Client Name : Rajasthan Urban Infrastructure Development Project (RUIDP)

Contractor Name : M/s Genius-LNA JV (162 B, Mansarovar, Pal Road, Jodhpur-342004


WORK PLAN
SN ACTIVITY RUHS, Jaipur Mahila Chikitsalaya, Jaipur
Description Start Date End Date Start Date End Date
1 Submission of Drawing & Design Completed Completed
2 Approval of Drawings & Design Completed Completed
Submission Civil structural drawings & design for foundation
3 Completed Completed
and plant building.
4 Approval of Civil structural Drawings & Design Completed Completed
Civil Markings on site & Completion of Civil Work on Site
5 Completed Completed
post the drawings finalization
6 Supply of 1st Lot of material - Internal Factory: Completed Completed
Supply of MS C-Channels for Base Frame and internal
6.1 Completed Completed
Structure
6.2 Supply of MS Sheet for Base Frame Completed Completed
Supply of MS Sheet sent for bending to factory for making
6.3 Completed Completed
MS Corners
6.4 Supply of MS Corners Completed Completed
6.5 Supply of MS Sheet sent for corrugation Completed Completed
6.6 Supply of MS Corrugated Sheets (Side & Partition Sheets) Completed Completed
Supply of MS Chequered Sheets, MS Pipes for Railings, MS
6.7 Completed Completed
C-Channels, MS Angles for steps
Supply of MS Flanges and round pipes for puddles
6.8 Completed Completed
fabrication - Internal Factory
6.9 Supply of MS Plate for Ribs - Internal Factory Completed Completed

7 MS Tank Fabrication work


7.1 Outer Frame Work of Container Base Frame Completed Completed
Fit-up and welding of structural members inside Outer Base
7.2 Completed Completed
Frame of container.
Fit-up and welding of MS Sheets above MS C-channels
7.3 Completed Completed
frame.
7.4 Fit-up and welding of base plate on base frame. Completed Completed
7.5 Shifting of Base Frame to Structure Completed Completed
7.6 Jointing Base Frame Completed Completed
7.7 Welding from bottom of Base frame. Completed Completed
7.8 Coal tar Epoxy Paint at bottom of Base Frame. Completed Completed
7.9 Fitup MS Corners of 1st Stage Height vertically. Completed Completed
7.1 Outside sites fabrication of all tanks Completed Completed
7.10 Inside partition sheet fitup of all tanks Completed Completed
7.11 Tube settler tank fabrication fitup Completed 06.04.2023 10.04.2023
7.12 Welding of MS Corners of 2nd Stage Height vertically. completed Completed
7.13 Welding of top MS Pipe above MS Corners. Completed Completed
7.14 Side & partition Sheets Fit-up (2nd Stage Height) completed Completed
Fitup and Welding of Ribs at joints and structure work with
7.15 Completed 10.04.2023 12.04.2023
MS C-Channels at all levels.
7.16 Complete welding of Container from Inside and outside. Completed 12.04.2023 18.04.2023
7.17 Cutting of sheets and welding puddle flanges. Completed 18.04.2023 20.04.2023
7.18 Welding Structure and walkway above container. Completed 20.04.2023 22.04.2023
7.19 Fabrication of Staircase and railing. Completed 20.04.2023 22.04.2023
7.20 Water Testing of all tanks start Completed 22.04.2023 24.04.2023
7.21 Leakage rectification if any Completed 24.04.2023 25.04.2023
7.21 FRP Lining inside Containers 07.04.2023 15.04.2023 25.04.2023 30.04.2023
7.22 Redoxide and epoxy paint outside container. 12.04.2023 15.04.2023 25.04.2023 30.04.2023

8 Supply of 2nd Lot of Material:

8.1 Supply of Coarse Bar Screens with lifting arrangements 15.04.2023 15.04.2023
8.2 Supply of Fine Screen 15.04.2023 15.04.2023
8.3 Supply of all Pumps 30.04.2023 30.04.2023
8.4 Supply of Screw Press 30.04.2023 30.04.2023
8.5 Supply of Electrical Panel & SCADA 30.04.2023 30.04.2023
8.6 Supply of Decanters with Hydraulic lifting arrangements 30.04.2023 30.04.2023
Supply of Air Blowers with acoustic chambers and diffusion
8.7 30.04.2023 30.04.2023
systems.
8.8 Supply of Motorised Valves, check valves, NRV, etc. 15.04.2023 15.04.2023
8.9 Supply of Cable, Cable Tray's, piping, fittings, etc. 15.04.2023 15.04.2023
8.10 Supply of Thimble Gate Valves with EO System 15.04.2023 15.04.2023
8.11 Supply of Flow meters 15.04.2023 15.04.2023
8.12 Supply of UV's 15.04.2023 15.04.2023

9 Installation:
9.1 Piping with Valves for transferring sludge to Sludge Sump 16.04.2023 19.04.2023 16.04.2023 19.04.2023
9.2 Installation of RAS Piping with complete piping work 01.05.2023 05.05.2023 01.05.2023 05.05.2023
Installation of Main Lifting Pumps with NRV's, expansion
9.3 bellows, Motorised Vales, Ultrasonic Flow Meter and piping 01.05.2023 05.05.2023 01.05.2023 05.05.2023
works.
9.4 Installation of Agitator in Flash Mixer 20.04.2023 30.04.2023 20.04.2023 30.04.2023
9.5 Installation of Diffusers in SBR Tanks 20.04.2023 30.04.2023 20.04.2023 30.04.2023
9.6 Installation of Tube Media in settling Tank 20.04.2023 30.04.2023 20.04.2023 30.04.2023
Installation of Air Blower and piping work with supports and
9.7 01.05.2023 05.05.2023 01.05.2023 05.05.2023
required fittings and acoustic chamber.
9.8 Installation of Thimble Gate Valves 01.05.2023 05.05.2023 01.05.2023 05.05.2023
9.9 Installation of Coarse Screens with lifting arrangements. 20.04.2023 30.04.2023 20.04.2023 30.04.2023
9.11 Installation of Auto Fine Screens with interconnecting piping 20.04.2023 30.04.2023 20.04.2023 30.04.2023
Installation of Screw Press with piping fittings and poly
9.12 01.05.2023 05.05.2023 01.05.2023 05.05.2023
dosing system.
9.13 Installation of UV's 20.04.2023 30.04.2023 20.04.2023 30.04.2023
9.14 Installation of Decanting System. 20.04.2023 30.04.2023 20.04.2023 30.04.2023
9.15 Installation and laying of Cable Tray's 05.05.2023 07.05.2023 05.05.2023 07.05.2023
9.16 Laying of Cables 07.05.2023 09.05.2023 07.05.2023 09.05.2023
9.17 Installation of Panel and Scada 10.05.2023 11.05.2023 10.05.2023 11.05.2023
9.18 Dressing and Termination of Cables 12.05.2023 13.05.2023 12.05.2023 13.05.2023

10 Testing & Commissioning 12.05.2023 13.05.2023 12.05.2023 13.05.2023


ACTIVITY MGH, Jodhpur
Description Start Date End Date
1 Submission of Drawing & Design Completed
2 Approval of Drawings & Design Completed
3 Submission Civil structural drawings & design for foundation and plant building. Completed
4 Approval of Civil structural Drawings & Design Completed
5 Civil Markings on site & Completion of Civil Work on Site post the drawings finalization Completed
6 Supply of 1st Lot of material - Internal Factory:
7 Supply of MS C-Channels for Base Frame and internal Structure Completed
8 Supply of MS Sheet for Base Frame Completed
9 Supply of MS Sheet sent for corrugation Completed
10 Supply of MS Corners Completed
11 Supply material to vendor for rolling tank 1 and 2 Completed
12 Base rolling material for layer 1 dispatch Completed
13 Supply of round tank second layer rolling sheet and channel Completed
14 Supply of round tank third layer rolling sheet and channel Completed
15 Supply of MS Corrugated Sheets (Side & Partition Sheets) Completed
Supply of MS Chequered Sheets, MS Pipes for Railings, MS C-Channels, MS Angles for
15.04.2023
16 steps
17 Supply of MS Flanges and round pipes for puddles fabrication - Internal Factory 15.04.2023
18 Supply of MS Plate for Ribs - Internal Factory 15.04.2023

MS Tank Fabrication work rectangular tank 1

1 Outer Frame Work of Container Base Frame Completed


2 Fit-up and welding of structural members inside Outer Base Frame of container. Completed
3 Fit-up and welding of MS Sheets above MS C-channels frame. Completed
5 Welding from bottom of Base frame. Completed
6 Coal tar Epoxy Paint at bottom of Base Frame. Completed
7 Fitup MS C orners of 1st Stage Height vertically. Completed
8 Outside sites fabrication of all tanks Completed
9 Inside partition sheet fitup of all tanks 29.03.2023 05.04.2023
10 Tube shettler tank fabrication fitup 05.04.2023 08.04.2023
11 Welding of MS Corners of 2nd Stage Height vertically. Completed
12 Welding of top MS Pipe above MS Corners. Completed
13 Side & partition Sheets Fit-up (2nd Stage Height) 29.04.2023 05.04.2023
14 fitup and Welding of Ribs at joints and structure work with MS C-Channels at all levels. 08.04.2023 10.04.2023
15 Complete welding of Container from Inside and outside. 08.04.2023 10.04.2023
16 Cutting of sheets and welding puddle flanges. 08.04.2023 10.04.2023

MS Tank Fabrication work rectangular tank 2

1 Outer Frame Work of Container Base Frame 15.04.2023 16.04.2023


2 Fit-up and welding of structural members inside Outer Base Frame of container. 15.04.2023 16.04.2023
3 Fit-up and welding of MS Sheets above MS C-channels frame. 17.04.2023 17.04.2023
4 Welding from bottom of Base frame. 18.04.2023 18.04.2023
5 Coal tar Epoxy Paint at bottom of Base Frame. 19.04.2023 19.04.2023
6 Fitup MS Corners and pipe 20.04.2023 21.04.2023
7 Fabrication of ms sheets 21.04.2023 25.04.2023
8 complete welding of ms sheets 25.04.2023 30.04.2023

Circular Tank Fabrication work 1 and 2

1 Outer Frame Work of Container Base Frame 1 and 2 Completed


2 making base ring and tank base fabrication 1 and 2 Completed
3 complete welding of both tanks base 1 and 2 Completed
4 first layer of circular tank fabrication tank 1 Completed
5 ring fabrication on first layer tank 1 Completed
6 second layer of circular tank fabrication tank 1 11.04.2023 12.04.2023
7 ring fabrication on second layer tank 1 12.04.2023 13.04.2023
8 third layer of circular tank fabrication tank 1 13.04.2023 14.04.2023
9 ring fabrication on third layer tank 1 14.04.2023 15.04.2023
10 full welding on first layer tank 1 16.04.2023 20.04.2023
11 full welding on second layer tank 1 16.04.2023 20.04.2023
12 full welding on third layer tank 1 16.04.2023 20.04.2023

13 first layer of circular tank fabrication tank 2 Completed


14 ring fabrication on first layer tank 2 Completed
15 second layer of circular tank fabrication tank 2 Completed
16 ring fabrication on second layer tank 2 12.04.2023 13.04.2023
ACTIVITY MGH, Jodhpur
Description Start Date End Date
17 third layer of circular tank fabrication tank 2 13.04.2023 14.04.2023
18 ring fabrication on third layer tank 2 14.04.2023 15.04.2023
19 full welding on first layer tank 2 16.04.2023 20.04.2023
20 full welding on second layer tank 2 16.04.2023 20.04.2023
21 full welding on third layer tank 2 16.04.2023 20.04.2023

22 Water testing of all tanks 20.04.2023 22.04.2023


23 leakage rectification of all tanks 23.04.2023 25.04.2023
24 FRP lining inside Containers 26.04.2023 02.05.2023
25 Epoxy Paint of all conatiners 02.05.2023 05.05.2023

Supply of 2nd Lot of Material:

1 Supply of Coarse Bar Screens with lifting arrangements 30.04.2023


2 Supply of Fine Screen 30.04.2023
3 Supply of all Pumps 30.04.2023
4 Supply of Screw Press 30.04.2023
5 Supply of Electrical Panel & SCADA 15.05.2023
6 Supply of Decanters with Hydraulic lifting arrangements 30.04.2023
7 Supply of Air Blowers with acoustic chambers and diffusion systems. 30.04.2023
8 Supply of Motorised Valves, check valves, NRV, etc. 30.04.2023
9 Supply of Cable, Cable Tray's, piping, fittings, etc. 30.04.2023
10 Supply of Thimble Gate Valves with EO System 15.05.2023
11 Supply of Flow meters 30.04.2023
12 Supply of UV's 30.04.2023

Installation:
1 Piping with Valves for transferring sludge to Sludge Sump 01.05.2023 02.05.2023
2 Installation of RAS Piping with complete piping work 01.05.2023 05.05.2023
Installation of Main Lifting Pumps with NRV's, expansion bellows, Motorised Vales,
3 01.05.2023 05.05.2023
Ultrasonic Flow Meter and piping works.
4 Installation of Agitator in Flash Mixer 01.05.2023 10.05.2023
5 Installation of Diffusers in SBR Tanks 01.05.2023 10.05.2023
6 Installation of Tube Media in settling Tank 01.05.2023 10.05.2023
Installation of Air Blower and piping work with supports and required fittings and acoustic
7 06.05.2023 10.05.2023
chamber.
8 Installation of Thimble Gate Valves 16.05.2023 20.05.2023
9 Installation of Coarse Screens with lifting arrangements. 01.05.2023 10.05.2023
10 Installation of Auto Fine Screens with interconnecting piping 01.05.2023 10.05.2023
11 Installation of Screw Pumps and Screw Press with piping fittings and poly dosing system. 05.05.2023 10.05.2023
12 Installation of UV's 01.05.2023 10.05.2023
13 Installation of Decanting System. 01.05.2023 10.05.2023
14 Installation and laying of Cable Tray's 11.05.2023 25.05.2023
15 Laying of Cables 11.05.2023 25.05.2023
16 Installation of Panel and Scada 25.05.2023 27.05.2023
17 Dressing and Termination of Cables 28.05.2023 29.05.2023

Testing & Commissioning 29.05.2023 30.05.2023


Client Name : Rajasthan Urban Infrastructure Development Project (RUIDP)
Contractor Name : M/s Genius-LNA JV (162 B, Mansarovar, Pal Road, Jodhpur-342004
WORK PLAN
SN ACTIVITY Satellite, Kota
Description Start Date End Date
1 Submission of Drawing & Design Completed
2 Approval of Drawings & Design Completed
Submission Civil structural drawings & design for foundation
3 Completed
and plant building.
4 Approval of Civil structural Drawings & Design Completed
Civil Markings on site & Completion of Civil Work on Site
5 Completed
post the drawings finalization
Completion of Civil Foundation Works to start fabrication
6 10.04.2023
works at site.
7 Supply of 1st Lot of material - Internal Factory:
Supply of MS C-Channels for Base Frame and internal
7.1 12.04.2023
Structure
7.2 Supply of MS Sheet for Base Frame 12.04.2023
Supply of MS Sheet sent for bending to factory for making
7.3 12.04.2023
MS Corners
7.4 Supply of MS Corners 12.04.2023
7.5 Supply of MS Sheet sent for corrugation 12.04.2023
7.6 Supply of MS Corrugated Sheets (Side & Partition Sheets) 12.04.2023
Supply of MS Chequered Sheets, MS Pipes for Railings, MS
7.7 12.04.2023
C-Channels, MS Angles for steps
Supply of MS Flanges and round pipes for puddles
7.8 12.04.2023
fabrication - Internal Factory
7.9 Supply of MS Plate for Ribs - Internal Factory 12.04.2023

8 MS Tank Fabrication work


8.1 Outer Frame Work of Container Base Frame 15.04.2023 15.04.2023
Fit-up and welding of structural members inside Outer Base
8.2 15.04.2023 16.04.2023
Frame of container.
Fit-up and welding of MS Sheets above MS C-channels
8.3 16.04.2023 17.04.2023
frame.
8.4 Welding from bottom of Base frame. 18.04.2023 18.04.2023
8.5 Coal tar Epoxy Paint at bottom of Base Frame. 18.04.2023 18.04.2023
8.6 Fitup MS Corners & Top Pipe 19.04.2023 19.04.2023
8.7 Outside sites fabrication of all tanks 19.04.2023 21.04.2023
SN ACTIVITY Satellite, Kota
8.8 Inside partition sheet fitup of all tanks 21.04.2023 23.04.2023
Fitup and Welding of Ribs at joints and structure work with
8.9 24.04.2023 24.04.2023
MS C-Channels at all levels.
8.10 Complete welding of Container from Inside and outside. 25.04.2023 29.04.2023
8.11 Cutting of sheets and welding puddle flanges. 29.04.2023 30.04.2023
8.12 Welding Structure and walkway above container. 01.05.2023 02.05.2023
8.13 Fabrication of Staircase and railing. 01.05.2023 02.05.2023
8.14 Water Testing of all tanks start 03.05.2023 03.05.2023
8.15 Leakage rectification if any 04.05.2023 04.05.2023
8.16 FRP Lining inside Containers 05.05.2023 08.05.2023
8.17 Redoxide and epoxy paint outside container. 08.05.2023 10.05.2023

9 Supply of 2nd Lot of Material:

9 Supply of Fine Screen 08.05.2023


9.1 Supply of all Pumps 08.05.2023
9.2 Supply of Screw Press 08.05.2023
9.3 Supply of Electrical Panel & SCADA 08.05.2023
9.4 Supply of Decanters with Hydraulic lifting arrangements 08.05.2023
Supply of Air Blowers with acoustic chambers and diffusion
9.5 08.05.2023
systems.
9.6 Supply of Motorised Valves, check valves, NRV, etc. 08.05.2023
9.7 Supply of Cable, Cable Tray's, piping, fittings, etc. 08.05.2023
9.8 Supply of Flow meters 08.05.2023
9.9 Supply of UV's 08.05.2023

10 Installation:
10.1 Piping with Valves for transferring sludge to Sludge Sump 10.05.2023 20.05.2023
10.2 Installation of RAS Piping with complete piping work 10.05.2023 20.05.2023
Installation of Main Lifting Pumps with NRV's, expansion
10.3 bellows, Motorised Vales, Ultrasonic Flow Meter and piping 10.05.2023 20.05.2023
works.
10.4 Installation of Agitator in Flash Mixer 10.05.2023 20.05.2023
10.5 Installation of Diffusers in SBR Tanks 10.05.2023 20.05.2023
SN ACTIVITY Satellite, Kota
10.6 Installation of Tube Media in settling Tank 10.05.2023 20.05.2023
Installation of Air Blower and piping work with supports and
10.7 10.05.2023 20.05.2023
required fittings and acoustic chamber.
10.8 Installation of Auto Fine Screens with interconnecting piping 10.05.2023 20.05.2023
Installation of Screw Press with piping fittings and poly
10.9 10.05.2023 20.05.2023
dosing system.
10.10 Installation of UV's 10.05.2023 20.05.2023
10.11 Installation of Decanting System. 10.05.2023 20.05.2023
10.12 Installation and laying of Cable Tray's 20.05.2023 22.05.2023
10.13 Laying of Cables 23.05.2023 25.05.2023
10.14 Installation of Panel and Scada 25.05.2023 26.05.2023
10.15 Dressing and Termination of Cables 28.05.2023 30.05.2023

11 Testing & Commissioning 30.05.2023 31.05.2023


ACTIVITY Janana, Jaipur NMCH, Kota

S.No. Description Start Date End Date Start Date End Date

1 Submission of Drawing & Design Completed Completed


2 Approval of Drawings & Design Completed Completed
Submission Civil structural drawings & design for foundation and plant
Completed Completed
3 building.

4 Approval of Civil structural Drawings & Design Completed Completed


Civil Markings on site & Completion of Civil Work on Site post the
Completed Completed
5 drawings finalization

6 Completion of Civil Foundation Works to start fabrication works at site. 30.03.2023 10.04.2023

7 Supply of 1st Lot of material - Internal Factory:


7.1 Supply of MS C-Channels for Base Frame and internal Structure 01.04.2023 15.04.2023
7.2 Supply of MS Sheet for Base Frame 01.04.2023 15.04.2023
7.3 Supply of MS Sheet sent for corrugation 07.04.2023 15.04.2023
7.4 Supply of MS Corners 07.04.2023 15.04.2023
7.5 Supply material to vendor for rolling tank 1 and 2 07.04.2023 15.04.2023
7.6 Base rolling material for layer 1 dispatch 07.04.2023 15.04.2023
7.7 Supply of round tank second layer rolling sheet and channel 07.04.2023 15.04.2023
7.8 Supply of round tank third layer rolling sheet and channel 07.04.2023 15.04.2023
7.9 Supply of MS Corrugated Sheets (Side & Partition Sheets) 07.04.2023 15.04.2023
Supply of MS Chequered Sheets, MS Pipes for Railings, MS C-
7.10 30.05.2023 15.05.2023
Channels, MS Angles for steps
Supply of MS Flanges and round pipes for puddles fabrication - Internal
30.05.2023 15.05.2023
7.11 Factory

7.12 Supply of MS Plate for Ribs - Internal Factory 30.05.2023 15.05.2023

MS Tank Fabrication work rectangular tank 1

1 Outer Frame Work of Container Base Frame 03.04.2023 03.04.2023 16.04.2023 16.04.2023

Fit-up and welding of structural members inside Outer Base Frame of


03.04.2023 05.04.2023 16.04.2023 17.04.2023
container.
2
3 Fit-up and welding of MS Sheets above MS C-channels frame. 06.04.2023 08.04.2023 17.04.2023 17.04.2023

5 Welding from bottom of Base frame. 09.04.2023 09.04.2023 18.04.2023 19.04.2023

6 Coal tar Epoxy Paint at bottom of Base Frame. 10.04.2023 10.04.2023 18.04.2023 19.04.2023

7 Fitup MS Corners and top pipe of 1st Stage Height vertically. 11.04.2023 11.04.2023 20.04.2023 20.04.2023

8 Outside sites fabrication of all tanks 12.04.2023 16.04.2023 21.04.2023 23.04.2023

9 Inside partition sheet fitup of all tanks 17.04.2023 20.04.2023 23.04.2023 25.04.2023

10 Welding of MS Corners of 2nd Stage Height vertically. 21.04.2023 21.04.2023 26.04.2023 26.04.2023

11 Welding of top MS Pipe above MS Corners. 22.04.2023 22.04.2023 26.04.2023 26.04.2023

12 Side & partition Sheets Fit-up (2nd Stage Height) 23.04.2023 26.04.2023 27.04.2023 29.04.2023

fitup and Welding of Ribs at joints and structure work with MS C-


27.04.2023 28.04.2023 30.04.2023 30.04.2023
Channels at all levels.
13
14 Complete welding of Container from Inside and outside. 29.04.2023 05.05.2023 01.05.2023 04.05.2023

15 Cutting of sheets and welding puddle flanges. 05.05.2023 06.05.2023 04.05.2023 05.05.2023

MS Tank Fabrication work rectangular tank 2

1 Outer Frame Work of Container Base Frame 20.05.2023 20.05.2023


Fit-up and welding of structural members inside Outer Base Frame of
20.05.2023 21.05.2023
2 container.

WILL BE DISPATCHED
FROM FACTORY BY
30/04/2023
ACTIVITY Janana, Jaipur NMCH, Kota

S.No. Description Start Date End Date Start Date End Date

3 Fit-up and welding of MS Sheets above MS C-channels frame. 21.05.2023 22.05.2023


WILL BE DISPATCHED
4 Welding from bottom of Base frame. FROM FACTORY BY 22.05.2023 23.05.2023
Coal tar Epoxy Paint at bottom of Base Frame. 30/04/2023 23.05.2023 23.05.2023
5
6 Fitup MS Corners and pipe 24.05.2023 24.05.2023
7 Fabrication of ms sheets 24.05.2023 26.05.2023
8 Complete welding of ms sheets 27.05.2023 31.05.2023

Circular Tank Fabrication work 1 and 2

1 Outer Frame Work of Container Base Frame 1 and 2 05.05.2023 06.05.2023 05.05.2023 06.05.2023
2 making base ring and tank base fabrication 1 and 2 06.05.2023 10.05.2023 06.05.2023 10.05.2023
3 complete welding of both tanks base 1 and 2 10.05.2023 12.05.2023 10.05.2023 12.05.2023
4 first layer of circular tank fabrication tank 1 13.05.2023 13.05.2023 13.05.2023 13.05.2023
5 ring fabrication on first layer tank 1 14.05.2023 14.05.2023 14.05.2023 14.05.2023
6 second layer of circular tank fabrication tank 1 15.05.2023 15.05.2023 15.05.2023 15.05.2023
7 ring fabrication on second layer tank 1 16.05.2023 16.05.2023 16.05.2023 16.05.2023
8 third layer of circular tank fabrication tank 1 16.05.2023 16.05.2023 16.05.2023 16.05.2023
9 ring fabrication on third layer tank 1 17.05.2023 17.05.2023 17.05.2023 17.05.2023
10 full welding on first layer tank 1 18.05.2023 18.05.2023 18.05.2023 18.05.2023
11 full welding on second layer tank 1 19.05.2023 19.05.2023 19.05.2023 19.05.2023
12 full welding on third layer tank 1 20.05.2023 20.05.2023 20.05.2023 20.05.2023

13 first layer of circular tank fabrication tank 2 13.05.2023 13.05.2023 13.05.2023 13.05.2023
14 ring fabrication on first layer tank 2 14.05.2023 14.05.2023 14.05.2023 14.05.2023
15 second layer of circular tank fabrication tank 2 15.05.2023 15.05.2023 15.05.2023 15.05.2023
16 ring fabrication on second layer tank 2 16.05.2023 16.05.2023 16.05.2023 16.05.2023
17 third layer of circular tank fabrication tank 2 16.05.2023 16.05.2023 16.05.2023 16.05.2023
18 ring fabrication on third layer tank 2 17.05.2023 17.05.2023 17.05.2023 17.05.2023
19 full welding on first layer tank 2 18.05.2023 18.05.2023 18.05.2023 18.05.2023
20 full welding on second layer tank 2 19.05.2023 19.05.2023 19.05.2023 19.05.2023
21 full welding on third layer tank 2 20.05.2023 20.05.2023 20.05.2023 20.05.2023

22 Water testing of all tanks 21.05.2023 23.05.2023 01.06.2023 02.06.2023


23 leakage rectification of all tanks 23.05.2023 23.05.2023 03.06.2023 04.06.2023
24 FRP lining inside Containers 24.05.2023 28.05.2023 05.06.2023 09.06.2023
25 Epoxy Paint of all conatiners 28.05.2023 30.05.2023 09.06.2023 10.06.2023

Supply of 2nd Lot of Material:

1 Supply of Fine Screen 05.06.2023 05.06.2023


2 Supply of all Pumps 05.06.2023 05.06.2023
3 Supply of Screw Press 05.06.2023 05.06.2023
4 Supply of Electrical Panel & SCADA 15.06.2023 15.06.2023
5 Supply of Decanters with Hydraulic lifting arrangements 05.06.2023 05.06.2023
6 Supply of Air Blowers with acoustic chambers and diffusion systems. 05.06.2023 05.06.2023
7 Supply of Motorised Valves, check valves, NRV, etc. 05.06.2023 05.06.2023
8 Supply of Cable, Cable Tray's, piping, fittings, etc. 05.06.2023 05.06.2023
9 Supply of Thimble Gate Valves with EO System 05.06.2023 05.06.2023
10 Supply of Flow meters 05.06.2023 05.06.2023
11 Supply of UV's 05.06.2023 05.06.2023

Installation:
1 Piping with Valves for transferring sludge to Sludge Sump 06.06.2023 15.06.2023 06.06.2023 15.06.2023
2 Installation of RAS Piping with complete piping work 06.06.2023 15.06.2023 06.06.2023 15.06.2023
ACTIVITY Janana, Jaipur NMCH, Kota

S.No. Description Start Date End Date Start Date End Date

Installation of Main Lifting Pumps with NRV's, expansion bellows,


3 06.06.2023 15.06.2023 06.06.2023 15.06.2023
Motorised Vales, Ultrasonic Flow Meter and piping works.
4 Installation of Agitator in Flash Mixer 06.06.2023 15.06.2023 06.06.2023 15.06.2023
5 Installation of Diffusers in SBR Tanks 06.06.2023 15.06.2023 06.06.2023 15.06.2023
6 Installation of Tube Media in settling Tank 06.06.2023 15.06.2023 06.06.2023 15.06.2023
Installation of Air Blower and piping work with supports and required
7 15.06.2023 18.06.2023 15.06.2023 18.06.2023
fittings and acoustic chamber.
8 Installation of Thimble Gate Valves 06.06.2023 15.06.2023 06.06.2023 15.06.2023
9 Installation of Coarse Screens with lifting arrangements. 06.06.2023 15.06.2023 06.06.2023 15.06.2023
10 Installation of Auto Fine Screens with interconnecting piping 06.06.2023 15.06.2023 06.06.2023 15.06.2023
11 Installation of Screw Pumps and Screw Press with piping fittings and pol 15.06.2023 18.06.2023 15.06.2023 18.06.2023
12 Installation of UV's 06.06.2023 15.06.2023 06.06.2023 15.06.2023
13 Installation of Decanting System. 06.06.2023 15.06.2023 06.06.2023 15.06.2023
14 Installation and laying of Cable Tray's 18.06.2023 21.06.2023 18.06.2023 21.06.2023
15 Laying of Cables 22.06.2023 25.06.2023 22.06.2023 25.06.2023
16 Installation of Panel and Scada 26.06.2023 27.06.2023 26.06.2023 27.06.2023
17 Dressing and Termination of Cables 27.06.2023 29.06.2023 27.06.2023 29.06.2023

Testing & Commissioning 29.06.2023 30.06.2023 29.06.2023 30.06.2023


ACTIVITY PBM, BIKANER
Description Start Date End Date

1 Submission of Drawing & Design Completed


2 Approval of Drawings & Design Completed

3 Submission Civil structural drawings & design for foundation and plant building. Completed

4 Approval of Civil structural Drawings & Design Completed

Civil Markings on site & Completion of Civil Work on Site post the drawings finalization Completed
5

6 Completion of Civil Foundation Works to start fabrication works at site. 30.04.2023

7 Supply of 1st Lot of material - Internal Factory:


7.1 Supply of MS C-Channels for Base Frame and internal Structure 01.05.2023
7.2 Supply of MS Sheet for Base Frame 01.05.2023
7.3 Supply of MS Sheet sent for corrugation 01.05.2023
7.4 Supply of MS Corners 01.05.2023
7.5 Supply material to vendor for rolling tank 1 and 2 01.05.2023
7.6 Base rolling material for layer 1 dispatch 01.05.2023
7.7 Supply of round tank second layer rolling sheet and channel 01.05.2023
7.8 Supply of round tank third layer rolling sheet and channel 01.05.2023
7.9 Supply of MS Corrugated Sheets (Side & Partition Sheets) 01.05.2023

Supply of MS Chequered Sheets, MS Pipes for Railings, MS C-Channels, MS Angles for


7.10 30.05.2023
steps

7.11 Supply of MS Flanges and round pipes for puddles fabrication - Internal Factory 30.05.2023

7.12 Supply of MS Plate for Ribs - Internal Factory 30.05.2023

MS Tank Fabrication work of EQT 1 & 2

1 Outer Frame Work of Container Base Frame 1 and 2 03.05.2023 03.05.2023

2 Making base ring and tank base fabrication 1 and 2 03.05.2023 05.05.2023

3 complete welding of both tanks base 1 and 2 06.05.2023 08.05.2023

4 first layer of circular tank fabrication tank 1 & 2 09.05.2023 09.05.2023

5 ring fabrication on first layer tank 1 & 2 10.05.2023 10.05.2023

6 second layer of circular tank fabrication tank 1 & 2 11.05.2023 11.05.2023

7 ring fabrication on second layer tank 1 & 2 11.05.2023 12.05.2023

8 third layer of circular tank fabrication tank 1 & 2 12.05.2023 13.05.2023

9 ring fabrication on third layer tank 1 & 2 13.05.2023 14.05.2023

10 full welding on first layer tank 1 & 2 14.05.2023 15.05.2023

11 full welding on second layer tank 1 & 2 15.05.2023 16.05.2023

12 full welding on third layer tank 1 & 2 16.05.2023 17.05.2023

MS Tank Fabrication work of Tube Settler Tank 1 & 2


ACTIVITY PBM, BIKANER
Description Start Date End Date

1 Outer Frame Work of Container Base Frame 1 and 2 03.05.2023 03.05.2023

2 Making base ring and tank base fabrication 1 and 2 03.05.2023 05.05.2023

3 complete welding of both tanks base 1 and 2 06.05.2023 08.05.2023

4 first layer of circular tank fabrication tank 1 & 2 09.05.2023 09.05.2023

5 ring fabrication on first layer tank 1 & 2 10.05.2023 10.05.2023

6 second layer of circular tank fabrication tank 1 & 2 11.05.2023 11.05.2023

7 ring fabrication on second layer tank 1 & 2 11.05.2023 12.05.2023

8 third layer of circular tank fabrication tank 1 & 2 12.05.2023 13.05.2023

9 ring fabrication on third layer tank 1 & 2 13.05.2023 14.05.2023

10 full welding on first layer tank 1 & 2 14.05.2023 15.05.2023

11 full welding on second layer tank 1 & 2 15.05.2023 16.05.2023

12 full welding on third layer tank 1 & 2 16.05.2023 17.05.2023

MS Tank Fabrication work of SBR Tank 1 & 2

1 Outer Frame Work of Container Base Frame 1 and 2 18.05.2023 18.05.2023

2 Making base ring and tank base fabrication 1 and 2 18.05.2023 20.05.2023

3 complete welding of both tanks base 1 and 2 21.05.2023 22.05.2023

4 first layer of circular tank fabrication tank 1 & 2 23.05.2023 23.05.2023

5 ring fabrication on first layer tank 1 & 2 23.05.2023 24.05.2023

6 second layer of circular tank fabrication tank 1 & 2 24.05.2023 25.05.2023

7 ring fabrication on second layer tank 1 & 2 25.05.2023 26.05.2023

8 third layer of circular tank fabrication tank 1 & 2 26.05.2023 27.05.2023

9 ring fabrication on third layer tank 1 & 2 28.05.2023 29.05.2023

10 full welding on first layer tank 1 & 2 30.05.2023 31.05.2023

11 full welding on second layer tank 1 & 2 01.06.2023 02.06.2023

12 full welding on third layer tank 1 & 2 03.06.2023 05.06.2023

MS Tank Fabrication work TESR & Sludge Sump

1 Outer Frame Work of Container Base Frame 05.06.2023 05.06.2023

2 Fit-up and welding of structural members inside Outer Base Frame of container. 05.06.2023 06.06.2023

3 Fit-up and welding of MS Sheets above MS C-channels frame. 06.06.2023 07.06.2023

4 Welding from bottom of Base frame. 07.06.2023 07.06.2023

5 Coal tar Epoxy Paint at bottom of Base Frame. 08.06.2023 08.06.2023

6 Fitup MS Corners and pipe 09.06.2023 09.06.2023

7 Fabrication of ms sheets 10.06.2023 13.06.2023

8 Complete welding of ms sheets 13.06.2023 15.06.2023


ACTIVITY PBM, BIKANER
Description Start Date End Date

9 Water testing of all tanks 15.06.2023 18.06.2023

10 leakage rectification of all tanks 18.06.2023 20.06.2023

11 FRP lining inside Containers 20.06.2023 28.06.2023


12 Epoxy Paint of all conatiners 28.06.2023 30.06.2023

Supply of 2nd Lot of Material:

1 Supply of Fine Screen 20.06.2023


2 Supply of all Pumps 20.06.2023
3 Supply of Screw Press 20.06.2023
4 Supply of Electrical Panel & SCADA 20.06.2023
5 Supply of Decanters with Hydraulic lifting arrangements 20.06.2023
6 Supply of Air Blowers with acoustic chambers and diffusion systems. 20.06.2023
7 Supply of Motorised Valves, check valves, NRV, etc. 20.06.2023
8 Supply of Cable, Cable Tray's, piping, fittings, etc. 20.06.2023
9 Supply of Thimble Gate Valves with EO System 20.06.2023
10 Supply of Flow meters 20.06.2023
11 Supply of UV's 20.06.2023

Installation:
1 Piping with Valves for transferring sludge to Sludge Sump 21.06.2023 25.06.2023
2 Installation of RAS Piping with complete piping work 21.06.2023 25.06.2023
Installation of Main Lifting Pumps with NRV's, expansion bellows, Motorised Vales,
3 25.06.2023 30.06.2023
Ultrasonic Flow Meter and piping works.
4 Installation of Agitator in Flash Mixer 21.06.2023 25.06.2023
5 Installation of Diffusers in SBR Tanks 21.06.2023 25.06.2023
6 Installation of Tube Media in settling Tank 21.06.2023 25.06.2023
Installation of Air Blower and piping work with supports and required fittings and acoustic
7 01.07.2023 07.07.2023
chamber.
8 Installation of Thimble Gate Valves 01.07.2023 07.07.2023
9 Installation of Coarse Screens with lifting arrangements. 25.06.2023 30.06.2023
10 Installation of Auto Fine Screens with interconnecting piping 25.06.2023 30.06.2023

11 Installation of Screw Pumps and Screw Press with piping fittings and poly dosing system. 01.07.2023 07.07.2023

12 Installation of UV's 21.06.2023 25.06.2023


13 Installation of Decanting System. 21.06.2023 25.06.2023
14 Installation and laying of Cable Tray's 08.07.2023 10.07.2023
15 Laying of Cables 10.07.2023 12.07.2023
16 Installation of Panel and Scada 12.07.2023 13.07.2023
17 Dressing and Termination of Cables 13.07.2023 15.07.2023
ACTIVITY PBM, BIKANER
Description Start Date End Date
Testing & Commissioning 14.07.2023 15.07.2023