Method Statement for Footing Concrete


Pouring
By Noel Mades Posted on February 2, 2014 In Method Statement (Civil) 17 Comments

Sharing is Caring:

When we talk about foundations, there are various types that we can use
depending on the structural design. The types of foundations are Isolated
footing, Combined Footing, Mat Foundations, Strap Foundations, Bored 88
/ 100 BOOKS
Pile, Pile Drive, etc. So in this article, we’ll talk about isolated footing
concrete pouring.

In our project, we do have usually Isolated footing foundations. When I was in my


previous company we had Mat Foundation which I’m going to write a method
statement later. So I’m going to share with you the Method Statement or Procedure on
how we’ll going to pour concrete on the footing foundation.

Here is the Method Statement for Footing Concrete Pouring

https://www.qualityengineersguide.com/method-for-footing-concrete-pouring 1/9
4/14/22, 3:48 PM Method Statement for Footing Concrete Pouring

1. Title

Method Statement for Footing Concrete Pouring

2. Scope

The purpose of this Method Statement for Footing Concrete Pouring is to describe the
measures and ways of completing concrete pour work for footings on this project. The
works shall be carried out in compliance with the drawings and project specifications.

3. Work Procedure for MS for Footing Concrete Pouring

1.  Reinforcement
It is intended to cut and bend rebar on site as per the bar bending
schedules.

CATEGORIES

Select Category

Some footings are composed of top and bottom reinforcement, the bottom
bars shall be supported with concrete block or spacer of correct thickness.
Inspection Request ( IR ) would be submitted for steel reinforcement for
checking and approval of the Engineer prior to concrete casting. SELECT WHAT TO READ NEXT
2. Casting
Make sure that the area within the shutter to be poured with concrete is
cleaned. Remove all rubbish, dirt, and any other deleterious material via an
air compressor.
Inspection Request can be submitted to the Engineer or Consultant for
approval of fixed steel reinforcement and installed forms if casting shall not
take place on the same day.

https://www.qualityengineersguide.com/method-for-footing-concrete-pouring 2/9
4/14/22, 3:48 PM Method Statement for Footing Concrete Pouring

Black HDPE 200 GSM


Duty Plastic Tarpauli
Tadpatri for Multipur
Strong and Long Las

Ad Agribegri

 Readymade concrete shall be provided from batching plant approved by


the Engineer. The rate of concrete supply shall be 30 to 50 Cubic Meters
per hour.
The required number of concrete pumps will be available on-site; extra
pump will be on standby ready for any incident circumstances.
Concrete vibrators shall be ready to use at the time of receiving concrete.
Number of vibrators shall be depending on the concreted area to improve
well compaction for concrete pump.
Computerized delivery tickets shall be checked for conformity as per the
approved design mix.
Slump and temperature shall be carried out from each concrete truck mixer.
Slump shall not be more than 150mm and not less than 100mm as per
Engineers instruction and approval. Temperature of fresh concrete shall not
be more than 30 deg. Celsius as per BS Standard.

OTHER RELATED BSI STANDARD

All data required for daily concrete schedule sheet will be recorded in the
daily concrete pour card.
Concrete at truck mixer shall not exceed more than 90 minutes from
leaving batching plant.
On acceptance, mix shall be directly unloaded in the concrete pumps. Care
shall be taken to make sure that concrete mix is not dropping from more
than a height of 2 meter. 
Concrete when introduced to the footing at the first level of 400mm shall
then be vibrated, the same shall be done for the succeeding layer of

https://www.qualityengineersguide.com/method-for-footing-concrete-pouring 3/9
4/14/22, 3:48 PM Method Statement for Footing Concrete Pouring

concrete until footing top level is reached.

Landscaping Ideas

When concrete reaches the proposed level; hand trowelling should carry
out to get a smooth surface according to the top footing level.
When the concrete is cured it shall then be applied with a waterproofing
system in accordance with the specification.
For approval: Inspection request would be submitted to the Engineer or
Consultant for the concrete pouring approval.

4. Safety

1. All works shall comply with safety procedures or instructions set out in the project
safety plan and Municipality rules and regulations.
2. Basic PPE to be worn by all staff and laborers.
3. Trained operators and banks man will be engaged to control or operate heavy
equipment machines.
SEARCH
5. Equipment and Tools
Search the site

Black HDPE 200 GSM


Mipatex HDPE Plastic
Heavy Duty Plastic… Geomembrane Black Fish…
ADVERTISEMENT
₹1,885 ₹2,300 ₹1,278 ₹2,856

Mipatex 40mm Rain Pipe


Mipatex Garden Shade Net
With Male Adapter +… 50% Shade, UV Stabilized,…
₹1,330 ₹2,793 ₹505 ₹1,060

Agribegri

1. Concrete pump
2. Truck Mixer
3. Boom loader
4. Bobcat
5. Concrete Vibrators
6. Wheel borrow
7. Surveying instrument
8. Metal tape 
9. Slump cone
10. Slump tray
11. Trowel
https://www.qualityengineersguide.com/method-for-footing-concrete-pouring 4/9
4/14/22, 3:48 PM Method Statement for Footing Concrete Pouring
12. Cubes
13. Shovel

6. Materials and Reference

1. C40/20 Concrete Grade with 70-80% GGBS


2. Deformed Bars: 20mm dia., 16mm dia., 10mm dia.

The material mentioned above is as per our project specification, please read your
project specs before writing the method statement for footing concrete pouring.

If you have any further comment or suggestion on the above method statement for
footing concrete pouring, you may write it down or leave a reply below.

Thanks!

Sharing is Caring:

Read also:  Method Statement for Blinding Works

Concrete Batching Plants -


Black HDPE 200 GSM Heavy
IIT Madras CCE & Intellipaat Get Hired By Product

Concrete Production
Duty Plastic Tarpaulin, Tirpal,
Companies
Equipment Tadpatri for Multipurpose,

Strong and Long Lasting

Product by Agribegri

Ad simemug.com Ad Agribegri Ad Intellipaat Ad Pesto Tech

Latest Omega Watches for


Jaypore Classics For Men
Men

Ad Kapoor Watch Company Ad Jaypore

About the Author

NOEL My Other Posts 

Hi! Welcome to my blog. My name is Noel Mades and I’m the author
of qualityengineersguide.com. I am a Civil Engineer by profession
 
but I’ve specialized and taken the journey in the field of Quality
Engineering. I’ve worked as a Quality Engineer in the well-known
companies in the United Arab Emirates for almost eleven years. 

https://www.qualityengineersguide.com/method-for-footing-concrete-pouring 5/9
4/14/22, 3:48 PM Method Statement for Footing Concrete Pouring

17 Comments

-18% -55% -31% -52%

Online Agro Store


Agribegri

west pump manage December 26, 2021

In your area, is the transfer of concrete on the foundation done through mud
pumps? It would be interesting if you could expand the profession to
transport raw materials with a variety of powerful pumps.

REPLY

Lilia Robberts June 11, 2018

Comment Text*Having a good foundation for a home is such a necessity! So


it is really important that things are done right when it comes to pouring the
concrete. I haven’t done it a lot, so I will need to look into getting help to
ensure things are done right. Reading this article I found it important to know
that truck mixers shouldn’t exceed more than 90 minutes.

REPLY

Ashiqullah Bashari November 19, 2018

Yes 90 minutes is the initial setting time of concrete. But it might be


different in temperature change.

REPLY

Hajeemoosa May 22, 2018

Hi Noel,

Greetings,

Do you have any idea about the construction methodology for a 22-storey
building in UAE?

Please advice.

REPLY

rania May 10, 2018

Where is carpentry works?


REPLY

https://www.qualityengineersguide.com/method-for-footing-concrete-pouring 6/9
4/14/22, 3:48 PM Method Statement for Footing Concrete Pouring

Author
Noel Mades May 10, 2018

I will try to make a blog post for that. Thanks.

REPLY

Ashraf Indikar January 28, 2018

Sir please answer my questions and help me.

1. Sir if we are using ajax mixtures in site, so how much rotation it should
take to mix it?

2. You have said that for vibrators the minimum height should be 400mm of
concrete, but our process of concreting is slow for filling 400mm it will set so
what is the procedure for vibration?

3. We are using 60mm vibrators is it proper, for our OHT?

REPLY

cathy May 30, 2017

Hello Sir Noel. Your post is very helpful. May i ask if your company is hiring
newbie Civil Engineer, with 1 year experienced working in DPWH?

REPLY

Author
Noel Mades May 31, 2017

I am not sure if they are hiring but it is better that you are here in
UAE. They will not hire from abroad unless they will go to the
Philippines to hire people. What field of civil engineering you
want to work on?

REPLY

Mohamed January 10, 2017

Please I need method statement for reinforced raft, thank you.

REPLY

NASEER AHMED July 27, 2014

Sir my question is ? How many hold points? Please reply.

REPLY

Author 
Noel Mades July 27, 2014

https://www.qualityengineersguide.com/method-for-footing-concrete-pouring 7/9
4/14/22, 3:48 PM Method Statement for Footing Concrete Pouring

If you are in Abu Dhabi-UAE, the footing should be inspected by the


Municipality Inspector so that is the hold there and also the Materials to be
used like concrete, rebars and the test report for FDT.

REPLY

barr February 9, 2014

sir i have a question about the result of slump test, what if the result is more
than 150mm or less than 100mm? as QA/QC engineer what are we going to
do if this case is happen?

REPLY

Author
Noel Mades February 9, 2014

Both are rejected, it is obvious that the slump did not comply to
the requirements. The slump tolerance which I did not show
which is written like this 125+/-25mm, but before you take action
consult first your Quality Manager.

REPLY

ubed June 7, 2017

Hello. Can I get method statement for raft foundation?

REPLY

Author
Noel Mades June 9, 2017

Hi, you can check my books at the product page.

REPLY

RAVI April 27, 2014

The slump has to be decide at the time of Design mix it will vary
depends upon grade of concrete and type of structure. In chimney
concrete slump require more ordinary foundations less than
100mm.

Check your design mix accordingly you can proceed.

REPLY


Leave a Reply

https://www.qualityengineersguide.com/method-for-footing-concrete-pouring 8/9
4/14/22, 3:48 PM Method Statement for Footing Concrete Pouring

Comment Text*

Name*

Email*

Website

Post Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

ABOUT ME RECENT POSTS RECENT COMMENTS CONNECT WITH ME

Hi! Welcome to my blog. My name is 7 Types of Concrete Crack SECD Technical Services LLC on Top      
Noel Mades and I’m the author of Repairing 10 Best Civil Engineering Blogs and
qualityengineersguide.com. I am a Civil Websites – 2022
 March 18, 2022
Engineer by profession but I’ve Advertise With Us
Noel Mades on 7 Reasons Why
specialized and taken the journey in Method Statement for Engineers Want to Work In Dubai –
the field of Quality Engineering. Read Installation and Testing Reason 8 is BONUS Donate With Us
More Here. of …
Noel Mades on Method Statement
 March 3, 2022
for Painting Works
The Top 10 Best Rafaqat Ali on Method Statement for
Construction Companies Painting Works
In …
Marites on The Top 10 Best
 February 27, 2022
Construction Companies In The
Philippines – 2022

Copyright © 2022. by qualityengineersguide.com: Theme by MyThemeShop TERMS OF USE WEBSITE DISCLAIMER PRIVACY POLICY

https://www.qualityengineersguide.com/method-for-footing-concrete-pouring 9/9

You might also like