Duration 2019

Activity Name (Days)


Start Date Finish Date
March April May June

Building Management 102.00 4 3 19 29 6 19


1
System
2 BMS Works @ LGF 11.00 4 3 19 15 3 19

BMS Pipe Hangers and 5.00 4 3 19 8 3 19


3
Pipes @ LGF
4 BMS Wiring @ LGF 2.00 9 3 19 11 3 19

BMS Devices Installation 4.00 12 3 19 15 3 19


5
@ LGF
BMS Works @ LGF 0.00 15 3 19 15 3 19
6
Complete
7 BMS Works @ UGF 17.00 9 3 19 28 3 19

BMS Pipe Hangers and 9.00 9 3 19 19 3 19


8
Pipes @ UGF
9 BMS Wiring @ UGF 3.00 20 3 19 22 3 19

BMS Devices Installation 5.00 23 3 19 28 3 19


10
@ UGF
BMS Works @ UGF 0.00 28 3 19 28 3 19
11
Complete
12 BMS Works @ 2F 17.00 20 3 19 8 4 19

BMS Pipe Hangers and 9.00 20 3 19 29 3 19


13
Pipes @ 2F
14 BMS Wiring @ 2F 3.00 30 3 19 2 4 19

BMS Devices Installation 5.00 3 4 19 8 4 19


15
@ 2F
BMS Works @ 2F 0.00 8 4 19 8 4 19
16
Complete
17 BMS Works @ 3F 7.00 30 3 19 6 4 19

BMS Pipe Hangers and 4.00 30 3 19 3 4 19


18
Pipes @ 3F
19 BMS Wiring @ 3F 1.00 4 4 19 4 4 19

BMS Devices Installation 2.00 5 4 19 6 4 19


20
@ 3F
BMS Works @ 3F 0.00 6 4 19 6 4 19
21
Complete
22 BMS Works @ 4F 7.00 4 4 19 11 4 19

BMS Pipe Hangers and 4.00 4 4 19 8 4 19


23
Pipes @ 4F
24 BMS Wiring @ 4F 1.00 9 4 19 9 4 19

BMS Devices Installation 2.00 10 4 19 11 4 19


25
@ 4F
BMS Works @ 4F 0.00 11 4 19 11 4 19
26
Complete
27 BMS Works @ 5F 7.00 9 4 19 16 4 19

BMS Pipe Hangers and 4.00 9 4 19 12 4 19


28
Pipes @ 5F
March April May June
Duration 2019
Activity Name (Days)
Start Date Finish Date
March April May June

29 BMS Wiring @ 5F 1.00 13 4 19 13 4 19

BMS Devices Installation 2.00 15 4 19 16 4 19


30
@ 5F
BMS Works @ 5F 0.00 16 4 19 16 4 19
31
Complete
32 BMS Works @ 6F 7.00 13 4 19 20 4 19

BMS Pipe Hangers and 4.00 13 4 19 17 4 19


33
Pipes @ 6F
34 BMS Wiring @ 6F 1.00 18 4 19 18 4 19

BMS Devices Installation 2.00 19 4 19 20 4 19


35
@ 6F
BMS Works @ 6F 0.00 20 4 19 20 4 19
36
Complete
37 BMS Works @ 7F 7.00 18 4 19 25 4 19

BMS Pipe Hangers and 4.00 18 4 19 22 4 19


38
Pipes @ 7F
39 BMS Wiring @ 7F 1.00 23 4 19 23 4 19

BMS Devices Installation 2.00 24 4 19 25 4 19


40
@ 7F
BMS Works @ 7F 0.00 25 4 19 25 4 19
41
Complete
42 BMS Works @ 8F 7.00 23 4 19 30 4 19

BMS Pipe Hangers and 4.00 23 4 19 26 4 19


43
Pipes @ 8F
44 BMS Wiring @ 8F 1.00 27 4 19 27 4 19

BMS Devices Installation 2.00 29 4 19 30 4 19


45
@ 8F
BMS Works @ 8F 0.00 30 4 19 30 4 19
46
Complete
47 BMS Works @ 9F 7.00 27 4 19 4 5 19

BMS Pipe Hangers and 4.00 27 4 19 1 5 19


48
Pipes @ 9F
49 BMS Wiring @ 9F 1.00 2 5 19 2 5 19

BMS Devices Installation 2.00 3 5 19 4 5 19


50
@ 9F
BMS Works @ 9F 0.00 4 5 19 4 5 19
51
Complete
52 BMS Works @ 10F 7.00 2 5 19 9 5 19

BMS Pipe Hangers and 4.00 2 5 19 6 5 19


53
Pipes @ 10F
54 BMS Wiring @ 10F 1.00 7 5 19 7 5 19

BMS Devices Installation 2.00 8 5 19 9 5 19


55
@ 10F
BMS Works @ 10F 0.00 9 5 19 9 5 19
56
Complete
March April May June
Duration 2019
Activity Name (Days)
Start Date Finish Date
March April May June

57 BMS Works @ 11F 7.00 7 5 19 14 5 19

BMS Pipe Hangers and 4.00 7 5 19 10 5 19


58
Pipes @ 11F
59 BMS Wiring @ 11F 1.00 11 5 19 11 5 19

BMS Devices Installation 2.00 13 5 19 14 5 19


60
@ 11F
BMS Works @ 11F 0.00 14 5 19 14 5 19
61
Complete
62 BMS Works @ 12F 7.00 11 5 19 18 5 19

BMS Pipe Hangers and 4.00 11 5 19 15 5 19


63
Pipes @ 12F
64 BMS Wiring @ 12F 1.00 16 5 19 16 5 19

BMS Devices Installation 2.00 17 5 19 18 5 19


65
@ 12F
BMS Works @ 12F 0.00 18 5 19 18 5 19
66
Complete
67 BMS Works @ 13F 7.00 16 5 19 23 5 19

BMS Pipe Hangers and 4.00 16 5 19 20 5 19


68
Pipes @ 13F
69 BMS Wiring @ 13F 1.00 21 5 19 21 5 19

BMS Devices Installation 2.00 22 5 19 23 5 19


70
@ 13F
BMS Works @ 13F 0.00 23 5 19 23 5 19
71
Complete
72 BMS Works @ 14F 7.00 21 5 19 28 5 19

BMS Pipe Hangers and 4.00 21 5 19 24 5 19


73
Pipes @ 14F
74 BMS Wiring @ 14F 1.00 25 5 19 25 5 19

BMS Devices Installation 2.00 27 5 19 28 5 19


75
@ 14F
BMS Works @ 14F 0.00 28 5 19 28 5 19
76
Complete
77 BMS Works @ 15F 7.00 25 5 19 1 6 19

BMS Pipe Hangers and 4.00 25 5 19 29 5 19


78
Pipes @ 15F
79 BMS Wiring @ 15F 1.00 30 5 19 30 5 19

BMS Devices Installation 2.00 31 5 19 1 6 19


80
@ 15F
BMS Works @ 15F 0.00 1 6 19 1 6 19
81
Complete
82 BMS Works @ RD 18.00 30 5 19 19 6 19

BMS Pipe Hangers and 10.00 30 5 19 10 6 19


83
Pipes @ RD
84 BMS Wiring @ RD 3.00 11 6 19 13 6 19

March April May June


Duration 2019
Activity Name (Days)
Start Date Finish Date
March April May June
BMS Devices Installation 5.00 14 6 19 19 6 19
85
@ RD
BMS Works @ RD 0.00 19 6 19 19 6 19
86
Complete
BMS Programming and 56.00 26 4 19 29 6 19
87
Testing
BMS Programming for 4.00 26 4 19 30 4 19
88
LGF-7F
BMS Programming for 4.00 20 6 19 24 6 19
89
8F-RD
90 Testing and 5.00 25 6 19 29 6 19
Comissioning
BMS Programming and 0.00 29 6 19 29 6 19
91
Testing Complete
Building Management 0.00 29 6 19 29 6 19
92
System Complete