WORK PROGRESS STATUS



A. TILING WORKS @ LANAI

1.0 Accomplishments 95%

2.0 Target Completion Date May 24, 2014

3.0 Cost to Complete ( LABOR Only) PHP 820.00

B. PAINTING WORKS

1.0 WALLS

1.1 Accomplishments 30%

1.2 Target Completion Date May 27, 2014

1.3 Cost to Complete ( LABOR Only) PHP 1,500

2.0 CEILING

1.1 Accomplishments 0%

1.2 Target Completion Date May 28, 2014

1.3 Cost to Complete ( LABOR Only) PHP 2,000

3.0 WINDOWS

1.1 Accomplishments 10%

1.2 Target Completion Date May 29, 2014

1.3 Cost to Complete ( LABOR Only) PHP 2,000

`