ICE ROOM WORK PROGRESS TRACKING SHEET

CONCRE DOOR FINAL


LOCATION PLAT FORM & CHIPPING BLOCK WORK FORM WORK REINFORCEMENT PLASTER PAINT
TE FIX FINISH

PALACE 1 25% 50% 75% 100% 25% 50% 75% 100% 25% 50% 75% 100% 25% 50% 75% 100% 100% 25% 50% 75% 100% 100% 25% 50% 75% 100% 100%

PALACE 2 25% 50% 75% 100% 25% 50% 75% 100% 25% 50% 75% 100% 25% 50% 75% 100% 100% 25% 50% 75% 100% 100% 25% 50% 75% 100% 100%

ATOLL 25% 50% 75% 100% 25% 50% 75% 100% 25% 50% 75% 100% 25% 50% 75% 100% 100% 25% 50% 75% 100% 100% 25% 50% 75% 100% 100%