You are on page 1of 11

C over Story

A “Construction Industry Payment


And Adjudication Act”:
Reducing Payment-Default And
Increasing Dispute Resolution Efficiency
In Construction
By Sr Noushad Ali Naseem Ameer Ali, President, The Institution of Surveyors Malaysia & Chair – Construction Industry
Working Group On Payment (WG 10). He can be contacted at e-mail: naseem@pd.jaring.my

This paper is in two parts. Part I covers various issues relating to payment in the Malaysian construction
industry, the proposed ‘Construction Industry Payment and Adjudication Act’ and some details on construction
adjudication as a speedy, economical, contemporaneous, and binding dispute resolution mechanism. Part II
(will be published in the Fourth quarter issue of Master Builders Journal) is in a question and answer format
covering nearly 50 questions that attempts to provide responses to many questions that may remain in various
related areas.

PART I

Introduction & Background projected estimated figures run into default is a major problem in the
billions of Ringgit. construction industry. Only the extent
Payment Default In The Malaysian varies with each survey.
Construction Industry Master Builders Association Malaysia
(MBAM) has also long been lamenting on Experience Of Other Countries
Payment has been said to be the life- the problems of delayed and non-
blood of the construction industry. Yet payment in the construction industry. One of the moves in the UK construction
the industry knows payment default, And MBAM too has been carrying out industry following Sir Michael Latham’s
specifically delayed and non-payment, surveys on payment issues. The surveys 1994 report ‘Constructing the Team’
remain a major problem. A recent only confirm the harsh reality – payment generally known as the Latham Report,
survey done by the Construction
Industry Development Board (CIDB) in
collaboration with University Malaya
(UM) ‘merely’ formally documents what
many in the construction industry
already know - there is a chronic
problem of delayed and non-payment
in the Malaysian construction industry
affecting the entire delivery chain. What
the survey does do is to provide
empirical evidence. It also extends the
findings to project estimates of delayed
and non-payment amounts based on
feedback from a sample of industry
players providing information on
payment problems between 2000 and
early 2006. The projected amounts are
staggering. Putting it mildly the

3 r d Q u a r t e r 2 0 0 6
C over Story

was the drafting of the Housing Grants,


Construction and Regeneration Act 1996
(UK Act). Part of the Act deals with a
scheme for payment and the resolution
of construction disputes through a
contemporaneous, speedy and
economical dispute resolution method
called adjudication.

Since then there are now similar Acts in


Australia, New Zealand and Singapore.
These include:

● Building and Construction Industry


Security of Payment Act 1999
amended in 2002 (New South Wales,
Australia)
● Building and Construction Industry
Security of Payment Act 2002
(Victoria, Australia) industry experience on payment including the main recommendation for a
● Construction Contracts Act 2002 problems and taking heed of Malaysian ‘Construction Industry Payment
(New Zealand) experience of other countries, WG 10 and Adjudication Act’.
● Building and Construction Industry then made various recommendations
Payments Act 2004 (Queensland, during the construction industry Payment And The
Australia) roundtable in June 2004 chaired by the Construction Industry
● Construction Contracts Act 2004 Honorable Minister of Works. One of
(Western Australia) the recommendations was for the The importance of payment in the
● Construction Contracts (Security of creation of a Malaysian ‘Construction construction industry
Payment) Act 2004 (Northern Industry Payment and Adjudication Act’.
Territory, Australia) The total contribution to Gross
● Building and Construction Industry Following agreement in principle Domestic Product (GDP) by the
Security of Payment Act 2004 during the meeting, WG 10 moved construction industry is significant.
(Singapore) towards its evolving vision which could Whilst in Malaysia it is in single digit,
be summarized as: ‘payment in the some developed countries have the
Some of these countries learnt the construction industry is timely’ - where construction industry contributing
consequences of payment default everyone in the construction industry more than 10% to GDP.
the hard ways – slow and sudden pays the appropriate amounts due in a
insolvencies, and minor and major timely manner. That ties in with the Payment in any industry has generally
insolvencies. Some of these countries construction industry masterplan vision been an issue of concern. In the
scrambled to get statutory provisions of making the Malaysian construction construction industry payment is an
after a few major disasters. industry world class by 2015. These in issue of major concern. This is because:
turn fit in with Malaysia’s 2020 vision of
Construction Industry Working Group becoming a fully developed country. (a) Unlike many other industries, the
on Payment (WG 10) durations of construction projects
One cannot have a ‘world class are relatively long;
Based on our own problems, payment construction industry’ if even ‘mundane’
was identified as one of ten priority things like payment is not being (b) The size of each construction
areas in the Malaysian construction honoured – whether in a timely manner project is relatively large and each
industry during a construction or at all! progress payment sum involved
industry roundtable in June 2003. An are often relatively large; and
industry working group (WG 10) led by I outline, in this paper, some key
the Institution of Surveyors Malaysia recommendations and developments on (c) Payment terms are usually on credit
(ISM) was then formed. Given the the plans to make the WG 10 vision a reality rather than payment on delivery.

3 r d Q u a r t e r 2 0 0 6
C over Story

Contrast these with say the medical and have introduced adjudication as a to realize the seriousness of the
industry or the tourism industry where fast, economical dispute resolution problem and to realize the potential
the size of each transaction is typically method for the construction industry. benefit of reducing the problem. The
much smaller. The durations of Malaysia too must not under-estimate seriousness of the problem has already
transactions in other industries are also the potential disastrous consequences been recognized by leaders in the
generally much shorter. of persistent payment default across the construction industry. Thus the
industry and the economy. At some identification of payment as an issue of
Cash Flow levels the problems are serious. We major concern and the formation of
cannot also deny that existing WG 10. Further recognition of the
Cash flow in the construction industry contractual arrangements and general problem was evident when the
is critical because of the relatively long legislation has not prevented the recommendations for the proposed
duration of projects. A planned problems. The test is in present results – Act were rapidly accepted by the
expected revenue flow is usually not what results we could have industry during the Construction
represented by an S curve. Any achieved. Industry Roundtable in June 2004
deviation due to either project delays or chaired by the Honorable Minister of
cash flow delays can have a major There is one self-test question that can Works.
impact on the project. be used to assess the seriousness of the
problem. Ask yourself the following Following the June 2004 industry
Diagram 1 below shows two planned S question and answer honestly: roundtable, a further open national
curves with different contract sums. If a conference was held in August 2004 to
deviation occurs halfway through the If all the past amounts due were paid gather wider feedback from industry.
project, it becomes increasingly more to your company today, and from And in order to get the maximum
difficult to recover if the original today onwards all amounts due are benefit from the experience of other
duration is to be maintained. This is paid promptly and in a timely countries around the world, WG 10
because the graph starts with a gentle manner, where would that put you recommended an international
slope then moves into a steep slope and your company financially – conference to be held in Kuala Lumpur.
before tapering off gently. Accelerating today, and in the future? This was primarily sponsored by the
to catch up on lost time on an already CIDB and held on 13 & 14 September
steep slope is an enormous task. The more significant the impact of your 2005. The international conference
answer on your company’s financial gathered about 18 top authorities
The Self-Test Question On Payment situation, the more serious the from around the world including all the
problem on payment is. countries that have introduced
The United Kingdom, nearly all states in legislation on payment and
Australia, New Zealand, and more Even without the benefits of the survey construction adjudication. This
recently Singapore have all statutorily results commissioned by the CIDB and international conference on payment
enacted provisions to address issues on UM, that question remains a self-test and adjudication legislation was
payment in the construction industry question for individuals in the industry acclaimed to be the first of its kind in
the world. Valuable feedback and
comments based on international
Construction S Curve experience were noted. Since then
50,000,000.00 further wide consultation and
45,000,000.00 briefings have been held in Malaysia
40,000,000.00 including briefings to captains of
35,000,000.00 industry, professional bodies, trade
Amount (RM)

30,000,000.00
organizations, academic institutions,
25,000,000.00
federal and state government
20,000,000.00
ministries and departments and the
15,000,000.00
Attorney-General’s chambers.
10,000,000.00
Following the development of early
5,000,000.00

-
concept proposals of our model,
0 1 2 3 4 5 6 7 8 9 10 11 12 13 exchanges of feedback was also held
Construction Period (m onth) with experts from Singapore, New
Diagram 1 Zealand and the United Kingdom.

3 r d Q u a r t e r 2 0 0 6
C over Story

all encompassing definition, disputes


on such ‘peripheral’ issues can be
avoided.

The UK Act has been so successful since


it came into force in May 1998 that the
process of adjudication is now even
being discussed for use in other
industries.

‘Pay All Appropriate Amounts Due’

‘Appropriate amounts due’ means


someone would have to decide what
such amount is. Where standard
terms of contracts are used the
mechanism would be through the
normal existing certification process
by an independent contract
The Malaysian Visions ● Clients (both public and private administrator eg superintending
sectors), officer or architect or contract
Malaysia has set its vision to be a ● Construction consultants involved administrator. Even if the contract
fully developed nation by 2020. The in construction projects such as administrator is not employed
construction industry has set it own architects, engineers and quantity independently but is instead an
vision to be ‘among the best in the surveyors. (Peculiarly, the New employee of one of the parties, the
world’ by 2015. As part of the plan, Zealand Act does not cover law would imply that duty to be
working groups on ten priority areas professional services relating to discharged fairly. And if payment is
were set up in June 2003. WG 10 was construction work) still not made following the normal
but only one of ten. ● Main contractors, certification process or the amount
● Sub-contractors, certified is alleged to be ‘unfair’, an
If the Malaysian construc tion ● Sub-sub-contractors, adjudicator may be called upon to
industry is to be ‘among the best in ● Suppliers ‘adjudicate’ on the certificate or other
the world’, the working group had to claims.
have an equally challenging vision. ‘The Construction Industry’
The vision of the working group on Where there is no provision for a
payment is: The construction industry includes contract administrator or progress
the building and civil engineering payment at all, such as the thousands
Ever yone in the construction sectors. Whether other sectors such as of present ‘domestic’ sub-contracts or
industr y pays all appropriate the oil and gas and shipping sectors ‘one-off ’ small contracts that are
amounts due in a timely manner. should be included is a question of entered into on a regular basis,
policy to be decided. Other countries legislation can step in to regularize
I now elaborate on the vision of WG do not include the shipping industry payment through a default payment
10 and how it can contr ibute and I think rightfully so. However mechanism. Again the process of
towards reducing payment default typically the oil and gas sector too has adjudication can step in to ensure it is
and increasing efficienc y in been excluded. If ‘because there is no done independently and fairly.
resolving disputes in the problem on payment in the oil and gas
construction industry. sector’ is the only reason, I do not see Following the independent process of
why the oil and gas sector should be adjudication through legislation,
‘Everyone’ excluded. Some of the court cases on there is a much higher possibility of
adjudication in the UK are on support from the court system in
Everyone means everyone involved in ‘peripheral’ issues such as whether a enforcing adjudicators’ decisions. This
the delivery chain of construction contract falls under the definition of a has been the experience in other
projects. They include: ‘construction contract.’ By having an countries with such legislation.

3 r d Q u a r t e r 2 0 0 6
C over Story

Parties who have had a fair ‘hearing’ because a longer period for payment, Studies also suggest the trait of
of their case through an independent known upfront, can be planned and integrity must be present consistently
adjudicator too are likely to accept the priced for in advance. Indeed if the if we are to achieve this vision of world
adjudicator’s decision and are less time for payment is unacceptably leadership. Without consistent
likely to seek to open up the same long a contractor might even choose integrity, eventually one will fall.
dispute in a protracted, relatively not to tender. On the other hand, ‘Situational integrity’ would not do – if
expensive arbitration or litigation. deviations from an original plan we are to be world class leaders.
Again that has been the experience in require re-planning, are often ‘Situational integrity’ is where the level
other countries with such legislation. unpredictable and can have a knock- of integrity of a person fluctuates
on effect on many other activities. depending on the situation faced.
‘Timely Manner’ Thus a breach on using pirated
Actual Time or Absolute Time software on one computer in the office
This is a key point in the WG 10 vision is sometimes waved away as trivial
statement. I t is important to The actual time or period needed which doesn’t affect the company’s
distinguish: would vary among players in the ‘overall integrity’! Or a company which
construction industry. The time period has tax planned and has avoided (which
(i) the actual time or duration within needed can be stated in the contracts - is lawful) some taxes and at the same
which payment must be made; upfront. Circumstances of the paying time evaded (which is unlawful) some
and party can be incorporated eg. internal tax cannot be said to be a company of
accounting procedures, audit integrity. One is either pregnant or not
(ii) the timeliness of payment. procedures and even management pregnant. One cannot be ‘partly
bureaucracy. The party bidding for the pregnant’ nor have ‘situational
The actual time within which payment contract can then price accordingly. pregnancy’. In the same way one either
must be made is the duration eg. 30 Example, if the contract states payment has integrity or doesn’t. Situational
days or 60 days given, within which is due within 90 days from the date of integrity usually means no integrity.
payment must be made. certification on a particular project
compared to a typical 30 day due ● Project Delays, Reduced Profitability
Timeliness on the other hand refers to period, the bidder can plan and price and Possible Liquidation
the punctuality of payment. for the long period through extra
facilities such as overdraft knowing well A failure on timely payment also affects
Example. if a contract specifies upfront the longer period for payment programmes which are pre-planned.
payment within 30 days, payment due. In some cases the bidder may This affects cash flow which in turn can
must be made within 30 days. If the even opt not to tender if the period is affect progress of the works and
contract specifies payment within 14 unacceptable. profitability. In bad cases as has
days or 6 months then payment is due happened in other countries such as the
within the 14 days or 6 months Timeliness United Kingdom, Australia, New
respectively. Zealand and Singapore, many
Failure on timeliness on the other hand companies facing unplanned cashflow
If a contract stipulates payment within has wide ranging implications. problems ended up in liquidation. In
90 days and payment is made in 80 the UK, between 1989 and 1994, over
days payment can be said to be timely. ● Integrity 35,000 businesses and companies
But in a contract which stipulates became insolvent with almost half a
payment within 60 days, if payment is A failure to pay within the time million jobs lost. That and the Latham
made in 80 days, payment is not timely. stipulated is a breach of promise – a Report eventually resulted in the
compromise on business ethics. drafting of the UK Act.
Both, actual time for payment and Studies on leadership consistently
timeliness are important. But identify integrity as among the top In New Zealand, insolvencies specifically
between the two, consistent timely traits of leaders. A person of integrity in the construction industry since 1998
payment is more important. There are does not breach promises. The included names spread throughout the
two reasons for this. First, because Malaysian construction industry has country such as David Brown
planned cash flow is critical to a set its target to be ‘among the best in the Construction, Auckland, Voss
business, par ticularly in the world’. To be among the best means to Construction, Wellington, Replica
construction industry. And secondly, be a leader in the world. Homes, Christchurch and several others

3 r d Q u a r t e r 2 0 0 6
C over Story

such as Campbell Construction, Equinox minds are the ‘safety collapse’ case of Dr Addressing The Vision – A Two
Construction and Hartner Construction. Liew in Sri Hartamas, Kuala Lumpur, and Pronged Approach
Earlier, major insolvencies included the gory reminder of the Highlands
McMillan & Lockwood Ltd and Angus Towers case – a ‘quality collapse’. The Nine years may seem a long time to
Construction. These were followed by Malaysian construction industry could achieve the stated vision. But it is not.
consequential failures of large numbers do without a ‘financial collapse’ as was To achieve this vision, a two pronged
of subcontractors. These events the case in many other countries. approach is recommended:
prompted serious action which
eventually resulted in the drafting and I have highlighted these reminders, the 1. A fundamental change in the
enactment of the New Zealand re-action in other countries and how we, mindset towards timely payment.
Construction Contracts Act 2002. in Malaysia, should be ‘pro-active’ in our This can partly be achieved
actions and avoid any potential through self realization of concepts
Thus, a failure on timely payment can ‘financial collapse’ at various forums such as present buzz words like
result in project delays, reduced including briefings mostly organized by ‘good corporate governance’, or
profitability and can even lead to the Construction Industry through concepts I have stated
companies going into liquidation. None Development Board (which comes earlier in this paper such as
of these effects should be present at any under the purview of the Ministry of realization of ‘situational integrity’
significant levels if an industry is to be Works) to captains of industry, or ‘partial integrity’ and its analogy
‘among the best in the world’. Currently it professional bodies, trade of being ‘part pregnant’; and
is common for construction projects in organizations, academic institutions,
Malaysia to be late. Some of the reasons federal and state government ministries 2. Statutory enactment to give
for the delay can be attributed to and departments and the Attorney- enough bite, particularly in the
delayed payment. We have only nine General’s chambers. In my capacity as short to medium term and in cases
years to go before 2015. Much work President of the Institution of Surveyors where there are chronic problems.
needs to be done over the next nine Malaysia, I similarly highlighted these
years – if we are to move towards reminders at the 2005 annual dialogue This paper covers the second prong
substantially eliminating payment with the Honorable Minister of Trade rather than the first – although I would
default. Tall order. But not impossible. and Industry and the annual budget recommend the first be also taken up,
dialogue chaired by the Right possibly at other forums.
‘Some men see things as they are and say Honorable Prime Minister in the
why. I dream things that never were and presence of the Honorable Finance Although the first is the preferred
say why not.’ Robert F Kennedy, Minister II and all other Ministry method in a mature society, to achieve
paraphrasing George Bernard Shaw. representatives. My request was for the vision within nine years, the stick
timely support of the proposed Act. method (such as through statutory
Many in the construction industry see After all the wise learn from other provisions) is also needed. Here is an
and often themselves suffer the effects people’s mistakes. analogy. The tax laws in Malaysia have
of payment default and keep moaning now been amended assuming a more
about the problem – sometimes giving mature society where everyone is
reasons for the problem. What we must responsible enough to self-assess their
do is to envision a dream like ‘payment own taxes and declare and pay all taxes
in the construction industry is timely’ - due. But the tax department too knows
where everyone in the construction the ‘stick’ method must complement
industry pays the appropriate amounts the ‘mature’ method. Hence the
due in a timely manner. Thus dreaming warning that their officers will conduct
of things even if it may appear idealistic random checks!
and maintain the stand ‘why not.’ After
all the construction industry masterplan A Malaysian ‘Construction
does speak of being ‘world class’. Industry Payment and
Adjudication Act’
When I speak to people in the industry
about the WG 10 long term vision of Support for a Malaysian ‘Construction
2015, I keep hearing a common lament Industry Payment and Adjudication Act’
– ‘I hope that is not too late.’ Fresh in their by the construction industry players has

3 r d Q u a r t e r 2 0 0 6
C over Story

been overwhelming. And MBAM has success. And ideally there must be This can be an issue in one-off
been a consistent major supporter and consensus. The construction industry contracts typical on smaller projects
contributor to the refinement of the has supported it overwhelmingly so far and in the large number of sub-
conceptual proposals. – although certain aspects of security contracts and sub-sub-contracts
for payment suited to Malaysia is yet to where the main contractor selects his
The next question to be considered is be agreed consensually. own sub-contractor – generally
how our version of a model referred to as ‘domestic’ sub-
‘Construction Industry Payment and Contents of a Construction contractors. A typical statutory
Adjudication Act’ should be. Should we Industry Payment and provision would provide for a default
just adopt any one of the models Adjudication Act mechanism if a construction contract
already developed around the world? does not provide for a payment
Or is our situation different such that we Typically the relevant acts around the mechanism.
cannot accept these models ‘lock, stock world cover various common aspects
and barrel’. Should we have something including the following. These are The intentions in the proposals for the
that is better than the current best? considered in some detail below: Malaysian Act are clear. The parties to
a construction contract are free to
We have in the past adopted the UK ● A scheme for regular payment agree terms of payment – whether
JCT 63 building contract lock, stock and where there is no provision for a payment in 30 days or even 100 days
nearly all barrels. We renamed it the payment mechanism in a of certification, milestone payments, a
PAM 69 contract. And despite serious construction contract. I repeat – single bullet payment on completion
judicial criticism we ‘lived with it’ for ‘where there is no provision for a or even payment in kind. Much of the
nearly thirty years! The vast majority of payment mechanism in a concept of freedom of contract is
Malaysian society, not being a litigious construction contract.’ preserved. The default mechanism for
one, did not directly face the ● Outlawing ‘pay-when-paid’ and ‘pay- regular payment is only for cases
consequences of the shortfalls of the if-paid’ clauses in construction where there is no payment mechanism
contract. But ask the few who did end contracts provided in the contract.
up in court. They will clearly say ● The rights for a party who has not
reforms to the contract must be made been paid to suspend works This clearly is a sensible provision and
and ought to have been made much ● The provision of a speedy dispute one that will avoid uncertainty on
earlier. Ignorance is not bliss. Just resolution process called payment provisions.
because there were few cases on PAM adjudication for disputes relating to
69 in Malaysia does not mean the a construction contract Outlawing ‘pay-when-paid’ and ‘pay-
contract was ‘ok’. It required the efforts ● The provision of remedies for the if-paid’ clauses in construction
of only a few – commissioned by recovery and security of payment contracts
Pertubuhan Akitek Malaysia - to make under a construction contract
the transformation to what is now the None of the nominated sub-contracts
PAM 98 contract and possibly and These are some of the major issues published in Malaysia including under
hopefully soon the 2006 or 2007 that have been debated by the the PAM 69, PAM 98, PWD 203 series, IEM
edition. industry at length for inclusion in the or CIDB 2000 contracts contain a ‘pay-
proposed Malaysian Act. In addition, when-paid’ or ‘pay-if-paid’ clause. They
Few people are all that is needed to statutorily providing the right to all have ‘pay-when-certified’ clauses. In
initiate the move for the construction interest on late payment has also other words payment must be made by
industry to achieve its 2015 vision of been suggested. the main contractor upon certification
being ‘world class’. Likewise for WG 10 by the certifier whether or not the main
to achieve its vision of: I now briefly consider some of the contractor is paid in a timely manner as
areas that may be covered in the provided under the main contract.
Everyone in the construction proposed Malaysian Act and how they
industry pays all appropriate may help towards eliminating But many contractor-drafted ‘domestic’
amounts due in a timely manner. payment default: sub-contracts or sub-sub-contracts
contain ‘pay-when-paid’ or ‘pay-if-paid’
Although only a few people are A scheme for payment where there is provisions. ‘Domestic’ sub-contracts are
needed to initiate the change, the no provision for progress payment in contracts which a contractor enters into
masses must support it to make it a a construction contract with a sub-contractor chosen by the

10

3 r d Q u a r t e r 2 0 0 6
C over Story

contractor. The only standard terms of logic behind the UK Act excluding such recommended to be outlawed, there is
‘domestic’ sub-contact published in protection in the event of insolvency is one other ‘conditional payment’
Malaysia – the ‘Model Terms of that the main contractor is in a better provision worthy of attention.
Construction Contract for Subcontract position to be able to ascertain the Recommendations have also been
Work’ published in September 2006 financial credentials of the client with made in Malaysia for outlawing
does not have a ‘pay-when-paid’ or ‘pay- whom the contractor contracted. payments which are conditional upon
if-paid’ provision. ‘other arrangements’ eg conditional
Although my earlier views were open upon availability of funds or drawdown
Pay-when-paid clauses are those on whether to outlaw such provisions, of financing facilities. Eg a client
clauses which defer the time when on balance, it now appears clear that like organisation providing for payment to
payment is due from say a main in other countries, these provisions a contractor being conditional upon
contractor to a sub-contractor until the must be outlawed for the Act to be there being say a minimum balance of
main contractor has received payment effective as a whole. RM 2 million in the bank or other
from the client. Pay-if-paid accounts. I know that such
clauses are clauses which provisions do exist in industry
attempt to exclude even the now.
liability for payment to a sub-
contractor until the main Payments conditional upon
contractor is paid. an architec t, engineer,
superintending officer, or
The effect of such clauses is that contract administrator’s
sub-contractors may well end up certificate must not however be
not being paid for reasons outlawed. This is because these
beyond their control. Worse still certifiers are expected to certify
is a situation where a client may fairly irrespective of their
set off amounts due to a main employer. In any case the
contractor due to the main adjudication provisions
contractor’s own fault. The sub- recommended for the proposed
contractor then does not get Act will be a check on any
paid although they may have unreasonable conduct by the
done their work properly and certifier contemporaneously.
were not in breach of their
contract. The rights of a party who has
not been paid to suspend works
All the similar Acts around the
world typically effectively outlaw pay- This is a typical right provided in other
when-paid and pay-if-paid provisions. Consider also a client organization that statutory provisions around the world
They may not be worded such that such awards a construction contract to a dealing with payment and
provisions are ‘banned’, but the effects company within its own group and adjudication. The right to suspend
of the wordings are such that such which is then sub-contracted out. A work is not provided in common law.
provisions are ‘effectively prohibited’. Eg pay-if-paid clause if not outlawed can See eg. Canterbury Pipe Lines Ltd v
Section 13 of the NZ Act states that a then be used as an excuse for not Christchurch Drainage Board [1979] 2
‘conditional payment provision of a paying the sub-contractor (an outside NZLR 347 (CA) and Lubenham Fidelities
construction contract has no legal effect’ party) who actually does the work. & Investments Co Ltd v South
and ‘is not enforceable in any civil Pembrokeshire District Council (1986) 33
proceedings’. Similar provisions are It may be timely to remind ourselves BLR 39. Newer standard terms of
found in the UK Act and the New South ‘cash flow is the life blood of the construction contracts tend to provide
Wales, Victorian, Queensland, Western construction industry.’ an express right to suspend works
Australian, Northern Territory and following non payment. Eg the CIDB
Singaporean Acts. A limited exception Whilst pay-when-paid and pay-if-paid Standard Form of Building Contract
is made in the UK Act allowing pay- provisions in construction contracts are 2000 and possibly the 2006 or 2007
when-paid provisions in situations known and are becoming increasingly amendments to the PAM Standard
when a client becomes insolvent. The common, and these have been Form of Building Contract 1998. The

11

3 r d Q u a r t e r 2 0 0 6
C over Story

PAM nominated sub-contract standard comparison of some salient features serious attention as methods of
terms have however always had a comparing litigation, arbitration, resolving construction disputes –
provision for the sub-contractor to adjudication and mediation on a typical complemented with the opportunity
suspend works. Strangely, a similar construction dispute. for eventual ‘fine justice’ in an
provision was never correspondingly arbitration, if the parties still need it.
provided in the main contract. *Tribunal cost means the costs
associated with the sitting tribunal eg Like in arbitration, in adjudication an
The necessity for such rights to be court fees, arbitrator’s, adjudicator’s or independent adjudicator who is
conferred statutorily arises because not mediator’s fees and the cost of venue, if appointed steps in and makes a binding
all construction work is undertaken any. The amounts shown are only an decision based on the evidence, facts
using published standard terms of estimated indicative range. and the law. The decision binds the
contract. parties to the contract immediately
**Parties’ cost means costs (again an upon getting the decision from the
Typically the Acts confer an automatic estimated indicative range) that the adjudicator but unlike the ‘finality’ of an
right to extension of time to the parties may incur eg. costs of employing arbitrator’s award the same dispute
contractor who rightfully suspends lawyers, claims consultants or other referred to in adjudication may be
work following non-payment. This right experts. But it excludes other internal opened up again in an arbitration
will of course cease when payment is costs eg. costs associated with the following the provisions in the contract.
finally made. parties’ time spent in preparing for the In construction contracts, for most
case, time spent at hearings or costs disputes that typically means following
The recommendation to date for the involved in preparing documentation completion or termination. The UK
Malaysian Act is for the right to suspend or travel costs. experience shows though that the vast
work to be conferred only following an majority of disputes referred to
adjudicator’s decision. ***Duration: This is an indication of the adjudications are not subsequently
estimated indicative time usually opened up in arbitration.
The provision of a speedy dispute required for a typical construction
resolution process (adjudication) for dispute from the start of the process eg Unlike arbitration, the adjudication
disputes relating to a construction one party writing to the other stating processes provided statutorily around
contract there is a dispute and suggesting it be the world are time limited. The duration
resolved in an arbitration or is typically statutorily set at 14 days, 20
Traditionally disputes in the adjudication or through mediation working or business days, 30 working or
construction industry have been through to a judgment, award, decision business days, 28 days or 42 days. Only
resolved through arbitration – or settlement agreement. if the parties agree, these durations may
whenever negotiations could not be extended. Rough justice – maybe,
conclude a disagreement which has I have always held the view that various given the short period for the dispute to
become a dispute. Theoretically, and dispute resolution methods must co- be resolved - but it can, and often is
the intent of arbitration was for a fast exist to complement each other to suit resolved contemporaneously (meaning
and economical, binding private the nature of dispute and the when the dispute occurs). Unlike a
dispute resolution mechanism. The circumstances of each case. But it typical arbitration which can usually
reality based on experience is rather becomes increasingly important for only start after completion of works or
different. Rarely will you find an construction disputes to be settled: after termination. And which often
arbitration on a construction dispute results in delayed justice – which some
being completed from the start of a ● Speedily; say is justice denied.
dispute to a final arbitrator’s award in ● Economically;
under a year. A typical arbitration on ● In a binding manner; In the UK more than 15,000
disputes in the construction industry ● Contemporaneously ie when it adjudications have been held since
(from referring a dispute to an appointing happens as opposed to years later; 1998. Over the corresponding period,
body through to getting an award from and the number of arbitrations has dropped
an arbitrator) could take anything from ● Wherever possible for good significantly. So has the number of
over a year to a few years and sometimes relationship to be maintained. cases in the Technology and
even more than 5 years. Construction Construction Court ( TCC) which
disputes in court usually take longer. The Based on the above considerations, handles construction cases. I would not
table below is an estimated indicative mediation and adjudication merit state that the sole reason for the decline

12

3 r d Q u a r t e r 2 0 0 6
C over Story

Table comparing salient features of litigation, arbitration, adjudication and mediation for a typical construction dispute

STATUTORILY
DESCRIPTION LITIGATION ARBITRATION PROVIDED MEDIATION
ADJUDICATON

Basis of resolution Rights based; based on Rights based; based on Rights based; based on Interest based; need
of dispute facts, evidence and law facts, evidence and law facts, evidence and law not be based on
facts, evidence or
law. Parties may
agree anything (that
is lawful)

Tribunal cost* (RM) 5K 50 K – 300 K 10 K – 50 K 2 K – 15 K

Parties’ costs – both 100 K – 600 K 100 K – 500 K 50 K - 100 K 10 K – 20 K


sides** (RM)

Duration*** 2 - 7 years 1 - 5 years 4 - 8 weeks 1 - 14 days

Rights to the Usually right to May only resort to With an enabling Act, Mediation can
process and pre- litigation precluded if arbitration if there is a adjudication would always be used by
conditions there is an arbitration written arbitration usually be permitted at the parties at any
clause in the contract, agreement in the any time time
but may be used to contract or if agreed by
challenge an the parties at any time
arbitrator’s award
although only on very
limited grounds

Timing If there is no arbitration Usually in construction Anytime Anytime


clause, anytime. If there contracts arbitration
is an arbitration clause, clauses provide that
only if an arbitrator’s arbitrations on most
award is being disputes may only start
challenged which may after completion or
be done only on very termination
limited grounds

Extent to which it Binding, but may be Binding, but the Binding but the same Not binding at any
may be binding and appealed to a higher arbitrator’s award may dispute may be time during the
appealed court be challenged in court reopened in process, except when
although in very arbitration/litigation settlement
limited circumstances agreement is reached

Relationship Usually confrontational Often quite May be a little Usually amicable


between disputing confrontational confrontational
parties

in arbitrations or the cases in the TCC are ‘traditional dispute resolution industry’? decide whether the potential effect of
solely because disputes are increasingly All true professionals know that an introducing adjudication in the
being resolved through adjudication or essential trait of a professional (and the construction industry would be in the
possibly mediation. But what I would say basis upon which professionals get the best interest of society and the economy
is there is at least anecdotal evidence authority to act – sometimes statutorily as a whole.
that, as a minimum, the introduction of and often to the exclusion of the public
adjudication could be partly the reason. at large) is altruism – putting client’s and So far the number of cases in court
If so, isn’t that bad news for the society’s interest before self interest. You relating to adjudication that I am aware

13

3 r d Q u a r t e r 2 0 0 6
C over Story

of are 256 in the UK, 110 in Australia most enter the adjudicator’s determination as At the time of my writing this, the
of which (93) are in New South Wales and a judgment in the District Court. recommendations by the steering
3 in New Zealand. I am aware of one in committee on the proposed
Malaysia. One party alleged I was On security for payment, unlike most ‘Construction Industry Payment and
properly appointed as an ‘adjudicator’ as other countries, the Malaysian scenario is Adjudication’ are for a payment bond
defined in their contract. The other party somewhat different. Malaysia operates to be mandated, but only at head
challenged my jurisdiction and the substantially on a sell-on-plan scheme. contract level. This was seen as a
appointing body’s right to appoint me. That means purchasers and end financiers compromise to avoid excessive cost
Thankfully, it was settled before it would be involved early on in the increase.
proceeded to hearing! development. Any attempt to provide
security for payment to a contractor, There have also been other ‘creative’
The number of cases might sound like subcontractor or supplier through a lien suggestions eg. by REHDA on the
many, but compared to over 15,000 or charging order scheme might not be in possibility of creating a ‘contractor’s
adjudications done to date 369 cases the best public interest and of many of the project account’. But this has yet to be
around the world is considered very few. parties – particularly the purchasers. explored in detail.
Further, and very importantly, many of
the cases were dealing with tangential According to Sr Lim Chong Fong, a Other Payments
issues such as jurisdiction of the practicing construction lawyer with a
adjudicator (including the one in background in quantity surveying and I have one last point on payment to be
Malaysia) and not just on issues relating who has done much research into this made. I have simply called it ‘other
to the dispute itself. Indeed even after 8 aspect of the proposal for the Act, payments’. I wish to re-visit my points
years and over 15,000 adjudications, two provisions through a mandatory trust on integrity and ‘situational integrity’.
of the most recent cases in the UK fund too have their shortfalls in Malaysia As I wrote earlier, one is either a person
Redworth Construction Limited v because tracking of funds movement of integrity or not.
Brookdale Healthcare Limited [2006] would remain a problem given the
EWHC 1994, 31 July 2006 and Harlow & various existing laws in Malaysia. That If we expect everyone to pay the full
Milner Ltd v Mrs Linda Teasdale [2006] leaves a third way to obtain security for sums due in a timely manner, we
EWHC 1708, 7 July 2006 both had payment in the construction industry - a should also pay those who we owe all
jurisdiction as a key issue. system of payment bonds, Sr Lim Chong amounts due in a timely manner.
Fong suggests is the best way to have Ideally, upon the due date - whether
The provision of remedies for the some security for payment. demanded or not. They include the
recovery of payments under a newspaper man, milkman (if they still
construction contract So far, providing a mandated system of exist) IWK, TNB, TM, government service
payment bonds has not had consensus tax and other taxes. And for
In order to give ‘teeth’ to the statutory within the construction industry. It is professionals it includes paying all
provisions, there must be provisions for also evident that having a professional subscriptions within the
remedies for the recovery of payment comprehensive scheme of bonds all the deadlines – even if one has shifted
following a decision or determination of way from the client to main contractor houses and addresses have not been
an adjudicator. These are provided in to subcontractors to sub subcontractors updated!
various ways depending on the and suppliers is likely to result in
jurisdiction. In the UK it is provided reciprocal insistence of having Physical infrastructure is but only a part
through enforcing the adjudicator’s performance bonds or performance of a fully developed nation. In the long
decision under s 42 of the Arbitration Act security deposits or retentions sums or run personal integrity must be all-
1996. Under the NSW and Victorian Acts, a combination of some of these security encompassing if we are to achieve the
apart from a right to suspend works, it is for performance all the way down the vision of:
recovered as a debt. The NSW Act has a chain of contracts. It was generally felt (i) Everyone in the construction
procedure to obtain an ‘adjudication that then, the increase in costs due to industry paying all appropriate
certificate’ which can then be filed ‘as a banking charges involved in providing amounts due in a timely manner;
judgment for debt in any court of a plethora of payment and performance and
competent jurisdiction.’ Similarly the NZ bonds would not be commensurate (ii) Making the Malaysian construction
Act provides for the right to suspend with the benefit of security of payment industry world class by 2015; and
works, to recover the adjudicator’s through a statutorily mandated bond (iii) Malaysia becoming a fully
determination as a debt in court and to system within Malaysia. developed nation by 2020. MBJ

14

3 r d Q u a r t e r 2 0 0 6

You might also like