01 MONITORING PENGECORAN BOREPILE

Jumlah Titik 44 MT : 23.40 m

PersLeg ABCD 11 Pad : 22.00 m


KEDALAMAN (m) TES TEKAN BETON
TGL VOLUME JUMLAH MUTU
NO PEKERJAAN LOKASI KETERANGAN
PENGECORAN MT Pad M3 BENDA UJI BETON 7 HARI 14 HARI 28 HARI

1 24-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg D 8 6.00 3 K 225 - 16 31-Jan-2023 7-Feb-2023 21-Feb-2023 1 Titik
2 24-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg D 11 7.00 3 K 225 - 16 31-Jan-2023 7-Feb-2023 21-Feb-2023 1 Titik
3 25-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg D 6 6.00 3 K 225 - 16 1-Feb-2023 8-Feb-2023 22-Feb-2023 1 Titik
4 25-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg C 1 6.00 3 K 225 - 16 1-Feb-2023 8-Feb-2023 22-Feb-2023 1 Titik
5 26-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg C 2 6.00 3 K 225 - 16 2-Feb-2023 9-Feb-2023 23-Feb-2023 1 Titik
6 26-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg D 1 6.00 3 K 225 - 16 2-Feb-2023 9-Feb-2023 23-Feb-2023 1 Titik
7 27-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg C 3 6.00 3 K 225 - 16 3-Feb-2023 10-Feb-2023 24-Feb-2023 1 Titik
8 27-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg D 2 6.00 3 K 225 - 16 3-Feb-2023 10-Feb-2023 24-Feb-2023 1 Titik
9 30-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg D 4 6.00 3 K 225 - 16 6-Feb-2023 13-Feb-2023 27-Feb-2023 1 Titik
10 30-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg C 5 6.00 3 K 225 - 16 6-Feb-2023 13-Feb-2023 27-Feb-2023 1 Titik
11 30-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg D 3 6.00 3 K 225 - 16 6-Feb-2023 13-Feb-2023 27-Feb-2023 1 Titik
12 30-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg C 4 6.00 3 K 225 - 16 6-Feb-2023 13-Feb-2023 27-Feb-2023 1 Titik
13 31-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg D 5 6.00 3 K 225 - 16 7-Feb-2023 14-Feb-2023 28-Feb-2023 1 Titik
14 31-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg C 6 6.00 3 K 225 - 16 7-Feb-2023 14-Feb-2023 28-Feb-2023 1 Titik
15 31-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg D 7 6.00 3 K 225 - 16 7-Feb-2023 14-Feb-2023 28-Feb-2023 1 Titik
16 31-Jan-2023 Borepile 23.40 22.00 Tower 1, Leg C 7 6.00 3 K 225 - 16 7-Feb-2023 14-Feb-2023 28-Feb-2023 1 Titik
17 2-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg D 10 6.00 3 K 225 - 16 9-Feb-2023 16-Feb-2023 2-Mar-2023 1 Titik
18 2-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg C 9 6.00 3 K 225 - 16 9-Feb-2023 16-Feb-2023 2-Mar-2023 1 Titik
19 2-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg D 9 6.00 3 K 225 - 16 9-Feb-2023 16-Feb-2023 2-Mar-2023 1 Titik
20 2-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg C 8 6.00 3 K 225 - 16 9-Feb-2023 16-Feb-2023 2-Mar-2023 1 Titik
21 4-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg C 11 6.00 3 K 225 - 16 11-Feb-2023 18-Feb-2023 4-Mar-2023 1 Titik
22 5-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg C 10 6.00 3 K 225 - 16 12-Feb-2023 19-Feb-2023 5-Mar-2023 1 Titik
23 5-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 8 6.00 3 K 225 - 16 12-Feb-2023 19-Feb-2023 5-Mar-2023 1 Titik
24 5-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 11 6.00 3 K 225 - 16 12-Feb-2023 19-Feb-2023 5-Mar-2023 1 Titik
25 5-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 7 6.00 3 K 225 - 16 12-Feb-2023 19-Feb-2023 5-Mar-2023 1 Titik
26 6-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 7 6.00 3 K 225 - 16 13-Feb-2023 20-Feb-2023 6-Mar-2023 1 Titik
27 6-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 10 6.00 3 K 225 - 16 13-Feb-2023 20-Feb-2023 6-Mar-2023 1 Titik
28 6-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 10 6.00 3 K 225 - 16 13-Feb-2023 20-Feb-2023 6-Mar-2023 1 Titik
29 6-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 9 6.00 3 K 225 - 16 13-Feb-2023 20-Feb-2023 6-Mar-2023 1 Titik
30 6-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 1 6.00 3 K 225 - 16 13-Feb-2023 20-Feb-2023 6-Mar-2023 1 Titik
31 7-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 6 6.00 3 K 225 - 16 14-Feb-2023 21-Feb-2023 7-Mar-2023 1 Titik
32 7-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 6 6.00 3 K 225 - 16 14-Feb-2023 21-Feb-2023 7-Mar-2023 1 Titik
T.01 MONITORING PENGECORAN BOREPILE

Jumlah Titik 44 MT : 23.40 m

PersLeg ABCD 11 Pad : 22.00 m


KEDALAMAN (m) TES TEKAN BETON
TGL VOLUME JUMLAH MUTU
NO PEKERJAAN LOKASI KETERANGAN
PENGECORAN MT Pad M3 BENDA UJI BETON 7 HARI 14 HARI 28 HARI

33 7-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 2 6.00 3 K 225 - 16 14-Feb-2023 21-Feb-2023 7-Mar-2023 1 Titik
34 7-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 1 6.00 3 K 225 - 16 14-Feb-2023 21-Feb-2023 7-Mar-2023 1 Titik
35 8-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 9 6.00 3 K 225 - 16 15-Feb-2023 22-Feb-2023 8-Mar-2023 1 Titik
T.01 MONITORING PENGECORAN BOREPILE

Jumlah Titik 44 MT : 23.40 m

PersLeg ABCD 11 Pad : 22.00 m


KEDALAMAN (m) TES TEKAN BETON
TGL VOLUME JUMLAH MUTU
NO PEKERJAAN LOKASI KETERANGAN
PENGECORAN MT Pad M3 BENDA UJI BETON 7 HARI 14 HARI 28 HARI

36 8-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 2 6.00 3 K 225 - 16 15-Feb-2023 22-Feb-2023 8-Mar-2023 1 Titik
37 9-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 11 6.00 3 K 225 - 16 16-Feb-2023 23-Feb-2023 9-Mar-2023 1 Titik
38 9-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 5 6.00 3 K 225 - 16 16-Feb-2023 23-Feb-2023 9-Mar-2023 1 Titik
39 10-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 8 6.00 3 K 225 - 16 17-Feb-2023 24-Feb-2023 10-Mar-2023 1 Titik
40 10-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 3 6.00 3 K 225 - 16 17-Feb-2023 24-Feb-2023 10-Mar-2023 1 Titik
41 11-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg A 4 6.00 3 K 225 - 16 18-Feb-2023 25-Feb-2023 11-Mar-2023 1 Titik
42 11-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 5 6.00 3 K 225 - 16 18-Feb-2023 25-Feb-2023 11-Mar-2023 1 Titik
43 11-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 4 6.00 3 K 225 - 16 18-Feb-2023 25-Feb-2023 11-Mar-2023 1 Titik
44 13-Feb-2023 Borepile 23.40 22.00 Tower 1, Leg B 3 6.00 3 K 225 - 16 20-Feb-2023 27-Feb-2023 13-Mar-2023 1 Titik
TOTAL KEDALAMAN (M) 1029.60 968.00 TOTAL VOL. 265.00 M3 Jumlah Titik/Leg 24 Titik
Pesentase 54.55%