Professional Documents
Culture Documents
Ind TRRNG
Ind TRRNG
Process
1. Designing
2. Lofting
3. Material Processing
4. Pre-Fabrication
5. Erection
6. Hull Outfitting
7. Delivery
↓ ↓ ↓ ↓
CAPTIVATOR
CAPTIVATOR MANGLES
R1 MANGLES
HYDRO LEVELLER
R2 MANGLES
R3 MANGLES
HEATING CHAMBER
BLASTING CHAMBER
SPRAY PAINTING
DRYING CHAMBER
NO of Piles 3
Specifications:
Speed 9.1M/Min
Specifications:
No of Rotoblast wheels 8
Power Req. 37 KW
Separation size 7”
Ventilation Req. 41,650 Cubic meter/hr
Specifications:
Speed 5M/Min
Specifications:
Width-6500 mm
Thickness 250 mm
Number of Torch 4
The SVTS, SVOS and DV are shown
above, after cutting the inspected plates are given their
respective identities such as
SVTS 25 3 mm NOSE
This suggests that the cut is Simple VEE Top side and the
angle is 25 degree. The NOSE is the thickness left from
bottom surface without cutting at the edge. For Double VEE
the NOSE is as shown above.
Specifications:
Capacity 320 T
CNC:
Specifications:
Specifications:
Size of Top Roller 19’
Min-19”
Capacity 10 M x 800 T
No of Dies 5
Specifications:
Capacity 250 T
Stroke 34”
Specifications:
Angle 1 to 3 degree
Correspondence to SHEARING:
Capacity 4 to 20 mm
Specifications:
Capacity 500 T
Stroke 99 mm
BULB PLATES: These are the flat bars with a bulb at one
end such that when the plate is joined with the other side at
the double bottom the force acting from the downwards is
resisted by the moment produced by the BULBS.
400 T COLD FRAME BENDING MACHINE: Here bending of
flat bars, angles, flat panels are done. The centre block of
the machine is fixed and the ends of the bars move
producing a bent bar.
Specifications:
Weight 21 T
HP of Motor 40
Horizontal Stroke 16”
Inside 10”
Specifications:
Min 40
1. Blasting Chamber
Specifications:
No. of wheels 5
Power 37 KW
Specifications:
No of guns 4
No of paint pump 1
DRYING CHAMBER:
Specifications:
PRE-FABRICATION
Panel construction is
done by two subsequent process Sub Assembling and
Assembling.
The PANEL is as shown:
Here welding of different parts
and surface finishing is done in order to create a panel.
Bottom Side
Shell
A-Fore end
B-Aft end
ERECTION DEPARTMENT
4. Alignment of Panels.
5. Consolidation of Panels.
FEATURES IN DETAIL:
3. Erection of Panels:
4. Alignment of Panels:
The side panels on D.S panels (P) & (S) are aligned with
the first panel DC/DB panels (datum) and with
reference to the Berth/Dock lines and unitized to form a
datum base of the vessel.
• Hold BHD, Side Shell panels (P) & (S) and U.D
Panels all aligned with first panel Datum-Base (4.2
line) moving from below upwards and utilized to
form a datum unit of Aft ward section of the
vessel.
5. Consolidation of Panels
The panel joint /Along with space tank is offered for dry
survey by class/owner after satisfactorily completing
the Q.C remarks.
HOSE TEST: With the help of fine tender water jet will be
forced on weld points with a pressure of 4-7 kg/cm 2 keeping
the water delivery nozzle tip 1.5 meter away from the
testing job and simultaneously inspects the other side of the
job for any leakage of water, if leaks are formed, the same
will be repaired.
DOCK PARTICULARS:
b) Width 53 m
d) Cope Level +4 m
of the dock
3. Height of dock cover from 52 m
Dock floor
a) Length 54.86 m
b) Breadth 6.00 m
c) Depth 10.40 m
d) Draught 5.45 m
CRANE FACILITIES:
1. Cranes:
Span 60 m
(75 T from 12 m to 35 m)
(50 T from 12 m to 40 m)
FEATURES:
Berth No.2 Berth
No.3 Berth No.4
Slipway.
5. Crane Facilities
35
T.H.H
8
T.L.L
Starboard side 60 T.L.L 45 T.H.H
45 T.H.H
35 T.H.H
8 T.L.L
1. Milling
2. Boring
3. Drilling
4. Lathe
5. Grinding
6. Engraving
7. Planer
2. Welding Section