Professional Documents
Culture Documents
2. OCCUPATIONAL RISKS
Falls to the same level
Cuts and other injuries
Running over
Particle Projection
3. PREVENTION MEASURES
- Whenever there is interference with the clearing works and pedestrian crossing, machinery shall be
organized and controlled by auxiliary trained personnel duly to monitor and direct their movements.
- Machinery operators shall check headlights, indicator lights and stop lights, and inspect the condition of the
tyres.
- People are not allowed close to the equipment.
ACTIVITY: EXCAVATION
1. PROCEDURE
Prior to trench excavation, the layout drawing should be carefully read, and surveying lead line of pipe shall be
marked at site. After approval of supervising engineer, underground existing utilities along pipeline should be
investigated and detected by means of inquiring from related local authority, even so test pits should be
excavated at the interval of around 20 meters so as not to damage the existing underground utilities.
Trench shall be excavated as per the designed elevation and lead line. During excavation, due to use of
machine, the trench bottom should be left for manual excavation at least 10-15cm if no groundwater, then
manpower shall be arranged for the final clearance and levelling of bottom. If the part of trench bottom is over-
excavated, the sand or soil free of stones shall be used as backfilling material and simply compacted as it is
necessary.
If the material of trench wall is loose and easy to fall down, the efficient and suitable measures of wall support
shall be taken to ensure the safety. During the excavation the distance between pipeline and wall or fence of
the existing house should be considered for safety reason. Normally the distance is not less than 0.8 meters.
The excavated materials shall be piled at one side of trench, and the other side will be used as access path for
transportation of pipe materials and construction area.
2. OCCUPATIONAL RISKS
Fall in height or same level
Burial
Cuts and other injuries
Electrocution
Running over
Dust
Falling objects
Detachment of land
3. PREVENTION MEASURES
- In trench excavation, Jiangsu will adopt the most appropriate containment solutions, taking into account the
following factors: ground cohesion, groundwater level and foreseeable accidents.
- Prior to commencing work, the ground will be checked for possible cracks or instability.
- All trenches more than 1.20 m deep must be naturally inclined or bent, and in any case the walls of the
excavation must be "cleared" of any loose elements;
- At all times when the trench is open, adequate access to the bottom of the excavation must be ensured,
either by stairs or other safe process that allows rapid escape in case of problems with the stability of the
excavation.
- In the case of accesses dug into the slope, they will be reinforced with the laying of a balcony and wooden
steps.
- The excavation materials must not be placed near the edge of the trench and it is necessary to ensure an
appropriate clearance (to be established case by case, but never less than 1/3 of the depth) in order to
prevent the excavation material from falling - if the excavation is bent and the bent is raised, excavation
materials may be deposited against this parapet, so the natural slope of this deposit does not exceed this
parapet in height;
- The equipment should always circulate away from the trench boundaries, with a minimum of 0.60 meters,
in such a way to prevent vehicles from falling. Such boundaries may consist of orange polyethylene nets at
least 1.00 meters high (if there is no risk of vehicles falling).
- At the boundaries of the trenches accessible for persons, the guardrails must be mounted at a suitable
distance to ensure adequate collective protection against the risk of falling.
- The guardrails will be used as collective protection in ditches higher than 1.50 m.
- The placement of any work support equipment (compressors, generators, etc.) or material close to the
trench edges shall be prohibited and adequate clearance not less than 60 cm must be kept;
- Every day, before starting any work inside the trenches, the stability of those trenches will be checked
(existence of cracks in the ground, defects in shoring material, etc.);
- The lifting and hauling equipment should be stabilized and be away from the trench edge.
- The approaching of vehicles to the edge of the trench for material transportation will be made within a safe
distance.
- Any materials will be placed more than 0.60 meters from the edge of the trench thus preventing accidental
overloads.
- Persons are not allowed to access to the dangerous area of the turntable.
2. OCCUPATIONAL RISKS
Fall in height or same level
Cuts and other injuries
Burial
Electrocution
Falling objects
3. PREVENTION MEASURES
- Provide secure stockpile area for pipes and fittings.
- Minimize height of pallets / stockpile.
- Maintain control of loads when lifting & moving.
- Apply appropriate signage and pedestrian control.
- Ensure security and equipment suitable to minimize vandalism.
- Keep area clean & clear of obstacles.
- Conduct site inspection to ensure access/egress is adequate for the task activities
- Maintain a safety working area around moving equipment.
- Maintain (specified) appropriate spillage control equipment.
- No load to be placed or moved near the edge of excavation where it is likely to cause collapse of side of
work.
2. OCCUPATIONAL RISKS
Fall in height or same level
Burial
Cuts and other injuries
Running over
Dust
Falling objects
Detachment of land
3. PREVENTION MEASURES
- Every day, before starting any work inside the trenches, the stability of those trenches will be checked
(existence of cracks in the ground, defects in shoring material, etc.);
- Every day, before starting any work inside the trenches, the condition of related equipment will be checked
carefully.
- Persons are not allowed to access to the dangerous area of the turntable.
- Whenever there is interference with the backfilling works and pedestrian crossing, machinery shall be
organized and controlled by auxiliary trained personnel duly to monitor and direct their movements.
- The equipment should always circulate away from the trench boundaries, with a minimum of 0.60 meters,
in such a way to prevent vehicles from falling.
- People are not allowed close to the equipment.
2. OCCUPATIONAL RISKS
Electrocution
Cuts and other injuries
Punctures and Crushes
Collapse of neighboring structures
Multiple burst injuries
3. PREVENTION MEASURES
- Ensure pipe not damaged.
- Ensure adequate support where a change in direction or reducer occurs.
- Don’t exceed pipe operating pressure, ensure pipe is correct diameter.
- Provision for a pressure gauge, stop valve and bleed valve is compulsory.
- Appropriate training and instruction in procedures for workers involved in the test.
- Designated test/exclusion zone.
- Lock-out/tag system to prevent persons other than those involved in the test from accidentally releasing
pressure.
- Consideration of the effects of hydro-static head pressure on the system in test.
- Adequate signage/information for persons other than those involved in the test.
- Protection of pipe-work and fittings with the potential to be damaged.
- To prevent joint or pipe section failure, fix brackets close enough together to prevent excessive movement.
ACTIVITY: FORMWORK
1. PROCEDURE
All formwork activities will be carried out in accordance with the specification.
Ensure that the props, shores, waling, bearers, clamps and tie rods are the right size and at the correct
spacing. The Formwork designer shall check the falsework system with respect to load imposed on it and
design parameters as laid down in the specification.
Forms fastened to previously cast concrete must be tightly fixed to prevent grout loss. Cellular foam plastic
strips can be used to make a seal.
Check quality of shutter lining, tightness of bolts and wedges, built-in items, inserts and other embedments.
Particular attention will be paid to the rigidity and line of stop ends and joint formers. Remove all tie-wire
clippings and nails, which may stain both the formwork and the concrete.
Ensure that adequate access and working platforms are in place for the concreting gang and that toe boards
and guardrails are provided. A spreader or lifting beam shall be used to prevent distortion when placing
formwork. Adjustable steel props shall be erected in plumb and verticality of props checked using a spirit level.
A prop should not be used if it is bent, creased or, rusted or has a bent head or base plate, damaged pin etc.
Proper release of agent shall be used so that it can be removed without damaging the surface finish of the
concrete. New timber and plywood forms shall be given first coat of the appropriate release agent 36 hours in
advance, then a second coat just before they are used. Avoid excessive use of release agent as this can
cause staining or retardation of the concrete.
A close watch should be kept on all wedges and fastenings. Make sure that they do not work loose. Grout loss
is an indication that some movement has occurred.
2. OCCUPATIONAL RISKS
Fall in height or same level
Falling objects
Crushing
Cuts and other injuries
Punctures
Collision
Electrocution
Burial by collapse of parts of the formwork
3. PREVENTION MEASURES
- The presence of personnel in the work areas during the hoisting, joisting, propping rebar operations is
strictly prohibited.
- The use of regulatory stairways to climb up to the casing panels is mandatory.
- Working from fully completed permanent or temporary work platforms e.g. not climbing on handrails or
guardrails to gain extra height
- Checking all required supports, bracing and ties are installed as the erection progresses
- Checking live loads arising from the erection work for the stage of completion—the number of workers and
plant items on the structure at any one time may need to be limited
- Tying props and frames laterally to prevent movement
- Providing adequate bracing between falsework frames to keep the structure rigid, and having all props and
frames bearing fully and evenly on their foundations.
- The nails in the wood used shall be removed as soon as possible.
- The nails shall be stacked up for a proper removal.
- Every electric machine shall have ground and differential switch protection.
- The stability of the casing panels and reinforcement shall be checked prior to pouring the concrete.
- After the completion of work, the work area shall be cleaned and all materials shall be stacked up for the
following removal.
ACTIVITY: CONCRETE
1. PROCEDURE
Concrete will be mixed on the site for placing and compaction. The Contractor shall inform the Engineer before
concrete starts and shall give the Engineer sufficient time to inspect the work which is to be concreted.
Concrete workers for compaction shall be properly trained in the use of vibrators prior to commencing work.
Concrete which in the opinion of the Engineer is no longer sufficiently workable shall not be placed in the
permanent work. Concrete shall be placed as close as practicable to its final position and shall not be moved
into place by vibration. Contractor shall make sure that concrete shall not to fall freely more than 2.7 m during
concreting work even by using of chute.
Unless otherwise permitted by the Engineer, concrete shall be compacted by means of internal vibrators of
suitable diameter. A sufficient number of vibrators shall be maintained in serviceable condition on the Site to
ensure that spare equipment is available in the event of breakdown.
Vibration shall not be applied by way of the reinforcement, and contact between internal vibrators and
formwork, reinforcement or built-in components shall be avoided as far as possible. Concrete shall be vibrated
in such a manner that the formwork, reinforcement or built-in components will not be displaced.
Internal vibrators shall be pushed down into the freshly placed concrete in an axial direction until the whole of
the concrete in their immediate vicinity has been vibrated to its full depth. They shall then be withdrawn slowly
and re-inserted in the next position. The vibrators shall be inserted deep enough to ensure that the top of the
previously compacted layer of concrete is also revibrated and the timing must be such that this layer is still
within the time limit for proper response to vibration.
After completion of the finishing process on the unformed faces of concrete, all surfaces exposed to air shall be
covered with a layer of approved material and all edges of which shall be security fixed such that no air
circulation can take place until such time as the concrete has hardened sufficiently to permit further protection.
The covering shall be removed and the concrete completely covered with hessian, sacking, or other similar
absorbent material, and the cover material shall be kept constantly wet.
2. OCCUPATIONAL RISKS
Fall in height
Falling objects
Burial
Bruises
Electrocution
Collapse
Contact with concrete (dermatoses)
3. PREVENTION MEASURES
- Prior to pouring, the safe state of the casing formwork shall be inspected to prevent blowouts and spillages.
- The vehicles shall always be 2 meters (as a general rule) away from the ditches (or baffles) to pour the
concrete. There shall be buffing gear at that distance so as to ensure safety. (Dumper or cement mixer).
- Prior to pouring, the person in charge shall inspect the good condition of earth retaining shoring of
emptying slopes that are in the area of the wall that is going to be poured, to perform strengthening or
correction as necessary.
- Prior to pouring, and to cap off the casing formwork, upper part of the work platform shall be constructed
from where the work the pouring and vibrated concrete operations shall be carried out.
- The pouring of concrete within the casing panels shall be done by uniformly spreading same in regular
tonnes, avoiding punctual overloads that deform or burst the casing.
- Secure chock at the paths' end, for vehicles which travel to pour concrete near the edges of the trenches,
(Dumper, truck mixer) shall be installed.
- The correct layout and disposal and condition of the protections shall be inspection prior to pouring.
- The proper performance of the casing panels during the pouring shall be monitored, and the process shall
be stopped if any failure is detected.
- There shall be easy and secure accesses to get to the workplaces.
- The top slabs will be covered in order to prevent falls to a different level.
- Concentrating concrete loads in only a single point is strictly prohibited. Pouring shall be carried out by
spreading the concrete smoothly and over wide surfaces.
2. OCCUPATIONAL RISKS
Fall in height
Falling objects
Burial
Bruises
Electrocution
Collapse
Contact with concrete (dermatoses)
3. PREVENTION MEASURES
- Valves must be inspected for dust, sand, iron oxide and other impurities before installation. If any of the
above debris must be cleaned up before installation.
- All valves must be equipped with gaskets of corresponding grade before installation.
- When installing flange doors, fasteners must be tightened, and flange bolts must be tightened in a
symmetrical direction in turn.
- In the process of valve installation, all valves must be installed correctly according to the system and
pressure. No random or mixed assembly is allowed. For this reason, all valves must be numbered and
recorded according to the system before installation.
- Avoid carelessly placing them outdoors or where there is a lot of dirt. In particular, be careful not to remove
the caps from the ends until the time immediately before installation.
- Before installing a valve on the piping line, check that the valve is the specified one by its marking, valve
name, valve number, etc., on the body surface.
- If foreign matter remains in the piping on which the valve is installed, the valve seat surface may be
damaged and a seat leak may occur. Therefore, thoroughly clean the piping and equipment.
- Check the flow direction arrow on the valve body before installing the piping.
- When installing valve piping, consider the operation space, maintenance space, and the installation of
chain blocks to lift heavy parts.
- Install the valve by a layout in consideration of daily walk round checks, lubrication, and maintenance.
- Install effective supports in piping to prevent excessive bending or twisting from acting on the valve due to
the valve outlet piping and the mass of highly charged fluid.
- Confirm that it is not loosen when water seal pipe is connected in valve.
2. OCCUPATIONAL RISKS
Electrocution
Cuts and other injuries
Running over
Dust
Contact with concrete (dermatoses)
Bruises
3. PREVENTION MEASURES
- Prior to construction, the construction machinery should be inspected to ensure that the operation condition
of the machinery and equipment is safe and reliable.
- Prior to the construction, an obvious roadblock should be set in front of the road section, traffic signs
should be set up, and traffic guidance should be done.
- Operators of machinery and electrical equipment must be trained before they start the work.
- Keep the construction site clean and orderly. The construction machinery is neatly parked, and the
environment of the construction area is tidy.
- The construction machinery is prone to dust, we will do the dust reduction work, and sprinkle water in time.
- The construction personnel must work in the conical traffic sign enclosure area and set up a special person
for traffic control.