SEQUENCE OF FINISHING ACTIVITIES - ALUMINIUM FORMWORK

Deshuttering activities

Post pour checking & closure

Conduit
checking for GI wire Shuttering tape removal
blockages Pulling

Meter Marking

Pipe provision for plumbing


works & bore packing

Water proofing works Sunkens (Tolet& Balcony) water Leakage testing


clearence proofing works

Screed concrete protection

PHE plumbing works in toilets/ Pressure testing/ Leak testing & correction.
Kitchen & Utility.

Toilet ledge wall block work Curing for 7 days

Fire line fixing works Leakage testing & Correction

Intenal wall & Ceiling Grinding


works

Gypsum Plaster works Gypsum Plaster Ceiling & Wall bull strip / Button
clearence marks
works

Rough plaster @ more than


12mm thick area

Bondit application

Gypsum plaster first Ceiling then


walls within specified period of
Bondit application. (wall bottom
left for skerting.)

Cornice work.

All Dado & tolet flooring All Dado & Toilet RCC wall hacking, Plumbing line
Tile clearence flooring Tile works groove filling & bull marking

Granite counter support MS frame


fixing

First coat Rough plaster

4 days curing

Dado tile line, level & lay out


checking & second coat plaster &
dado tile fixing except near door
frame area.

Curing for 4 days

Toilet flooring tile work.

Curing for 4 days

MS /railing insert
plates for
balcony/internal stairs

Granite counter and ledge wall


top granite fixing work.

Railing Fixing @ Balcony &


Staircase area.

Rain water shaft Block work &


plaster.

Vitrified tile flooring Vitrified flooring Concrete slab surface cleaning.


Clearence. works.

Balcony coping,window sill, Button marking.


Door thresold granite works

Mortor bed preparation & Tile


laying

Curing for 4 days

Tile protection

Vetrified skerting except door


jambs & curing

Gypsum plaster above skirting.

All Ceiling & walls Putty works

All ceiling & wall Primer


completion

Ceiling first coat paint


Door and window
Clearance
Door and window fixing

Ceiling final coat paint

Balance skiriting
All MS railings final coat paint works

Electrical & telephone Silicon works on both sides of


Wiring works windows.

Window grill fixing Sanitary fixtures

Toilet grid frame


Switches fixing Wall first coat paint setting

Switch plate cover fixing

Painting Clearance

False ceiling grid tiles

CP fittings completion

Floor & Dado tile joints cleaning.

Dado tile grouting works


completion.

Internal silicon works in toilets

Water commisioning testing

All floor & skirting tile grouting

Final coat of painting

Note:

DB display,Magic eye,Mosquito Indicates preceding activity to be completerd to


mesh fixing start succeeding activity

Indicates activity can be done simultaneously

Deep Cleaning

Final Clearance

Final HO