FLATS SEQUENCE OF WORKS - T6 & T7

Floor Clearance - Removal of Debris,


Deshuttering, other material etc.

Entire Floor Level marking bedding thickness to be noted

If thickness extra then backcoat


Bull Pad markings
plaster in toilets

Core Cut / Chipping works

Bore Packing & pond testing Railing fixing by others

Shaft Blockwork, Bund wall and


Waterproofing by other vendor
Plaster

Plumbing & MEP works Waterproofing by other vendor

MS framing for Granite counters in


Window Cill
Toilets

Blockwork - Ledge wall

Master Bedroom IPS Ledge wall Plaster Balcony Sunken Filling

Back Coat Plaster 2nd coat

Toilet Dado works

Toilet Flooring works

Bedroom, Living & Kitchen


Flooring & Skirting
Flooring & Skirting

Toilet Granite, Ledge wall & framing

Kitchen Dado

Balance Skirting, Cill, Main Door


Threshold

Door frame fixing by others

Cill, Skirting, Threshold

Handover of Flat Tiling works