Due Date
# Action Item Owner Comments
Date completed
1 Civil design of the Anchor Block Maylane/ Mr. Ulisses 05/31/19 Suncontractor
2 Fabrication of the Anchor Block (If required) Maylane/ Mr. Ulisses 06/06/19 Subcontractor
The two pressure switches for suction were transferred from HP pumps #6 and
#9A to the transfer pumps.
6 Include 2 pressure switches in CWO 12 Mr. Ulisses/SOM 05/24/19 CCC will buy new switches to replace (will be included on the CWO)
Total of new switches for Transfer pumps is 4
Include calibration of the switches on the After clarification with SOM, this is not part of the scope but is a completed
7 Tiago/Sylvana 05/31/19
Moyno Pumps in CWO 12 activity.
4 ASSEMBLE THE
BLIND FLANGE
7 WELDING (CRITICAL)
8 PERFORM RT
(CRITICAL)
9 ASSEMBLE THE
PIPES
10 REPAIR
11 PERFORM RT
NOTES:
SOME ACTIVITIES WILL BE PERFORMED TOGETHER:
1&2
4 &5
Diameter in Flow
2 111 Gpm 25 m3/h
2 111 Gpm
2 111 Gpm
MAX FLOW