Professional Documents
Culture Documents
PROJECT REPORT
ON
SINGLE CAVITY HOT TIP MOULD
IN
WORKORDER NO.822098N
CUSTOMER-LARSEN &TOUBRO LTD.
MUMBAI
By
ADTDM-04
YOGESH V.NIKAM
ENROLL NO. =2004141
Production Department 1
PROJECT REPORT
PROJECT REPORT
Production Department 2
PROJECT REPORT
Mr. Mahesh kande, Mr.Yogesh Dxit, Mr. Amit Gajbhiye & Mr.
thanks for the valuable guidelines and help from Mr. Vishal Sabde
At last I would like to thank all the members of IGTR and collogues
Production Department 3
PROJECT REPORT
This project reveals the effort taken during the implant training in
July 2008.
such as Injection Mould; hot tip Mould & Compression Mould etc. It also
gives a view of design consideration involved in press tool, mould & die-
casting-dies. It gives the idea of the flow of design from the stage of
PAGE
Sr.no. DESCRIPTION
NO.
Production Department 4
PROJECT REPORT
INTRODUCTION
01 6-13
DESIGN CONSIDERATION
02 14
PROCESS
Design & PROJECT details
03 15-17
COMPONENT DETAILS
04 17-19
COMPONENT MATERIAL
05 20-21
DETAIL
11
cost estimation 50-62
12
tool inspection report 63-68
Production Department 5
PROJECT REPORT
1 BASICS
The single most important component in the moulding process is
the Mould. Some times cost of the mould overtakes machine cost and
always plays a vital role in deciding the product cost.
Almost 70% of the plastic products are produced by Injection Moulding
method among all the plastics processing techniques available so far.
So it is obvious that a large number of Injection moulds are made
everywhere. Accordingly a lot of developments in mould making
techniques have taken place. Hot Runner Mould is one of such great
achievements in mould making field.
1. E
VOLUTION OF HOT RUNNER MOULDS
Production Department 6
PROJECT REPORT
more wastage. One can argue of reusing the scrap as seconds and
mixing to virgin material, but, still the process is uneconomical.
Production Department 7
PROJECT REPORT
The classification of Hot Runner Systems is subject to the kind of
heating provision available with it. They are two types in general, i.e.
In this case the melt is heated from out side while passing through
the feeding channel. Electrical heaters supply the heat.
Production Department 8
PROJECT REPORT
The hot sprue bushings are designated to remove the superfluous direct
gate on single mouldings. Also this is used to carry plastic melt up to
main runner in case of multiple gate design.
Manifold
Production Department 9
PROJECT REPORT
Injection Nozzles
Heaters
1. Catridge heaters
Most Common method of manifold heating is done with catridge
heaters. They are placed inside accurately drilled and reamed holes
parallel to the runner. The advantage lies with easy replacement of the
heaters. Catridge heaters are commercially available as standard part
in various diameters, lengths and wattage.
2. Tabular heaters
3. Band heater
4. Coil heater
Temperature Sensors
The hot runner system remains hot during its entire operation.
Temperature sensor is essential to keep track of the temperature of the
manifold and other components. Different types of thermocouples are
used to sense the temperature and give feed back to the controlling
unit.
Production Department 10
PROJECT REPORT
Temperature Controller
COMMERCIAL
2. Savings in cost for
regrind
3. No investment for
grinder
4. No Investment for
robotized runner picker No sprue or runner is produced
5. Savings in storage cost
for scrap
6. Shorter cycle Moulding of the sprue and
7. Shot size is reduced by
runner is eliminated
volume
8. Larger shot volume is
available for filling
larger number of
cavities
Production Department 11
PROJECT REPORT
9. Cooling timeis reduced
1 Smaller opening stroke
0. than for a three plate
mould
1 Ease of manufacturing Standard parts for hot runner
1. system are easily available, i.e.
Sprue bushings
Manifolds
Nozzles
Heaters
Thermocouples
1 Less moving parts Hot runner system become
2. compared to three integral and remain fixed to the
plate mould injection half
DISADVANTAGES
FLAWS REASONS
1. More work is Experienced designers are
necessary in mould required
design
2. Higher mould cost Incorporation of auxiliary
COMMERCIAL
3. Unit cost goes up
equipment’s like Nozzles, Heaters,
incase of low
Temperature sensors,
production
Temperatures etc.
requirement
4. Costly maintenance Careful handling is essential. Also
repair due to wear & tear and
damage costs more
TEC
sensitive material.
DESIGN CONSIDERATION
Moulds:-
✖ Material used for the component, its applications.
✖ Shrinkage of the material.
✖ Calculate the weight of the component.
✖ Study the detail of the component.
Production Department 13
PROJECT REPORT
✖ Type of mould required for the component to be produced.
✖ Machine available for the component.
✖ Injection pressure required.
✖ Type of runner system & gate required.
✖ Type of ejection system weather blade, stripper etc.
✖ Split and side core consideration if the component is having
any groove or notch on its sides.
✖ Cycle time required for the component for complete fill.
✖ Effective cooling in a short duration is necessary.
✖ Cooling channels must be lick proof.
✖ Selection of the material for core & cavity.
✖ Adding of shrinkage to core & cavity dimensions.
✖ Parts in the assembly must not foul with each other in
operation.
The layout of the tool must not be oversized
Component detail
Production Department 14
PROJECT REPORT
DESIGN input
Production Department 15
PROJECT REPORT
Existing Sample of Component
The Tool related input from the customer may be in the form of
Type of Mould / Die
No. of Cavities
Production Rate
The Material related input from the customer may be in the form of
Component Material
Shrinkage
Component weight
Die Set Material
Core/Cavity Material
Aesthetic & Functional Requirements of Component that should be
discussed with the customer are as follows
Type of gate
Location of gate
Parting Line Constraints
Ejection mark constraints
Other inputs required from the customer are as follows
Reference Information
Standard Parts
Side Core Actuation Method
Machine Specification
Tool details…
The two plate Hot tip mould has been designed for single cavity
system, provided with Pin point gating for auto degating. The tool
with 354mm shut height and gross weight of 180 kg with ejection
stroke of 42 mm.
Materials for the plates are taken as M.S./C-45 and for inserts it is
ORVAR SUPREME also, based on the property of EN-31 we have
selected it for guide pillar and guide bush. the slide is made of o.s
material to Resist wear and tear during functionng.
Push back pins has been provided with springs as to assure the self
return provision of the ejector assembly. The ejector assembly
including ejector plate and ejector back plate has been supported by
two ejector supports, it is also provided with two ejector guide pillar
screwed with cavity back plate. Component has been feeded by point
gate to assure minimum gate mark and self degating.
Sufficient cooling has been provide in tool to optimize cycle mark and
to achive sound product. As the core in fixed half required cooling, to
assure effective cooling we have provided cooling channel right from
the bottom plate, the concept of cooling is not quite popular,
provision of cooling has also been provided in moving half cavity
insert.
Every aspects and considerations of designing and manufacturing
also has been taken in the tool to fulfill the requirement of the
customer and fit to economy of the organization.
Component details…
Production Department 17
PROJECT REPORT
Component details…
Production Department 18
PROJECT REPORT
Production Department 19
PROJECT REPORT
Shrinkage – 0.6%
Density - 1.2 gm/cm3
Type of Polymer – Amorphous Thermoplastic
Project details…
Mould details
Production Department 20
PROJECT REPORT
3 Total shot weight 33 grms.
1. Weight Calculations :-
Production Department 21
PROJECT REPORT
2. SHOT CAPACITY:-
The screw type machine is normally rated in terms of “Swept Volume”
of the injection cylinder (Cu. Cms).
3. PLASTICISING CAPACITY:
Plasticizing rate of material B (g/hr) = plasticizing rate of
material A (g/hr) x QA/QB
A = Polystyrene
B = ABS (Material actually to be used)
Production Department 22
PROJECT REPORT
Q = Thermal capacity of the material (cal/g) (Heat content)
QA = 239.4 KJ/Kg
QB = 302.4 KJ/Kg
= 48 KN
0.85 W
Ns =
m
Ns = 0.85 X 54.68 / 33
= 1.4 Approx.2
= 0.8 Approx
t= 3 C. P. d4
E.Y.
t = Min. wall thickness (cm)
y = Max. Deflection of Side Wall = 0.003cm
Pc= Max. Cavity Pressure = 900 bar
d = Total Depth of Cavity Wall = 3.6 cm
Production Department 26
PROJECT REPORT
4.0 0.140
5.0 0.142
= 0.5 cm
= 5.00 mm
SPLIT CALCULATION:-
Production Department 27
PROJECT REPORT
M = (L x Sin Ø)-(c/cos Ø)
Where:
M = split movement in mm = 15.5 mm
Ø = angle of finger cam = 18º
L =working length of finger cam=?
C = clearance = 0.5
We have to find L
15.5 = (L x sin18º)-(0.5/cos18º)
=28 mm
So working length of finger cam taken as 30 mm
Project details…
Production Department 28
PROJECT REPORT
Machine Selection
Production Department 29
PROJECT REPORT
CLOSING UNIT
Production Department 30
PROJECT REPORT
Part details…
CAVITY INSERT
Part details…
Production Department 31
PROJECT REPORT
CORE INSERT
Assembly details…
ASSEMBLY DETAILS
Production Department 32
PROJECT REPORT
ASSEMBLY OF TOOL
Assembly details…
Production Department 33
PROJECT REPORT
Assembly details…
Production Department 34
PROJECT REPORT
HOT TIP
Production Department 36
PROJECT REPORT
Production Department 37
PROJECT REPORT
Assembly details…
2D ASSEMBLY DRAWING
Production Department 38
PROJECT REPORT
Production Department 39
PROJECT REPORT
Part list…
PROCESS PLANNING
Production Department 40
PROJECT REPORT
As work piece quantities and costs in press work are usually high, considerable
the right type of tooling. The process plan should take into account the total cost:
material, tooling, labour (time). Process planning generally includes the following
considerations.
necessary to follow the proper methodology of manufacturing, so that one can get
accurate dimensional stability for that particular part within appropriate time.
In Die casting dies also all the parts of the tool are
machining sequence. Below mentioned sheet expresses all the view of machining
sequence of the tool. Similarly all the parts of the tool are manufactured by the
the assembly.
⇒ The part is studies and the plans for sequence of process like conventional,
inspection etc.
⇒ Special requirements for the tooling, electrode, and CAD/CAM support for the
programs required for the Core & Cavity inserts that are to be machined on
the CNC machines etc. are planned in advance to meet the process flow & to
⇒ Stage drawings of each parts coming & going out from process are made for
inspection methodology.
completion of the job in the planned time period to maintain the delivery
date.
⇒ The above information is applied for all processes related to the part
indicating earliest start & finish date of each process with respect to material
monthly priority list etc.The start & finish date can be taken from the job
cards the earliest finish date of assembly can be analyzed for the first trial
their support
Production Department 42
PROJECT REPORT
JOB CARD
WORK 822098 PART MATERIAL O.S
ORDER NO.
PART NO. 01 PART MATERIAL SIZE 61.80X181.5X147.5
PART NAME MAIN CORE INS PART QTY 61
DATE FINISH SIZE
A. PROCESS FLOW
XX
XX
B. REWORK DETAILS
PLAN BY
DATE
Production Department 43
PROJECT REPORT
A. PROCESS FLOW
XX
XX
B. REWORK DETAILS
PLAN BY
DATE
Production Department 44
PROJECT REPORT
WORK 822098 PART MATERIAL OS
ORDER NO.
PART NO. 63 PART MATERIAL SIZE
PART NAME LOCAL CORE-1 PART QTY 01
DATE FINISH SIZE
A. PROCESS FLOW
10 WIRE CUT XX
XX
XX
B. REWORK DETAILS
PLAN BY
DATE
Production Department 45
PROJECT REPORT
WORK 822098 PART MATERIAL O.S
ORDER NO.
PART NO. 64 PART MATERIAL SIZE
PART NAME LOCAL CORE2 PART QTY 01
DATE FINISH SIZE
A. PROCESS FLOW
10 WIRE CUT XX
XX
XX
B. REWORK DETAILS
PLAN BY
DATE
A. PROCESS FLOW
10 WIRE CUT XX
11 EDM XX
XX
B. REWORK DETAILS
PLAN BY
DATE
A. PROCESS FLOW
MATERIAL C%
SR. PROCESS Mn%
M/C Si%
START S%
COMP.P% QTY
Cr% Ni%
COMP.Mo%
SIGN
NO. DESCRIPTION DATE DATE ACC. REJ. BY
01 BLOCK 0.25
M.S. VF2
0.6- 16/6
0.1- 16/6 0.55 0.2-
0.055 XX
MILLING
02 S/G 0.
NEW 0.
17/6 17/6 0. XX
KENT
03 SPOTTING & 9
V33 35
20/6 20/6 35 XX
DRILLING
EN-8
04 B/W 0.35- 0.6-
B/W 0.05-
22/6 0.06
23/6 0.06 XX
07 0.
H/T 52-54 HRC 1. 25/6
PLANT 0. 2/7 XX
45 0 35
08 S/G KENT 2/7 2/7 XX
EN-31 0.9-
09 CNC MILLING 0.3-
HAAS 0.1-
4/7 0.05
4/7 0.05 1.0- XX
1. 0. 0. 1.
10 WIRE CUT XX
2 75 35 6
XX
OHNS 0.85- 1.0- 0.2- 0.3- 0.3
XX
0. 1. 0. 0.
B. REWORK DETAILS
95 5 4 6
PLAN BY
DATE
Production Department 48
PROJECT REPORT
of operations involving the heating and cooling the steel in solid state;
uses.
Hardening
It is a method of steel heating, 40 - 500C above the upper critical
temperature for hypo eutectoid steel or 40 - 500 above lower critical
temperature for hyper eutectoid steel, soaking for a specified time. The
hardness obtained by hardening process depends upon following –
1) Carbon content
2) Quenching rate
3) Work size
Quenching
Mark tempering – it is a process in which a steel is heated at the
hardening temperature soaked for a specified time & quenched in
isothermal bath having temperature 1800 to 3000C, kept just above the
martensite start line. The material is held there for a time just before
the nose of the bainite line. Afterwards it is cooled in air. The end
product it martensite.
Objective
1) Less distortions or warping
2) Less change in volume
3) Less change of quenching cracks & internal stresses
H.T. FOR
ORVAR SUPREME -
Hardening temperature - 1020 to 1050 deg. cel.
Quenching medium - air
Hardness after quenching - 46 to 52 HRC
Production Department 50
PROJECT REPORT
Tempering temperature - 250 to 550 deg. Cel.
Hardness after tempering - 54 HRC
H.T. FOR
O.H.N.S -
Hardening temperature - 790 to 815 deg. cel.
Quenching medium - oil
Hardness after quenching - 63 to 65 HRC
Tempering temperature - 150 to 425 deg. Cel.
Hardness after tempering - 50 HRC
Cost estimation…
Production Department 51
PROJECT REPORT
Production Department 52
PROJECT REPORT
Cost estimation…
Costingof tool
Involves
Production Department 53
PROJECT REPORT
Cost estimation…
1) Designing cost
It required,
60hours - 2D designing
20 hours - 3D modeling
Production Department 54
PROJECT REPORT
Cost estimation…
2) Material costs.
H = height of piece.
Production Department 55
PROJECT REPORT
Cost estimation…
Lathe 290/-
Milling 290/-
Surface grinding 290/-
Cylindrical grinding 290/-
The tool requires,
Lathe = 20 hours
Milling = 60 hours
Surface grinding = 48 hours
Cylindrical grinding = 18 hours
Production Department 56
PROJECT REPORT
Cost estimation…
4) Precision machining cost
Lathe = 00 hours
Milling = 18 hours
Wire cut = 30 hours
EDM = 40 hours
Production Department 57
PROJECT REPORT
Cost estimation…
Conventional 80/-
vacuum 300/-
Conventional = 60 hours.
Vacuum = 20 hours.
Production Department 58
PROJECT REPORT
Cost estimation…
6) Inspection cost
Conventional = 200/-
CMM = 1000/-
Conventional = 18 hours
CMM = 06 hours
Production Department 59
PROJECT REPORT
Cost estimation…
----------------------
3, 27,000 /-
Trail report…
Production Department 61
PROJECT REPORT
INSPECTION
Due to the great advancement, the continuous improvements in
Inspection does not mean fulfilling of the specifications lay down by the
raw material form to the finished products in the hands of the end
Inspection of all the parts are carried out by trained personal and
precisely working machines and it is followed by below mentioned path
Production Department 62
PROJECT REPORT
report.
⇒ The details of the process of each part can be obtained from the
Production Department 63
PROJECT REPORT
ASSEMBLY – PROCESS
While assembly of all parts and sub units first of all check the
following things.
parts.
Then drilling operation, for cooling holes, tapping holes are performed
on the bench drilling machines. Then those holes get tapped. Then after
the manufacturing of all the parts, actual assembly gets starts. All
standard parts available like Allen screw, etc which is required during
Production Department 64
PROJECT REPORT
etc. if required. For assembly of tool various points which are to be
⇒ Check all parts of standard die set and plate thickness for
further calculation.
⇒ Check all the standard parts which are being used in this tool.
⇒ All the inserts are maintained as per drawing for easy fitment.
Production Department 65
PROJECT REPORT
Trail report…
TOOL INSPECTION REPORT
INJECTION MOLDING DEPARTMENT
Material: -
Inj.moulding machine:-SP80
No. of shots:-
Shot weight:-
Component weight :-
REMARKS / OBSERVATIONS:-
Observation on component
1}
2}
3)
1}
2)
3)
4}
PARAMETERS:-
Clamping pressure :-
Injection Time :-
Holding Time :-
Cooling Time & Refilling Time:-
Total Cycle Time :-
Production Department 66
PROJECT REPORT
ACHIEVEMENT
tool & Die Making. It helped me lot in better understanding of the concepts
specific period of time for which I had to work to the best of my abilities to
⇒ In the project work I was given an opportunity to study the HOT TIP Mould
⇒ It was a nice opportunity for me to learn about such a tool, thus enhancing
my knowledge.
Production Department 67
PROJECT REPORT
CONCLUSION
various parts of the mold depends on the technique adopted for its
tool. The final mould design is prepared after the part design has
have been clarified. The outcome is a near perfect design and the
Production Department 68