineer/Consultant
The Contractor CONSTRUCTION GENERAL CONTRACTING HOUSE LTD Related ITP #

MEP Sub Contractor ARCO Electromechanical LLC Related MS #

Works Location As attached

Details of Pipeline
Location of Pipe line

Dia. of pipeline

Gravity Test Medium Water


Test pipe stub out exposed1.5mtr from
the installed pipes
Gravity test initial time
Gravity test final time
Duration of Test
All joints are free from leakage

Remarks:

Accompanying document : For Contractor Arco/CGC For Supervision Consultant

Quality Engineer (Engineer)

Name:
Signature:
Date:
Appendix 6
Proposed Organization Chart
OBADA ALAQTASH
General Manager
LEGEND:

OFFICE
BACKUP OMAR KAYYALI
Operations Director

FULLTIME
ROHAN HAIETHAM
ANUBIS RAJA CHAOUDHURY AHMAD MAGDY ELAZIEM
Contracts Manager Planning Manager Projects Director HSE Manager

SPECIALIST
CONTRACTOR
DAWN CHICA MOHAMAD TAHA BRITON NKHEBWA
Planning Engineer Hussein Gewily HSE Officer HSE Officer
Project Manager

ABEDALRAHMAN HUSSEIN
MUHAMMAD TAYSEER ALAA ALSHAFIEY MOHAMMAD SHAWQI Monish AMIT TIWARI AHTESHAM RIAZ
BANAT SAWALMEH ARLYN DIATA Sr. QA/QC
Construction Manager Authority Liaison Construction Manager Sr. QA/QC Engineer Head of Mechanical Head of Electrical
Sr. Mechanical Sr. Electrical Document Controller Engineer
Officer PARCEL 2 (Mech.) Design Design
Engineer Engineer PARCEL 1 (Elect.)

MECHANICAL THOUFIQUE Bakrudeen


Mech. T & C Elect. T & C ELECTRICAL TEAM
ELECTRICAL TEAM TEAM Storekeeper Mechanical BIM Electrical BIM
Engineer Engineer MECHANICAL TEAM Storekeeper PARCEL 2 Coordinator
PARCEL 1 PARCEL 2 Coordinator
PARCEL 1

DONALD PAUL ALI AHMAD RASHEED KHAN UDAY PRATAB Ali Ahmed Furqan
AMIR KHAN TOMMY DAGATAN Natural Gas HV Specialist
RAJNISH KUMAR HV Specialist Site Mechanical Specialist Contractor Site Mechanical Site Electrical Contractor Site Electrical Mechanical Electrical
ARUL KUMAR Site Electrical Contractor Site Electrical Engineer Engineer Engineer Engineer Draftsman Draftsman
Natural Gas Engineer
Site Mechanical Site Mechanical Engineer
Specialist Contractor
Engineer Engineer

Gladson Aamir
Plumbing Fire Fighting Plumbing Electrical Fire Alarm Specialist Electrical
Fire Alarm Specialist Electrical HVAC Supervisors HVAC Supervisors Mechanical Electrical
Electrical Supervisors Specialist Contractor Supervisors Supervisors Contractor Supervisors
Fire Fighting Plumbing Contractor Supervisors Draftsman Draftsman
Plumbing HVAC Supervisors Supervisors
HVAC Supervisors Specialist Contractor Supervisors
Supervisors

Technicians and Technicians and BMS Specialist Technicians and Technicians and Technicians and ELV Specialist Technicians and
ELV Specialist Electrical Labors Labors Contractor Labors Labors Labors Contractor Labors
Technicians and
BMS Specialist Technicians and Technicians and Contractor Supervisors
Technicians and Technicians and Labors
Contractor Labors Labors
Labors Labors

ARCO ELECTROMECHANICAL LLC