EPIC FOR UPGRADATION OF AC UPS UNITS IN NGL3, MESAIEED
TITLE: CONDUIT & FITTINGS INSTALLATION CHECKLIST
DOC NO. EI-E/006 CONTRACT NO. GC12105200
PROJECT NO. SYSTEM/SUB-SYSTEM NO. MANUFACTURER TYPE LOCATION DRAWING NO. ITEM CHECKLIST DESCRIPTION RESULT REMARKS
1 Conduit material/accessories as per project specification
Surface mounted conduits shall be laid in straight lines with neat bends & 2 sets permits ease drawing in cables
3 No conduit shall have more than two right angle bends without a draw-in box
Conduit shall be installed in accordance with manufacturer's installation
4 instructions 5 All conduits shall be installed with fish wires to permit ease of wiring
6 Conduits arranged such that running couples are minimum
Conduits shall be fastened with heavy duty spacing saddles fixed at intervals 7 not exceeding 1.2m Check if underground conduit bending radius not less than cable 8 manufacturer bending radius. 9 Check if underground conduit is not less than 2 inch diameter
10 Check if underground conduit rising from ground has concrete encasement
11 Proper sockets/bushes shall be provided for conduit entry to enclosures.
12 Cables shall run in conduit with min space factor of 40%
Damaged coating shall be properly repaired with protective paint as per 13 project specifications. All metallic conduit couplings/joints shall be properly repaired with protective 14 paint as per project specifications. 15 Conduit in plaster/concrete shall be secured by holdfasts or crampits
Remarks:-
Dopet Construction Dopet QA/QC QP
Name Position Signature Date DOC NO : 3513-M3GE-2-25-0019 REV. A PAGE 17 OF 29