Professional Documents
Culture Documents
This method statement describes work of installing lightning pole and road sign on connecting bridge works.
The stage of installing lightning pole and road sign are illustrated by Figure 1 and 2.
START
NO
Check the quality of material
and according to the spec
YES
Material Delivery
Foundation Work
Installing Lightning
Pole
Installing Electrical
Work NO
Megger Test
YES
FINISH
NO
Check the quality of material
and according to the spec
YES
Material Delivery
Foundation Work
FINISH
2. Work Explanation
2.1 Material
Materials used for lightning pole work are as follows :
1. Street lightning pole type A2
2. Cable Type-1
3. Cable Type-2
4. Cable Type-3
5. Cable Type-4
6. Cable Type-5
7. Cable Type-6
8. PVC Conduit Ø 4”
9. Pull Box Type A and B
2.2 Tools
Tools used for lightning pole and road sign work are as follows :
1. Stamper
2. Hammer
3. Welding Tools
4. Bolt
5. Bolt Fastener
6. Excavator
7. Screwdriver
8. Saw Cutting Concrete Machine
b. Electrical Work
1. Installation of electric wiring
2. Cable which is under protected by using PVC pipe
3. Installed pull box on the lightning pole
4. Do megger test to make sure lightning pole working
a. Installation of Foundation
The installation of foundation consist of :
Cutting concrete on the barrier for the foundation.
Install the plate as foundation for road sign and supports
Carried out casting after the position of the plate has been fixed in aacordance with the image
Check the road sign and support aacording with the shop drawing
Installation of road sign with the support (pole) done by welding according to the specification and
shop drawing
Lifting the road signs and support using excavator and installed according to the location of
foundation.
3. Quality Plan
Quality assurance works in this Project describes as follows:
Material Selection
NO
Material Test
OK
Construction Work
NO
OK
Finish
The Contractor will carry out following actions to avoid mistakes and to secure the quality.
• Especially, the Contractor will explain the work procedure and materials to be used to the sub-contractor.
• All survey work will be checked by the Engineer’s surveyor.
• All material and shop drawing will be tested and approved prior to commence the work.
• Sampling and Test in the site will be done with attendance of the Engineer’s inspector.
4. Work Scheduling
Work schedule will be planned to follow description on Table 2 and Table 3 below