Professional Documents
Culture Documents
lining works
Refractory
PR RFR P07 27 V1.0 1/6
Introduction
The purpose of this guideline is to recognize the specific hazards related to cyclone lining work and to
outline the necessary requirements for this type of work.
The following risks need to be addressed:
burn and dust inhalation during inspection
Inhalation of dust and dust in eyes during de-bricking and demolishing of castable in confined
space.
Refractory, coating & concrete panels (corroded anchors) may fall.
Air blasters, air lancing nozzles
Radioactive level detection
Work at height, trip and slips.
Confined space
Blocked escape routes
Such hazards can be eliminated or controlled by appropriate prevention measures, but sometimes, not
completely.
This guideline is applicable to all the employees and contractors of Lafarge.
Prerequisites
Before kiln stops, extensive automatic and/or manual cleaning has to be performed (air blasting, Cardox
shot, Woma guns…)
Gas temperature inside the cyclones and risers are to be brought down to reduce heat stress, according
to local regulations (about less than 50 deg C), before the inspection starts.
Hanging or loose coating and refractory are to be cleaned from outside using the access holes and
manhole doors. When it is not possible, contractor alpinists should be hired to clean downwards
The appropriate work permit must be obtained before scaffolding activities are allowed inside the
confined area
Scaffolding inside the cyclone and risers is carried out by a recognised contractor or trained workers, who
is well aware of our work at height guideline and scaffolding guideline. Provisions should be made to
allow heavy blocks to fall down on to the platform (re-enforced platform at work level).
Demolition workers should be registered and certified by the employer.
All rights of reproduction, representation, adaptation and translation relating to this report belong to Lafarge SA. Lafarge SA reserves the right to exploit this
report or not and to freely distribute it to all of its current and future subsidiaries worldwide in any form, whether paper, electronic or digital, including via Procedure Template developed by
internet and/or intranet. This report along with its content is of a confidential nature. In particular, it may not be reproduced, copied, transmitted, published,
divulged and/or appropriated in whole or in part for personal use or for use by a third party without prior consent from the Production & Process Department,
except for reproduction by or for affiliated Lafarge companies.
How to ensure safety for cyclone
lining works
Refractory
PR RFR P07 27 V1.0 2/6
Basic rules
1. General
Ensure that personal protective equipment are worn, including a dust, fumes mask (P3 type) and safety
harness.
1.4 Lighting
Sufficient lighting must be provided to ensure a safe work environment.
How to ensure safety for cyclone
lining works
Refractory
PR RFR P07 27 V1.0 3/6
2. Specific
During coating and brick cleaning, release this mechanical lock but remove one small piece of feed pipe
in the bottom most cyclone feed pipes and close the entry to kiln inlet with a sliding gate made of ply
wood or steel plate. Cordon off the area with red tape.
Once cleaning in all stages is over, clean the debris and remove the red tape.
Reduce discharge height for safer removal of materials, as much as possible
Maintain escape ways and working areas clean at all times
During scaffolding and refractory installation, again isolate individual cyclones by locking the double flap
in closed position
In case the double flaps are removed for maintenance, install a sliding gate at the cyclone discharge.
How to ensure safety for cyclone
lining works
Refractory
PR RFR P07 27 V1.0 4/6
Pneumatic lock
The air blasters/ air cannons and the cyclical cleaning equipment serving all the cyclones must be locked
out (air and power). The system must be purged off their gas or air charge. Purge valves may be left
open.