Professional Documents
Culture Documents
8.1 Supply of Coarse Bar Screens with lifting arrangements 15.04.2023 15.04.2023
8.2 Supply of Fine Screen 15.04.2023 15.04.2023
8.3 Supply of all Pumps 30.04.2023 30.04.2023
8.4 Supply of Screw Press 30.04.2023 30.04.2023
8.5 Supply of Electrical Panel & SCADA 30.04.2023 30.04.2023
8.6 Supply of Decanters with Hydraulic lifting arrangements 30.04.2023 30.04.2023
Supply of Air Blowers with acoustic chambers and diffusion
8.7 30.04.2023 30.04.2023
systems.
8.8 Supply of Motorised Valves, check valves, NRV, etc. 15.04.2023 15.04.2023
8.9 Supply of Cable, Cable Tray's, piping, fittings, etc. 15.04.2023 15.04.2023
8.10 Supply of Thimble Gate Valves with EO System 15.04.2023 15.04.2023
8.11 Supply of Flow meters 15.04.2023 15.04.2023
8.12 Supply of UV's 15.04.2023 15.04.2023
9 Installation:
9.1 Piping with Valves for transferring sludge to Sludge Sump 16.04.2023 19.04.2023 16.04.2023 19.04.2023
9.2 Installation of RAS Piping with complete piping work 01.05.2023 05.05.2023 01.05.2023 05.05.2023
Installation of Main Lifting Pumps with NRV's, expansion
9.3 bellows, Motorised Vales, Ultrasonic Flow Meter and piping 01.05.2023 05.05.2023 01.05.2023 05.05.2023
works.
9.4 Installation of Agitator in Flash Mixer 20.04.2023 30.04.2023 20.04.2023 30.04.2023
9.5 Installation of Diffusers in SBR Tanks 20.04.2023 30.04.2023 20.04.2023 30.04.2023
9.6 Installation of Tube Media in settling Tank 20.04.2023 30.04.2023 20.04.2023 30.04.2023
Installation of Air Blower and piping work with supports and
9.7 01.05.2023 05.05.2023 01.05.2023 05.05.2023
required fittings and acoustic chamber.
9.8 Installation of Thimble Gate Valves 01.05.2023 05.05.2023 01.05.2023 05.05.2023
9.9 Installation of Coarse Screens with lifting arrangements. 20.04.2023 30.04.2023 20.04.2023 30.04.2023
9.11 Installation of Auto Fine Screens with interconnecting piping 20.04.2023 30.04.2023 20.04.2023 30.04.2023
Installation of Screw Press with piping fittings and poly
9.12 01.05.2023 05.05.2023 01.05.2023 05.05.2023
dosing system.
9.13 Installation of UV's 20.04.2023 30.04.2023 20.04.2023 30.04.2023
9.14 Installation of Decanting System. 20.04.2023 30.04.2023 20.04.2023 30.04.2023
9.15 Installation and laying of Cable Tray's 05.05.2023 07.05.2023 05.05.2023 07.05.2023
9.16 Laying of Cables 07.05.2023 09.05.2023 07.05.2023 09.05.2023
9.17 Installation of Panel and Scada 10.05.2023 11.05.2023 10.05.2023 11.05.2023
9.18 Dressing and Termination of Cables 12.05.2023 13.05.2023 12.05.2023 13.05.2023
Installation:
1 Piping with Valves for transferring sludge to Sludge Sump 01.05.2023 02.05.2023
2 Installation of RAS Piping with complete piping work 01.05.2023 05.05.2023
Installation of Main Lifting Pumps with NRV's, expansion bellows, Motorised Vales,
3 01.05.2023 05.05.2023
Ultrasonic Flow Meter and piping works.
4 Installation of Agitator in Flash Mixer 01.05.2023 10.05.2023
5 Installation of Diffusers in SBR Tanks 01.05.2023 10.05.2023
6 Installation of Tube Media in settling Tank 01.05.2023 10.05.2023
Installation of Air Blower and piping work with supports and required fittings and acoustic
7 06.05.2023 10.05.2023
chamber.
8 Installation of Thimble Gate Valves 16.05.2023 20.05.2023
9 Installation of Coarse Screens with lifting arrangements. 01.05.2023 10.05.2023
10 Installation of Auto Fine Screens with interconnecting piping 01.05.2023 10.05.2023
11 Installation of Screw Pumps and Screw Press with piping fittings and poly dosing system. 05.05.2023 10.05.2023
12 Installation of UV's 01.05.2023 10.05.2023
13 Installation of Decanting System. 01.05.2023 10.05.2023
14 Installation and laying of Cable Tray's 11.05.2023 25.05.2023
15 Laying of Cables 11.05.2023 25.05.2023
16 Installation of Panel and Scada 25.05.2023 27.05.2023
17 Dressing and Termination of Cables 28.05.2023 29.05.2023
10 Installation:
10.1 Piping with Valves for transferring sludge to Sludge Sump 10.05.2023 20.05.2023
10.2 Installation of RAS Piping with complete piping work 10.05.2023 20.05.2023
Installation of Main Lifting Pumps with NRV's, expansion
10.3 bellows, Motorised Vales, Ultrasonic Flow Meter and piping 10.05.2023 20.05.2023
works.
10.4 Installation of Agitator in Flash Mixer 10.05.2023 20.05.2023
10.5 Installation of Diffusers in SBR Tanks 10.05.2023 20.05.2023
SN ACTIVITY Satellite, Kota
10.6 Installation of Tube Media in settling Tank 10.05.2023 20.05.2023
Installation of Air Blower and piping work with supports and
10.7 10.05.2023 20.05.2023
required fittings and acoustic chamber.
10.8 Installation of Auto Fine Screens with interconnecting piping 10.05.2023 20.05.2023
Installation of Screw Press with piping fittings and poly
10.9 10.05.2023 20.05.2023
dosing system.
10.10 Installation of UV's 10.05.2023 20.05.2023
10.11 Installation of Decanting System. 10.05.2023 20.05.2023
10.12 Installation and laying of Cable Tray's 20.05.2023 22.05.2023
10.13 Laying of Cables 23.05.2023 25.05.2023
10.14 Installation of Panel and Scada 25.05.2023 26.05.2023
10.15 Dressing and Termination of Cables 28.05.2023 30.05.2023
S.No. Description Start Date End Date Start Date End Date
6 Completion of Civil Foundation Works to start fabrication works at site. 30.03.2023 10.04.2023
1 Outer Frame Work of Container Base Frame 03.04.2023 03.04.2023 16.04.2023 16.04.2023
6 Coal tar Epoxy Paint at bottom of Base Frame. 10.04.2023 10.04.2023 18.04.2023 19.04.2023
7 Fitup MS Corners and top pipe of 1st Stage Height vertically. 11.04.2023 11.04.2023 20.04.2023 20.04.2023
9 Inside partition sheet fitup of all tanks 17.04.2023 20.04.2023 23.04.2023 25.04.2023
10 Welding of MS Corners of 2nd Stage Height vertically. 21.04.2023 21.04.2023 26.04.2023 26.04.2023
12 Side & partition Sheets Fit-up (2nd Stage Height) 23.04.2023 26.04.2023 27.04.2023 29.04.2023
15 Cutting of sheets and welding puddle flanges. 05.05.2023 06.05.2023 04.05.2023 05.05.2023
WILL BE DISPATCHED
FROM FACTORY BY
30/04/2023
ACTIVITY Janana, Jaipur NMCH, Kota
S.No. Description Start Date End Date Start Date End Date
1 Outer Frame Work of Container Base Frame 1 and 2 05.05.2023 06.05.2023 05.05.2023 06.05.2023
2 making base ring and tank base fabrication 1 and 2 06.05.2023 10.05.2023 06.05.2023 10.05.2023
3 complete welding of both tanks base 1 and 2 10.05.2023 12.05.2023 10.05.2023 12.05.2023
4 first layer of circular tank fabrication tank 1 13.05.2023 13.05.2023 13.05.2023 13.05.2023
5 ring fabrication on first layer tank 1 14.05.2023 14.05.2023 14.05.2023 14.05.2023
6 second layer of circular tank fabrication tank 1 15.05.2023 15.05.2023 15.05.2023 15.05.2023
7 ring fabrication on second layer tank 1 16.05.2023 16.05.2023 16.05.2023 16.05.2023
8 third layer of circular tank fabrication tank 1 16.05.2023 16.05.2023 16.05.2023 16.05.2023
9 ring fabrication on third layer tank 1 17.05.2023 17.05.2023 17.05.2023 17.05.2023
10 full welding on first layer tank 1 18.05.2023 18.05.2023 18.05.2023 18.05.2023
11 full welding on second layer tank 1 19.05.2023 19.05.2023 19.05.2023 19.05.2023
12 full welding on third layer tank 1 20.05.2023 20.05.2023 20.05.2023 20.05.2023
13 first layer of circular tank fabrication tank 2 13.05.2023 13.05.2023 13.05.2023 13.05.2023
14 ring fabrication on first layer tank 2 14.05.2023 14.05.2023 14.05.2023 14.05.2023
15 second layer of circular tank fabrication tank 2 15.05.2023 15.05.2023 15.05.2023 15.05.2023
16 ring fabrication on second layer tank 2 16.05.2023 16.05.2023 16.05.2023 16.05.2023
17 third layer of circular tank fabrication tank 2 16.05.2023 16.05.2023 16.05.2023 16.05.2023
18 ring fabrication on third layer tank 2 17.05.2023 17.05.2023 17.05.2023 17.05.2023
19 full welding on first layer tank 2 18.05.2023 18.05.2023 18.05.2023 18.05.2023
20 full welding on second layer tank 2 19.05.2023 19.05.2023 19.05.2023 19.05.2023
21 full welding on third layer tank 2 20.05.2023 20.05.2023 20.05.2023 20.05.2023
Installation:
1 Piping with Valves for transferring sludge to Sludge Sump 06.06.2023 15.06.2023 06.06.2023 15.06.2023
2 Installation of RAS Piping with complete piping work 06.06.2023 15.06.2023 06.06.2023 15.06.2023
ACTIVITY Janana, Jaipur NMCH, Kota
S.No. Description Start Date End Date Start Date End Date
3 Submission Civil structural drawings & design for foundation and plant building. Completed
Civil Markings on site & Completion of Civil Work on Site post the drawings finalization Completed
5
7.11 Supply of MS Flanges and round pipes for puddles fabrication - Internal Factory 30.05.2023
2 Making base ring and tank base fabrication 1 and 2 03.05.2023 05.05.2023
2 Making base ring and tank base fabrication 1 and 2 03.05.2023 05.05.2023
2 Making base ring and tank base fabrication 1 and 2 18.05.2023 20.05.2023
2 Fit-up and welding of structural members inside Outer Base Frame of container. 05.06.2023 06.06.2023
Installation:
1 Piping with Valves for transferring sludge to Sludge Sump 21.06.2023 25.06.2023
2 Installation of RAS Piping with complete piping work 21.06.2023 25.06.2023
Installation of Main Lifting Pumps with NRV's, expansion bellows, Motorised Vales,
3 25.06.2023 30.06.2023
Ultrasonic Flow Meter and piping works.
4 Installation of Agitator in Flash Mixer 21.06.2023 25.06.2023
5 Installation of Diffusers in SBR Tanks 21.06.2023 25.06.2023
6 Installation of Tube Media in settling Tank 21.06.2023 25.06.2023
Installation of Air Blower and piping work with supports and required fittings and acoustic
7 01.07.2023 07.07.2023
chamber.
8 Installation of Thimble Gate Valves 01.07.2023 07.07.2023
9 Installation of Coarse Screens with lifting arrangements. 25.06.2023 30.06.2023
10 Installation of Auto Fine Screens with interconnecting piping 25.06.2023 30.06.2023
11 Installation of Screw Pumps and Screw Press with piping fittings and poly dosing system. 01.07.2023 07.07.2023