1. Compilation basis
2. Construction deployment
2.1 Construction preparation
2.1.1 Production preparation
3. Construction of Bored Pile
3.1 Procedures
Once the reinforcement cage has been installed, it has to gradually place the guidance
pipe. The end of guidance pipe is no more than 500mm above the hole bottom.
Before the under - water concrete casting, it has to re-measure the hole depth ; once the
thickness os bottom sediment exceeds the request of Technical code of building Pile
foundations (JGJ 94-2008), it has to clean the hole again, upon eligibility, the quality
inspector has to sign and issue the inspection certificate befor the casting the under –
water concrete.
3.7 Concrete Quality Control of Bored Pile
3.7.1 Control of slump
3.7.2 Casting
Some typical pictures