WORKING PROCEDURE PLAN OF WORKING BORED PILES

1. Compilation basis

2. Construction deployment
2.1 Construction preparation
2.1.1 Production preparation
3. Construction of Bored Pile
3.1 Procedures

Drawing 1. Equiment of bored pile (only for referece)

Drawing 2. Flowchart of bored pile


3.2 Drilling Hole

3.3 Hole Cleaning

3.4 Fabrication and hoisting of reinforcement cage


The method of fix the core drilling pipe is the same to the sonic pipe.

3.5 Installation of guidance pipe

Once the reinforcement cage has been installed, it has to gradually place the guidance
pipe. The end of guidance pipe is no more than 500mm above the hole bottom.

3.6 Concrete casting

Before the under - water concrete casting, it has to re-measure the hole depth ; once the
thickness os bottom sediment exceeds the request of Technical code of building Pile
foundations (JGJ 94-2008), it has to clean the hole again, upon eligibility, the quality
inspector has to sign and issue the inspection certificate befor the casting the under –
water concrete.
3.7 Concrete Quality Control of Bored Pile
3.7.1 Control of slump

3.7.2 Casting
Some typical pictures