DS Myanmar Factory Project
Construction Method Statement
TABLE OF CONTENTS
1. INTRODUCTION ..........…………………………………………………………… 1
2. SCOPE …..…………………………………………………………….. 1
4. SAFETY .………………....……...………………………………………………… 4
7 APPENDIXES ..…………………………………………………………………… 5
Page | 2
DS Myanmar Factory Project
Construction Method Statement
1. Introduction
The objective of this method statement is to explain the method to be carried out
during the execution stage of Footing Concreting Work to ensure the work is done
in compliance with the technical specifications and guided by suitable engineering
standard practices.
This project is located at the Thilawa SEZ Zone B of Thanlyin City in Yangon
Division in Myanmar.
2. Scope
The purpose of this Method Statement is to describe the measures and ways
of completing concrete pour work for footings on this project. The works shall be
carried out in compliance with the drawings and project specification.
3. Work Procedure
1. Reinforcement
It is intended to cut and bend rebar on site as per the bar bending
schedules.
Some footings are composed of top and bottom reinforcement, the
bottom bars shall be supported with concrete block of correct
thickness.
Inspection Request (IR) would be submitted for steel reinforcement
for checking and approval of the engineer prior to concrete casting.
2. Casting
Make sure that the area within the shutter to be poured with concrete
is cleaned. Remove all rubbish, dirt, and any other deleterious
material.
Inspection Request shall be submitted to the engineer or Consultant
for approval of fixed steel reinforcement and installed formworks.
Readymade concrete shall be provided from batching plant approved
by the Engineer. The rate of concrete supply shall be 30 to 50 Cubic
Meter per hour.
The required number of concrete pumps will be available on site.
Concrete vibrators shall be ready to use at time of receiving concrete.
Number of vibrators shall be depending on concreted area to improve
well compaction for concrete pump.
Computerized delivery sheet shall be checked for conformity as per
the approved design mixer.
Slump and temperature shall be carried out from each concrete truck
mixer.
Slump shall not mare than 150mm and not less than 100mm as per
Engineers instruction and approval. Temperature of fresh concrete
shall not more than 30 deg. Celsius as per BS standard.
All data required for daily concrete schedule sheet will be recorded
in the daily concrete pour record.
Concrete at truck mixer shall not exceed more than 90 minutes from
leaving batching plant.
Page | 3
DS Myanmar Factory Project
Construction Method Statement
4. Safety
1. All works shall comply with safety procedure or instruction set out in project
safety plan and MJTD rules and regulations.
2. Basic PPE to worn by all staff and labourers.
3. Trained operator and watch man will be engaged to control or operate heavy
equipment machine.
4. The casting area shall be protected to avoid the damage, use proper barrier.
1. Concrete Pump
2. Truck Mixer
3. Concrete Vibrators
4. Wheel Borrow
5. Surveying instrument
6. Metal tape
7. Slump cone
8. Slump tray
9. Trowel
10. Cubes
11. Shovel
Page | 4
DS Myanmar Factory Project
Construction Method Statement
7. Appendixes
Page | 5
DS Myanmar Factory Project
Construction Method Statement
Appendix-A
Site Organization
Contractor
Project Manager
Ye Yint
Construction Manager
Kamar Aye Thuzar Aung Naing Lin Tun Than Zaw Aung
Site Engineer
Page | 6
DS Myanmar Factory Project
Construction Method Statement
Appendix- B
IN CASE OF SIT
1. FIRE MANAGEMENT
2. INJURY
3. INCIDENT
KAS
MAIN CONTRACTOR
EMERGENCY CALL LIST & TELE NO.
Page | 7
DS Myanmar Factory Project
Construction Method Statement
Appendix- C
Page | 8
INSPECTION SHEET
Project DS MYANMAR FACTORY
Works Rebar
Date Time
Building □
Checked
No Check Item How Tolarence Judgement Date
by
Clean, no oil, no rust scaling, free from any
1 Visual
foreign materials
2 Correct size, dimension, type and grade Visual
3 Fixing and placing Visual
4 Mechanically cut Visual
5 Free from cracks and damage Visual
6 Cold bended Visual
7 Diameter and quantity Visual
Stirrup, Hoop: +/-
8 Rebar spacing and alignment Measuring 5mm,
Other:+/-10mm
Stirrup, Hoop: +/-
9 Lapping and anchorage length and location Visual 5mm,
Other:+/-10mm
Upper ground:
30-40mm,
10 Concrete cover Visual Under ground:
50- 75mm
( SEE ATTACHMENT)
SIT SIT
QA/QC ENGINEER PM/CM
INSPECTION SHEET
Date Time
Building □
Checked
No Check Item How Tolarence Judgement Date
by
Fixing rigidity, gaps are wedge, prevent
1 Virtual
inclining and movement
Support spacing, fixing of bottom form and
2 Virtual
shoring
3 Vertically/ plumbness of form Measuring
4 Column and external wall formwork height Measuring
5 Column, beam and slab Measuring
6 Footing and pile cap size Measuring
7 Straightness of top external wall form Measuring
Concrete shuttering formwork and
8 Virtual
construction joint treatment
9 Clean and free from foreign materials Virtual
Insert cast in metal, insulator, E&M pipe
10 Virtual
embedment and sleeves
11 Configuration joint location Virtual
Measuring
12 Construction joint location
& Virtual
13 Water tightness and no big gaps Virtual
Measuring
14 Concrete cover and spacer blocks
& Virtual
( SEE ATTACHMENT)
SIT SIT
QA/QC ENGINEER PM/CM
Form No :
Rev. No :
CONCRETE POUR RECORD
D / O No. :
Date :
1A Location of Pour :
1B Job Name :
1C Unit :
2 Mixer Truck No :
5 Slump At Site : mm
6 Temperature At Site : °C
8 Cube Reference :
Inspected By :
Signature :
Date :