SUMMARY
TODATE CUMULATIVE THIS WEEK PREVIOUS WEEK CUMULATIVE
Overall
Planned Earned Variance Planned Earned Variance Planned Earned Variance
Percentage % 44.33% 52.45% 8.12% 0.00% 0.00% 0.00% 44.33% 52.45% 6.92%
Manhours 13994.50 16556.41 2561.90 0.00 0.00 0.00 13994.50 16179.00 2184.50
WBS PROGRESS
TODATE CUMULATIVE THIS WEEK PREVIOUS WEEK CUMULATIVE
WBS
Planned Earned Variance Planned Earned Variance Planned Earned Variance
Construction 48.61% 57.72% 9.11% 0.00% 0.00% 0.00% 48.61% 57.72% 9.11%
Fabshop Work 100.00% 98.94% -1.06% 0.00% 0.00% 0.00% 100.00% 98.94% -1.06%
Off Plot Work 100.00% 71.07% -28.93% 0.00% 0.00% 0.00% 100.00% 71.07% -28.93%
On plot Work 0.00% 28.07% 28.07% 0.00% 0.00% 0.00% 0.00% 28.07% 28.07%
Client CPP
Budgeted Manhours 31568
Updated on Thursday, January 30, 2020