Construction of QTIF-716 PWI Flow line at QW-21

Activity ID Activity Name Original Start Finish Schedule % Performance 2019 2020
Duration Complete % Complete
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
380.00 28-Feb-19 A 16-May-20 62.44% 42.56% 16-May-20, Construction of QTIF
Construction of QTIF-716 PWI Flow line at QW-21
Milestones 380.00 28-Feb-19 A 16-May-20 0% 0% 16-May-20, Milestones

MS-010 Contract Award 0.00 28-Feb-19 A 100% 100% Contract Award


MS-020 Issue IFC Drawings and MRS 0.00 28-Feb-19 A 100% 100% Issue IFC Drawings and MRS
MS-030 Delivery of All Aramco Supplied Materials 0.00 27-Feb-20 100% 0% Delivery of All Aramco Supplied Materials
MS-040 Delivery of All Contractor Supplied Materials 0.00 27-Feb-20 100% 0% Delivery of All Contractor Supplied Materials
MS-045 Commencement of Fabrication Shop Activities 0.00 29-Feb-20 100% 0% Commencement of Fabrication Shop Activities
MS-050 Completion of Fabrication Shop Activities 0.00 27-Feb-20 100% 0% Completion of Fabrication Shop Activities
MS-060 Commencement of Well-Site Activities/Site Handover to Contractor 0.00 29-Feb-20* 100% 0% Commencement of Well-Site Activities/Site Handover to C
MS-070 Completion of Well-Site Activities/Site Handover to Aramco 0.00 26-Mar-20 0% 0% Completion of Well-Site Activities/Site Handover
MS-090 Mechanical Completion Certificate (MCC) 0.00 02-Apr-20 0% 0% Mechanical Completion Certificate (MCC)
MS-130 Project Closing 0.00 16-May-20 0% 0% Project Closing
MS-PROJ Project Management & Site Operation (LOE) 368.00 28-Feb-19 A 16-May-20 85.05% 81.79% Project Management & Site Ope

Procurement 107.00 28-Feb-19 A 30-Nov-19 A 0% 0% 30-Nov-19 A, Procurement

Delivery of Aramco Materials 24.00 28-Feb-19 A 30-Oct-19 A 0% 0% 30-Oct-19 A, Delivery of Aramco Materials
601-AM-01 Delivery of 8" Water Injection Wellhead Flowline Pipe & Fittings 12.00 28-Feb-19 A 30-Oct-19 A 100% 100% Delivery of 8" Water Injection Wellhead Flowline Pipe & Fittings
702-AM-01 Delivery of UFM 24.00 28-Feb-19 A 06-May-19 A 100% 100% Delivery of UFM
702-AM-02 Delivery of TIT PIT, Thermowell 22.00 28-Feb-19 A 05-May-19 A 100% 100% Delivery of TIT PIT, Thermowell
702-AM-03 Delivery of MCV 24.00 28-Feb-19 A 07-May-19 A 100% 100% Delivery of MCV
Delivery of Contractor Materials 88.00 24-Mar-19 A 30-Nov-19 A 0% 0% 30-Nov-19 A, Delivery of Contractor Materials
601-702-BOQ Prepare BOQ/Material Approvals/Issue PO 16.00 24-Mar-19 A 02-May-19 A 100% 100% Prepare BOQ/Material Approvals/Issue PO
601-CM-01 Delivery of Concrete, Rebar and Anchor Bolt Materials 19.00 04-Apr-19 A 29-Jun-19 A 100% 100% Delivery of Concrete, Rebar and Anchor Bolt Materials
601-CM-02 Delivery of Structural Steel Materials 19.00 16-Apr-19 A 24-Oct-19 A 100% 100% Delivery of Structural Steel Materials
702-CM-01 Delivery of Power Cables 28.00 21-Apr-19 A 30-Nov-19 A 100% 100% Delivery of Power Cables
702-CM-03 Delivery of Instrument Cables 70.00 14-Apr-19 A 30-Nov-19 A 100% 100% Delivery of Instrument Cables
702-CM-07 Delivery of Ground Cable & Rod 28.00 28-Apr-19 A 24-Jun-19 A 100% 100% Delivery of Ground Cable & Rod
702-CM-08 Delivery of Lighting Poles With Fixtures 36.00 21-Apr-19 A 30-Nov-19 A 100% 100% Delivery of Lighting Poles With Fixtures

Construction 299.00 01-May-19 A 02-Apr-20 69.37% 47.28% 02-Apr-20, Construction

Fabrication Shop Work 47.00 01-May-19 A 13-Feb-20 A 100% 100% 13-Feb-20 A, Fabrication Shop Work
Pre-cast 46.00 18-May-19 A 13-Feb-20 A 100% 100% 13-Feb-20 A, Pre-cast
601-PR-001 Precasting & Painting PS-2 foundation for Wellsite 20.00 18-May-19 A 01-Jun-19 A 100% 100% Precasting & Painting PS-2 foundation for Wellsite
601-PR-002 Precasting & Painting of Removable Anchor Foundation For Wellsite 12.00 25-May-19 A 29-Aug-19 A 100% 100% Precasting & Painting of Removable Anchor Foundation For Wellsite
601-PR-003 Precasting & Painting of Wellhead Platform Foundations for Wellsite 10.00 25-May-19 A 08-Aug-19 A 100% 100% Precasting & Painting of Wellhead Platform Foundations for Wellsite
601-PR-004 Precasting & Painting of Wellhead Guardrail Foundations for Wellsite 10.00 01-Jun-19 A 08-Aug-19 A 100% 100% Precasting & Painting of Wellhead Guardrail Foundations for Wellsite
702-PR-001 Precasting & Painting of Lighting Pole Foundations for Wellsite 10.00 19-May-19 A 13-Feb-20 A 100% 100% Precasting & Painting of Lighting Pole Foundations for Wellsite
Structural Fabrication 34.00 01-May-19 A 03-Oct-19 A 100% 100% 03-Oct-19 A, Structural Fabrication
601-ST-001 Fabrication & Painting of Wellhead Guardrail for Wellsite 10.00 01-Jun-19 A 01-Aug-19 A 100% 100% Fabrication & Painting of Wellhead Guardrail for Wellsite
601-ST-002 Fabrication & Painting of Wellhead Platform For Wellsite 10.00 01-Jun-19 A 03-Oct-19 A 100% 100% Fabrication & Painting of Wellhead Platform For Wellsite
601-ST-003 Fabrication & Painting of Removable Anchor For Wellsite 8.00 01-May-19 A 19-Sep-19 A 100% 100% Fabrication & Painting of Removable Anchor For Wellsite
601-ST-004 Fabrication & Painting of Portable Valve Operating Platform for Wellsite 10.00 19-May-19 A 03-Oct-19 A 100% 100% Fabrication & Painting of Portable Valve Operating Platform for Wellsite
Spool Fabrication 26.00 05-May-19 A 18-Sep-19 A 100% 100% 18-Sep-19 A, Spool Fabrication
601-SP-001 Fabrication & Girth Coating of 8" PWI W/H F/L Shop joints for Wellsite 22.00 05-May-19 A 18-Sep-19 A 100% 100% Fabrication & Girth Coating of 8" PWI W/H F/L Shop joints for Wellsite
601-SP-002 Fabrication & Girth Coating of 8" Removal Anchor Shop joints for Wellsite 12.00 18-May-19 A 26-Jun-19 A 100% 100% Fabrication & Girth Coating of 8" Removal Anchor Shop joints for Wellsite
On Plot Work 57.00 27-Jan-20 A 02-Apr-20 59.71% 30.64% 02-Apr-20, On Plot Work
Site Mobilization 5.00 27-Jan-20 A 30-Jan-20 A 0% 0% 30-Jan-20 A, Site Mobilization
ON-SM-01 Mobilization of Shelter and Portable Cabin on Site 4.00 27-Jan-20 A 30-Jan-20 A 100% 100% Mobilization of Shelter and Portable Cabin on Site
ON-SM-02 Mobilization of Equipments on Site 4.00 27-Jan-20 A 30-Jan-20 A 100% 100% Mobilization of Equipments on Site
ON-SM-03 Mobilization of Manpower on Site 4.00 27-Jan-20 A 30-Jan-20 A 100% 100% Mobilization of Manpower on Site
ON-SM-04 Getting Site work Permit 1.00 27-Jan-20 A 27-Jan-20 A 100% 100% Getting Site work Permit
Piping Tie-In 48.00 27-Jan-20 A 26-Mar-20 70.82% 32.81% 26-Mar-20, Piping Tie-In
601-ME-001 Site Survey 2.00 27-Jan-20 A 28-Jan-20 A 100% 100% Site Survey

Actual Work Critical Remaining Work Summary Date Revision Checked Approved Data Date Page
Remaining Work Milestone 27-Feb-20 1 of 3
Construction of QTIF-716 PWI Flow line at QW-21
Activity ID Activity Name Original Start Finish Schedule % Performance 2019 2020
Duration Complete % Complete
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
601-ME-002 Wellpad Preparation & Pipe Trench Excavation 6.00 02-Feb-20 A 06-Feb-20 A 100% 100% Wellpad Preparation & Pipe Trench Excavation
601-ME-003 Installation of Wellhead Flowline Tie-in Foundations (PPS-2) 4.00 06-Feb-20 A 13-Feb-20 A 100% 100% Installation of Wellhead Flowline Tie-in Foundations (PPS-2)
601-ME-004 Installation of Removal Anchor Foundation & Base Plate 3.00 09-Feb-20 A 27-Feb-20 A 100% 100% Installation of Removal Anchor Foundation & Base Plate
601-ME-005 Installation of Wellhead Flowline Tie-in 8" Spools 8.00 25-Feb-20 A 05-Mar-20 100% 14% Installation of Wellhead Flowline Tie-in 8" Spools
601-ME-006 Installation of 8" Removal Anchor Spool 4.00 07-Mar-20 10-Mar-20 100% 0% Installation of 8" Removal Anchor Spool
601-ME-006N Installation of Positive Coupling 4.00 07-Mar-20 10-Mar-20 100% 0% Installation of Positive Coupling
601-ME-007 Installation of 8" Valves of Wellhead Flowline 4.00 07-Mar-20 10-Mar-20 100% 0% Installation of 8" Valves of Wellhead Flowline
601-ME-008 Bolt Torquing & Hydrotesting of 8" Wellhead Flowline 2.00 11-Mar-20 12-Mar-20 100% 0% Bolt Torquing & Hydrotesting of 8" Wellhead Flowline
601-ME-009 External Painting of Welhead Flowline Tie-in 4.00 12-Mar-20 16-Mar-20 25% 0% External Painting of Welhead Flowline Tie-in
601-ME-010 Installation of Wellhead Platform Foundation 2.00 12-Mar-20 14-Mar-20 50% 0% Installation of Wellhead Platform Foundation
601-ME-011 Installation of Wellhead Platform 3.00 15-Mar-20 17-Mar-20 0% 0% Installation of Wellhead Platform
601-ME-012 Installation of Wellhead Gaurd Rail Foundation 2.00 10-Feb-20 A 17-Mar-20 0% 95% Installation of Wellhead Gaurd Rail Foundation
601-ME-013 Installation of Wellhead Gaurd Rail 3.00 18-Mar-20 21-Mar-20 0% 0% Installation of Wellhead Gaurd Rail
601-ME-013C Installation of Crash Barrier 3.00 22-Mar-20 24-Mar-20 0% 0% Installation of Crash Barrier
601-ME-014 Installation of Valve Operating Platform 2.00 25-Mar-20 26-Mar-20 0% 0% Installation of Valve Operating Platform
Electrical & Instrumentation 41.00 01-Feb-20 A 26-Mar-20 54.94% 46.89% 26-Mar-20, Electrical & Instrumentation
702-EI-001 Site Survey 1.00 01-Feb-20 A 01-Feb-20 A 100% 100% Site Survey
702-EI-002 Cables Trench Excavation 6.00 03-Feb-20 A 05-Mar-20 100% 85% Cables Trench Excavation
702-EI-003 Pulling & Laying of Power Cables 5.00 16-Feb-20 A 11-Mar-20 100% 82% Pulling & Laying of Power Cables
702-EI-004 Pulling & Laying of Instrument Cables 5.00 16-Feb-20 A 11-Mar-20 100% 82% Pulling & Laying of Instrument Cables
702-EI-005 Pulling & Laying of Grounding Cable 5.00 16-Feb-20 A 11-Mar-20 100% 60% Pulling & Laying of Grounding Cable
702-EI-006 Testing & Commissioning of All Cables 3.00 12-Mar-20 15-Mar-20 100% 0% Testing & Commissioning of All Cables
702-EI-007 Cables Trench Backfill 4.00 16-Mar-20 19-Mar-20 75% 0% Cables Trench Backfill
702-EI-008 Installation of MCV 2.00 21-Mar-20 22-Mar-20 0% 0% Installation of MCV
702-EI-009 Installation of UFM 2.00 21-Mar-20 22-Mar-20 0% 0% Installation of UFM
702-EI-010 Installation of PIT, TIT & TW 3.00 21-Mar-20 23-Mar-20 0% 0% Installation of PIT, TIT & TW
702-EI-011 Installation of Lighting Pole Foundation 4.00 10-Feb-20 A 18-Mar-20 0% 85% Installation of Lighting Pole Foundation
702-EI-012 Installation of Lighting Poles with FIxtures 5.00 19-Mar-20 24-Mar-20 0% 0% Installation of Lighting Poles with FIxtures
702-EI-013 Installation of Analog & Digital Junction Box Foundation 2.00 20-Feb-20 A 27-Feb-20 A 0% 100% Installation of Analog & Digital Junction Box Foundation
702-EI-014 Installation of Analog & Digital Junction Box 3.00 21-Mar-20 23-Mar-20 0% 0% Installation of Analog & Digital Junction Box
702-EI-015 Termination of All Power Cables 2.00 25-Mar-20 26-Mar-20 0% 0% Termination of All Power Cables
702-EI-016 Termination of all Instrument Cables 2.00 25-Mar-20 26-Mar-20 0% 0% Termination of all Instrument Cables
702-EI-017 Termination of all Grounding Cables 2.00 25-Mar-20 26-Mar-20 0% 0% Termination of all Grounding Cables
Cathodic Protection Surface Assembly 37.00 10-Feb-20 A 29-Mar-20 61.1% 16.87% 29-Mar-20, Cathodic Protection Surface Assemb
902-CP-000 Site Survey 1.00 10-Feb-20 A 10-Feb-20 A 100% 100% Site Survey
902-CP-001 CP Cable Trench Excavation 7.00 10-Feb-20 A 14-Mar-20 100% 60% CP Cable Trench Excavation
902-CP-002 Pulling & Laying of CP Cable 3.00 27-Feb-20 A 17-Mar-20 100% 24% Pulling & Laying of CP Cable
902-CP-003 Installation of Surface Casing for Drilling 5.00 07-Mar-20 11-Mar-20 100% 0% Installation of Surface Casing for Drilling
902-CP-004 Anode Hole Drilling & Deep Anode Bed Installation 5.00 12-Mar-20 17-Mar-20 60% 0% Anode Hole Drilling & Deep Anode Bed Installation
902-CP-005 Installation of Multipurpose Junction Box with foundation for CP 5.00 07-Mar-20 11-Mar-20 100% 0% Installation of Multipurpose Junction Box with founda
902-CP-006 Installation of Anode Junction Box with foundation for CP 5.00 12-Mar-20 17-Mar-20 20% 0% Installation of Anode Junction Box with foundation f
902-CP-007 CP Cable Trench Backfilling 3.00 18-Mar-20 21-Mar-20 0% 0% CP Cable Trench Backfilling
902-CP-008 Termination of all CP Cables 2.00 25-Mar-20 26-Mar-20 0% 0% Termination of all CP Cables
902-CP-009 Commissioning of CP System 3.00 26-Mar-20 29-Mar-20 0% 0% Commissioning of CP System
Testing & Commissioning 3.00 26-Mar-20 29-Mar-20 0% 0% 29-Mar-20, Testing & Commissioning
801-RS-001 Commissioning of RTU Points 3.00 26-Mar-20 29-Mar-20 0% 0% Commissioning of RTU Points
Yes Items Closing 6.00 26-Mar-20 01-Apr-20 0% 0% 01-Apr-20, Yes Items Closing
601-MC-001 Walk through & Closing of Yes Items For Tie-in 6.00 26-Mar-20 01-Apr-20 0% 0% Walk through & Closing of Yes Items For Tie-in
702-MC-001 Walk through & Closing of Yes Items For E&I 6.00 26-Mar-20 01-Apr-20 0% 0% Walk through & Closing of Yes Items For E&I
Mechanical Completion 0.00 02-Apr-20 02-Apr-20 0% 0% 02-Apr-20, Mechanical Completion
MCC MCC Routing 0.00 02-Apr-20 0% 0% MCC Routing

Closeout 44.00 26-Mar-20 16-May-20 0% 0% 16-May-20, Closeout

Actual Work Critical Remaining Work Summary Date Revision Checked Approved Data Date Page
Remaining Work Milestone 27-Feb-20 2 of 3
Construction of QTIF-716 PWI Flow line at QW-21
Activity ID Activity Name Original Start Finish Schedule % Performance 2019 2020
Duration Complete % Complete
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Exception Items Closing 7.00 26-Mar-20 02-Apr-20 0% 0% 02-Apr-20, Exception Items Closing
601-EX-001 Closing of Exception For Tie-in 7.00 26-Mar-20 02-Apr-20 0% 0% Closing of Exception For Tie-in
702-EX-001 Closing of Exception Items For E&I 7.00 26-Mar-20 02-Apr-20 0% 0% Closing of Exception Items For E&I
As-built Approval 12.00 02-Apr-20 15-Apr-20 0% 0% 15-Apr-20, As-built Approval
601-AB-001 Approval of As-Built For Tie-in 12.00 02-Apr-20 15-Apr-20 0% 0% Approval of As-Built For Tie-in
702-AB-001 Approval of As-Built For E&I 12.00 02-Apr-20 15-Apr-20 0% 0% Approval of As-Built For E&I
Materials Reconciliation 20.00 16-Apr-20 09-May-20 0% 0% 09-May-20, Materials Reconciliation
601-MR-001 Approval of MRS For Tie-in 20.00 16-Apr-20 09-May-20 0% 0% Approval of MRS For Tie-in
702-MR-001 Approval of MRS For E&I 20.00 16-Apr-20 09-May-20 0% 0% Approval of MRS For E&I
Final CRPO Reconciliation 16.00 16-Apr-20 04-May-20 0% 0% 04-May-20, Final CRPO Reconciliatio
FCRPO Final CRPO Reconciliation 16.00 16-Apr-20 04-May-20 0% 0% Final CRPO Reconciliation
Final Invoice/Closing 6.00 10-May-20 16-May-20 0% 0% 16-May-20, Final Invoice/Closing
FCLOSE Final Invoice Approval 6.00 10-May-20 16-May-20 0% 0% Final Invoice Approval

Actual Work Critical Remaining Work Summary Date Revision Checked Approved Data Date Page
Remaining Work Milestone 27-Feb-20 3 of 3