This document outlines the construction schedule for a transmission project (TP) with 11 steps from excavation to commissioning taking place between July 2023 and August 2023. The steps include excavation, foundation, wall castings, slab and beam installation, plastering, and commissioning. The durations range from 1 to 4 days with a total project time of 27 days.
This document outlines the construction schedule for a transmission project (TP) with 11 steps from excavation to commissioning taking place between July 2023 and August 2023. The steps include excavation, foundation, wall castings, slab and beam installation, plastering, and commissioning. The durations range from 1 to 4 days with a total project time of 27 days.
This document outlines the construction schedule for a transmission project (TP) with 11 steps from excavation to commissioning taking place between July 2023 and August 2023. The steps include excavation, foundation, wall castings, slab and beam installation, plastering, and commissioning. The durations range from 1 to 4 days with a total project time of 27 days.
FMS - HO Name of Name of Start Date End Date No of Days
Step 5 CONSTRUCTION OF TP EXCAVATION TP 01/07/2023 02/07/2023 1
Step 5 CONSTRUCTION OF TP PCC TP 02/07/2023 03/07/2023 1 Step 5 CONSTRUCTION OF TP FOUNDATION TP 03/07/2023 06/07/2023 3 Step 5 CONSTRUCTION OF TP WALL 1ST CASTING 06/07/2023 09/07/2023 3 Step 5 CONSTRUCTION OF TP WALL 2ND CASTING 09/07/2023 12/07/2023 3 Step 5 CONSTRUCTION OF TP RECEIVER SLAB AND TOP BEAM 12/07/2023 15/07/2023 3 Step 5 CONSTRUCTION OF TP RECEIVER WALL 12/07/2023 15/07/2023 3 Step 5 CONSTRUCTION OF TP STEPS 15/07/2023 19/07/2023 4 Step 5 CONSTRUCTION OF TP PLASTERING INTERNAL 19/07/2023 22/07/2023 3 Step 5 CONSTRUCTION OF TP PLASTERING EXTERNAL 22/07/2023 25/07/2023 3 Step 5 CONSTRUCTION OF TP TOP SLAB 26/07/2023 28/07/2023 2 Step 5 CONSTRUCTION OF TP Commissioning of TP 09/08/2023 13/08/2023 4