DS Myanmar Factory Project

Construction Method Statement

DS MYANMAR FACTORY PROJECT

METHOD STATEMENT FOR

FOOTING CONCRETE POURING

FEBRUARY 19, 2020

Submitted by

STERLING INDUSTRIAL TECHNOLOGIES

COMPANY LIMTED

Page | 1
DS Myanmar Factory Project
Construction Method Statement

TABLE OF CONTENTS

1. INTRODUCTION ..........…………………………………………………………… 1

2. SCOPE …..…………………………………………………………….. 1

3. WORK PROCEDURE ……………………………………………………………… 1

4. SAFETY .………………....……...………………………………………………… 4

5 EQUIPMENT AND TOOLS ………………………....…...………....................... 4

6 MATERIALS AND REFERENCES …………………………………………… 4

7 APPENDIXES ..…………………………………………………………………… 5

Page | 2
DS Myanmar Factory Project
Construction Method Statement

1. Introduction

The objective of this method statement is to explain the method to be carried out
during the execution stage of Footing Concreting Work to ensure the work is done
in compliance with the technical specifications and guided by suitable engineering
standard practices.
This project is located at the Thilawa SEZ Zone B of Thanlyin City in Yangon
Division in Myanmar.

2. Scope

The purpose of this Method Statement is to describe the measures and ways
of completing concrete pour work for footings on this project. The works shall be
carried out in compliance with the drawings and project specification.

3. Work Procedure

1. Reinforcement
 It is intended to cut and bend rebar on site as per the bar bending
schedules.
 Some footings are composed of top and bottom reinforcement, the
bottom bars shall be supported with concrete block of correct
thickness.
 Inspection Request (IR) would be submitted for steel reinforcement
for checking and approval of the engineer prior to concrete casting.

2. Casting
 Make sure that the area within the shutter to be poured with concrete
is cleaned. Remove all rubbish, dirt, and any other deleterious
material.
 Inspection Request shall be submitted to the engineer or Consultant
for approval of fixed steel reinforcement and installed formworks.
 Readymade concrete shall be provided from batching plant approved
by the Engineer. The rate of concrete supply shall be 30 to 50 Cubic
Meter per hour.
 The required number of concrete pumps will be available on site.
 Concrete vibrators shall be ready to use at time of receiving concrete.
Number of vibrators shall be depending on concreted area to improve
well compaction for concrete pump.
 Computerized delivery sheet shall be checked for conformity as per
the approved design mixer.
 Slump and temperature shall be carried out from each concrete truck
mixer.
 Slump shall not mare than 150mm and not less than 100mm as per
Engineers instruction and approval. Temperature of fresh concrete
shall not more than 30 deg. Celsius as per BS standard.
 All data required for daily concrete schedule sheet will be recorded
in the daily concrete pour record.
 Concrete at truck mixer shall not exceed more than 90 minutes from
leaving batching plant.

Page | 3
DS Myanmar Factory Project
Construction Method Statement

 On acceptance, mix shall be directly unloaded in the concrete


pumps. Care shall be taken to make sure that concrete mix is not
dropping from more than a height of 2 meter.
 During the concrete placing, tamping and vibrating shall be carried
out by experienced operators using vibrators. Care shall be taken to
ensure that vibration is continued long enough to produce optimum
consolidation without segregation of aggregates.
 When the concrete reach proposed level; hand trowelling should
carry out to get a smooth surface according to the top of footing
level.
 For the method of concrete curing, conventional water spraying
technique shall be applied.
 For Approval: Inspection request would be submitted to the main
contractor Engineer for the concrete pouring approval.

4. Safety

1. All works shall comply with safety procedure or instruction set out in project
safety plan and MJTD rules and regulations.
2. Basic PPE to worn by all staff and labourers.
3. Trained operator and watch man will be engaged to control or operate heavy
equipment machine.
4. The casting area shall be protected to avoid the damage, use proper barrier.

5. Equipment and Tools

1. Concrete Pump
2. Truck Mixer
3. Concrete Vibrators
4. Wheel Borrow
5. Surveying instrument
6. Metal tape
7. Slump cone
8. Slump tray
9. Trowel
10. Cubes
11. Shovel

6. Materials and Reference


1. Concrete Grade for Structure : F’C = 17.0 MPA
2. Rebar Grade for Structure Members: Grade = SD 490
Deformed Bars : 18 mm dia., 16mm dia., 14mm dia., & 12mm dia.

The materials mentioned above are as per our project specification.

Page | 4
DS Myanmar Factory Project
Construction Method Statement

7. Appendixes

1. Site Organization……………………………………. Appendix - A


2. Emergency Flow Chart…………………………….. Appendix - B
3. Inspection Sheets ………………………………….. Appendix – C

Page | 5
DS Myanmar Factory Project
Construction Method Statement

Appendix-A

Site Organization

Contractor

Sterling Industrial Technologies Co., Ltd

Project Manager

Ye Yint

Construction Manager

Wai Phyo Aung

Surveyor Quantity Surveyor QC/Senior Site Engineer Safety Supervisor

Kamar Aye Thuzar Aung Naing Lin Tun Than Zaw Aung

Site Engineer

Tin Wam Moe

Page | 6
DS Myanmar Factory Project
Construction Method Statement

Appendix- B

Emergency Flow Chart

EYE WITNESS SIT


INFORMER
SITE ENGINEER

IN CASE OF SIT

1. FIRE MANAGEMENT
2. INJURY
3. INCIDENT

KAS

MAIN CONTRACTOR
EMERGENCY CALL LIST & TELE NO.

1. THANLYIN POLICE OFFICE – 056-25504


2. THANLYIN GENERAL HOSPITAL - 09-420123047 CLIENT
3. SIT CO., LTD – 09-421016897
4. MAIN CONTRACTOR – 09-950270527

Page | 7
DS Myanmar Factory Project
Construction Method Statement

Appendix- C

Page | 8
INSPECTION SHEET
Project DS MYANMAR FACTORY
Works Rebar
Date Time
Building □
Checked
No Check Item How Tolarence Judgement Date
by
Clean, no oil, no rust scaling, free from any
1 Visual
foreign materials
2 Correct size, dimension, type and grade Visual
3 Fixing and placing Visual
4 Mechanically cut Visual
5 Free from cracks and damage Visual
6 Cold bended Visual
7 Diameter and quantity Visual
Stirrup, Hoop: +/-
8 Rebar spacing and alignment Measuring 5mm,
Other:+/-10mm
Stirrup, Hoop: +/-
9 Lapping and anchorage length and location Visual 5mm,
Other:+/-10mm
Upper ground:
30-40mm,
10 Concrete cover Visual Under ground:
50- 75mm

11 Beam sleeve location and reinforcement bar Visual

( SEE ATTACHMENT)

SIT SIT
QA/QC ENGINEER PM/CM
INSPECTION SHEET

Project DS MYANMAR FACTORY


Works Formwork

Date Time
Building □
Checked
No Check Item How Tolarence Judgement Date
by
Fixing rigidity, gaps are wedge, prevent
1 Virtual
inclining and movement
Support spacing, fixing of bottom form and
2 Virtual
shoring
3 Vertically/ plumbness of form Measuring
4 Column and external wall formwork height Measuring
5 Column, beam and slab Measuring
6 Footing and pile cap size Measuring
7 Straightness of top external wall form Measuring
Concrete shuttering formwork and
8 Virtual
construction joint treatment
9 Clean and free from foreign materials Virtual
Insert cast in metal, insulator, E&M pipe
10 Virtual
embedment and sleeves
11 Configuration joint location Virtual
Measuring
12 Construction joint location
& Virtual
13 Water tightness and no big gaps Virtual
Measuring
14 Concrete cover and spacer blocks
& Virtual

( SEE ATTACHMENT)

SIT SIT
QA/QC ENGINEER PM/CM
Form No :
Rev. No :
CONCRETE POUR RECORD

PROJECT : DS MYANMAR FACTORY

D / O No. :

Date :

ITEM DESCRIPTION AT WORK SITE

1A Location of Pour :

1B Job Name :

1C Unit :

2 Mixer Truck No :

3A Arrival Time : A.M / P.M

3B Departure Time : A.M / P.M

4 Pouring Time : Hours

5 Slump At Site : mm

6 Temperature At Site : °C

7 No. of Cubes Taken : Nos

8 Cube Reference :

9 Actual Quantity Poured : m³

10 Cumulative Quantity Poured : m³

Inspected By :

Signature :

Date :