You are on page 1of 2

MONITORING PENGECORAN BOREPILE

T.11
Jumlah Titik 32 MT : 16.00 m

PersLeg ABCD 8 Pad : 14.00 m


KEDALAMAN (m) TES TEKAN BETON
TGL VOLUME JUMLAH MUTU
NO PEKERJAAN LOKASI KETERANGAN
PENGECORAN MT Pad M3 BENDA UJI BETON 7 HARI 14 HARI 28 HARI

1 26-Dec-2022 Borepile 16.00 14.00 Tower 11, Leg D 8 4.00 3 K 225 - 16 2-Jan-2023 9-Jan-2023 23-Jan-2023 1 Titik
2 26-Dec-2022 Borepile 16.00 14.00 Tower 11, Leg D 7 4.00 3 K 225 - 16 2-Jan-2023 9-Jan-2023 23-Jan-2023 1 Titik
3 27-Dec-2022 Borepile 16.00 14.00 Tower 11, Leg D 6 4.00 3 K 225 - 16 3-Jan-2023 10-Jan-2023 24-Jan-2023 1 Titik
4 28-Dec-2022 Borepile 16.00 14.00 Tower 11, Leg D 5 4.00 3 K 225 - 16 4-Jan-2023 11-Jan-2023 25-Jan-2023 1 Titik
5 29-Dec-2022 Borepile 16.00 14.00 Tower 11, Leg D 4 4.00 3 K 225 - 16 5-Jan-2023 12-Jan-2023 26-Jan-2023 1 Titik
6 30-Dec-2022 Borepile 16.00 14.00 Tower 11, Leg D 3 4.00 3 K 225 - 16 6-Jan-2023 13-Jan-2023 27-Jan-2023 1 Titik
7 31-Dec-2022 Borepile 16.00 14.00 Tower 11, Leg D 2 4.00 3 K 225 - 16 6-Jan-2023 13-Jan-2023 27-Jan-2023 1 Titik
8 3-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg D 1 4.00 3 K 225 - 16 6-Jan-2023 13-Jan-2023 27-Jan-2023 1 Titik
9 5-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg C 1 4.00 3 K 225 - 16 12-Jan-2023 19-Jan-2023 2-Feb-2023 1 Titik
10 5-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg A 5 4.00 3 K 225 - 16 12-Jan-2023 19-Jan-2023 2-Feb-2023 1 Titik
11 6-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg C 2 4.00 3 K 225 - 16 13-Jan-2023 20-Jan-2023 3-Feb-2023 1 Titik
12 7-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg C 3 4.00 3 K 225 - 16 14-Jan-2023 21-Jan-2023 4-Feb-2023 1 Titik
13 8-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg C 4 4.00 3 K 225 - 16 15-Jan-2023 22-Jan-2023 5-Feb-2023 1 Titik
14 9-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg A 7 4.00 3 K 225 - 16 16-Jan-2023 23-Jan-2023 6-Feb-2023 1 Titik
15 9-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg C 5 4.00 3 K 225 - 16 16-Jan-2023 23-Jan-2023 6-Feb-2023 1 Titik
16 11-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg C 6 4.00 3 K 225 - 16 18-Jan-2023 25-Jan-2023 8-Feb-2023 1 Titik
17 12-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg C 7 4.00 3 K 225 - 16 19-Jan-2023 26-Jan-2023 9-Feb-2023 1 Titik
18 12-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg A 1 4.00 3 K 225 - 16 19-Jan-2023 26-Jan-2023 9-Feb-2023 1 Titik
19 13-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg C 8 4.00 3 K 225 - 16 20-Jan-2023 27-Jan-2023 10-Feb-2023 1 Titik
20 14-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg A 2 4.00 3 K 225 - 16 21-Jan-2023 28-Jan-2023 11-Feb-2023 1 Titik
21 16-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg A 3 4.00 3 K 225 - 16 23-Jan-2023 30-Jan-2023 13-Feb-2023 1 Titik
22 17-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg B 1 4.00 3 K 225 - 16 24-Jan-2023 31-Jan-2023 14-Feb-2023 1 Titik
23 18-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg B 2 4.00 3 K 225 - 16 25-Jan-2023 1-Feb-2023 15-Feb-2023 1 Titik
24 19-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg B 3 4.00 3 K 225 - 16 26-Jan-2023 2-Feb-2023 16-Feb-2023 1 Titik
25 19-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg A 6 4.00 3 K 225 - 16 26-Jan-2023 2-Feb-2023 16-Feb-2023 1 Titik
26 21-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg A 4 4.00 3 K 225 - 16 28-Jan-2023 4-Feb-2023 18-Feb-2023 1 Titik
27 21-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg B 4 4.00 3 K 225 - 16 28-Jan-2023 4-Feb-2023 18-Feb-2023 1 Titik
28 22-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg A 8 4.00 3 K 225 - 16 29-Jan-2023 5-Feb-2023 19-Feb-2023 1 Titik
29 23-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg B 5 4.00 3 K 225 - 16 30-Jan-2023 6-Feb-2023 20-Feb-2023 1 Titik
30 24-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg B 6 4.00 3 K 225 - 16 31-Jan-2023 7-Feb-2023 21-Feb-2023 1 Titik
31 25-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg B 7 4.00 3 K 225 - 16 1-Feb-2023 8-Feb-2023 22-Feb-2023 1 Titik
32 26-Jan-2023 Borepile 16.00 14.00 Tower 11, Leg B 8 4.00 3 K 225 - 16 2-Feb-2023 9-Feb-2023 23-Feb-2023 1 Titik
MONITORING PENGECORAN BOREPILE
T.11
Jumlah Titik 32 MT : 16.00 m

PersLeg ABCD 8 Pad : 14.00 m


KEDALAMAN (m) TES TEKAN BETON
TGL VOLUME JUMLAH MUTU
NO PEKERJAAN LOKASI KETERANGAN
PENGECORAN MT Pad M3 BENDA UJI BETON 7 HARI 14 HARI 28 HARI

TOTAL KEDALAMAN (M) 512.00 448.00 TOTAL VOL. 20.00 M3 Jumlah Titik/Leg 5 Titik
Pesentase 15.63%