You are on page 1of 16

1 Modernization: Economic Benefits | Greater Efficiency | Jobs | Sustainable Energy | Improved Air Quality

slide 1 of 16
Agenda

  Introductions
  Project Description
  Facilities Retained
  Wet to Dry Process
  Key Areas Examined
in DEIS
  Schedule

www.lafargeravenafacts.com

2
slide 2 of 16
Lafarge Team

  Martin Turecky, Lafarge


Plant Manager, Ravena Plant

  John Reagan, Lafarge


Environmental Manager,
Ravena Plant

  Bill Voshell, Lafarge


Regional Environmental Manager

  Marc Desimone, Lafarge


Engineering Manager
  Elena Barnett, HDR
Vice President
  Jim Brown, HDR
Senior Vice President

3
slide 3 of 16
The Ravena Process
Today: Wet Process

Wet Process
(1950-60’s Technology)
  Raw materials are mixed with water and
ground in slurry mills. Slurry is stored and
homogenized in large slurry basins.
  Slurry mixture is fed directly to the kiln
without preheating.
  A large amount of extra fuel is used in
evaporating the water.
  A larger kiln is needed, because much of the
kiln’s length is used up for the drying proces.
  In 1962, the Ravena cement plant’s nearly
600-foot long kiln was the largest piece of
moving industrial equipment in the world.

4
slide 4 of 16
The Ravena Process
Tomorrow: Dry Process

Dry Process
Pre-heater/pre-calciner kiln line
(State-of-the-art Technology)
  Raw materials are ground, mixed, and fed to a
kiln in a dry state. Ground dry material is
preheated in a preheater tower.
  The preheater tower is a tall vertical structure in   Reduced process waste.
which the dry kiln feed enters at the top of the
tower and is heated by kiln exhaust gas entering   ZERO process wastewater discharges through
at the bottom of the tower. re-use and recycling.

  Preheating of the ground dry material prior to   Minimization of Impacts to Hudson River:
entering the kiln results in substantial energy •  Achieves objectives of Hudson River
savings compared to the energy required to heat Estuary Program.
the wet slurry mixture.
•  Flow minimization through reuse/recycle
  The Rotary kiln length of approximately 200 ft. is of wastewater and use of non-Hudson
much shorter than the wet kilns. River water sources.
  New emissions control technology includes: •  DEC approved best technology available
scrubber, SNCR, state-of-the-art dust collectors for water intake from the Hudson River
and CEMS. to minimize impacts to
aquatic organisms.

5
slide 5 of 16
Facilities

Facilities Retained Facilities Removed


  Quarry facilities   Raw Mills (2)
  Conveyors   Coal Mills (2)
  Administration building   Slurry Basins (2)
  Laboratory   Kilns (2)
  Maintenance facilities   Electrostatic
  Cement Storage Silos Precipitator Building

  Wharf facilities   Clinker Coolers (2)


  Most supporting infrastructure   Associated drives, fans
and ancillary equipment
  Stack

6
slide 6 of 16
New Facilities

Phase l
  Secondary crusher   Scrubber
  Raw mill storage bins   SNCR—selective non-
  Raw mill catalytic reduction
  Alkali bypass   Baghouse dust collectors
  Coal mill   Fans, drives and ancillary equipment
  Prehemogenization silo   Continuous Emissions Monitors
(CEMs): NOx, SO2, PM, Hg, CO/CO2,
  Kiln
THC and HCl
  Preheater precalciner tower
  Clinker cooler

Phase ll
  Power generating system
  Finish mill
  Clinker storage Ravena’s Quarry
  Preblending system

7
slide 7 of 16
Wet vs. Dry

Raw Milling
  Horizontal configuration to vertical
  Same raw materials except water

8
slide 8 of 16
Wet vs. Dry

Kiln Feed Storage


  Dry storage silo
  12 hour storage
  Extraction and transport of powder

9
slide 9 of 16
Wet vs. Dry

Wet Process Dry Process

10
slide 10 of 16
Lafarge Ravena Plant
Proposed Plant Modernization Project

Key Areas Examined


  Land Use and Zoning
  Solid Waste
  Noise
  Traffic
  Visual Impact
  Water and Coastal
Resources
  Natural Resources
  Socioeconomic
  Air Quality
  Energy Resources

11
slide 11 of 16
DEIS: Water, Energy & Waste
Comparison: Modernized Facility & Existing Plant

12
slide 12 of 16
Existing vs. New Plant
Emissions from modernized plant compared to existing plant

13
slide 13 of 16
The Future
Modernization Project Timeline

State-of-the-Art New Facility

14
slide 14 of 16
Modernization Benefits

15
slide 15 of 16
Lafarge Ravena Plant Modernization Project
Information and Updates

Learn more and get project updates online at:


lafargeravenafacts.com

16
slide 16 of 16

You might also like