Vegetal soil:
Foundation soil:
SAB := 5.60m
1. EARTH WORKS
01.01.Ts C 18 A1
Mechanical digging using a 65-80 Hp type bulldozer, including pushing of the soil up to
10m, in terrain of category I.
3 3
UM01.01 := 100m hundreds_m3 := 100m
2
hr hundreds_m2 := 100m
NTi01.01 := 2.21
3
100m
(
Round_V01.01 := Ceil V01.01 , 0.01hundreds_m3 )
Round_V01.01 = 1.81⋅ hundreds_m3 rounded volume of excavated soil
01.02. Ts C 22 A1
Extra-hours for the article Ts C 18, for the transportation of the vegetal layer of soil on
each extra 10m, over the estimated distance (using a bulldozer of 65-80 hp). The computed
volume of soil is multiplied by the swelling coefficient (coeficient de infoiere), 1.28 and by the
coefficient 2 ( 2*10m = (30m-10m )), for the carrying distance of 30m.
3
UM01.02 := 100m
hr
NTi01.02 := 1.33
3
100m
V01.02 := V01.01⋅ 1.28⋅ 2 = 4.6114⋅ hundreds_m3
(
Round_V01.02 := Ceil V01.02 , 0.01hundreds_m3 )
Round_V01.02 = 4.62⋅ hundreds_m3
01.03. Ts C 04 F1
Mechanical excavation using the chain-excavator of 0.71-1.25 m3, with internal combustion
engine and hydraulic command, in soil with natural humidity, with discharge in auto vehicle, in
terrain of category II.
*One computes the volume of the under-taken soil, until the protection masonry.
3
UM01.03 := 100m
hr
NTi01.03 := 1.35
3
100m
LSGI := 26.325m
lSGI := 13.668m
( )
V01.03 := LSGI − 0.6m − 0.6m ⋅ lSGI − 2( 0.6m + 0.2m + 0.3m) ⋅ hSGI = 3.7457⋅ hundreds_m3
(
Round_V01.03 := Ceil V01.03 , 0.01hundreds_m3 )
Round_V01.03 = 3.75⋅ hundreds_m3
01.04. Ts C 04 B1
Mechanical excavation with the chain-excavator of 0.71-1.25 m3, with internal combustion
engine and hydraulic command, in soil with natural humidity, with discharge in deposit, in terrain
of category II.
*One computes the volume of soil to be excavated and reused at the fillings after finishing
of the infrastructure.
3
UM01.04 := 100m
hr
NTi01.04 := 1.20
3
m
LSGI = 26.325 m
lSGI = 13.668 m
2
Ab := LSGI⋅ lSGI = 359.8101 m
VSG0 :=
1
(A + Ab +
3 B
)
AB⋅ Ab ⋅ hSGI = 5.2491⋅ hundreds_m3
or
LSGS + LSGI lSGS + lSGI
VSG := ⋅ ⋅ hSGI = 5.2489⋅ hundreds_m3
2 2
(
Round_V01.04 := Ceil V01.04 , 0.01hundreds_m3 )
Round_V01.04 = 1.51⋅ hundreds_m3
01.05. Ts E 01 B1
UM=100m2
NTi=8.82 hours/100m2
2
UM01.05 := 100m
(
Round_S01.05 := Ceil S01.05 , 0.01hundreds_m2 )
Round_S01.05 = 3.6⋅ hundreds_m2
01.06. Ts A 02 E1
Manual digging in narrow spaces, having under or over 1.00m width, done without vertical
bracing, at foundations, channels, drains, in middle terrain.
3
UM01.06 := 1m
hr
NTi01.06 := 1.19
3
m
Axis A: VA := ( LSGI − 2⋅ 0.6m) ⋅ 1.2m⋅ 0.4m + 4⋅ ( 0.1m + 0.3m) ⋅ 1.7m⋅ 0.4m = 13.148⋅ m3
Axis C: VC := VA = 13.148⋅ m3
Axis 5: V5 := V4 = 4.9181⋅ m3
01.07. Ts D 02 B1
Spreading the soil coming from terrain of first or second category, using the 65-80 hp
bulldozer, in layers with height of 21-30cm.
*One computes the volume of the space that needs to be filled (V01.04) and corrects it
using the swelling factor of 1.28.
3
UM01.07 := 100m
hr
NTi01.07 := 0.9
3
100m
V01.07 := V01.04⋅ 1.28 = 1.9241⋅ hundreds_m3
(
Round_V01.07 := Round V01.07 , 0.01hundreds_m3 )
Round_V01.07 = 1.92⋅ hundreds_m3
01.08. Ts D 05 B1
Mechanically ramming-up the fills in successive layers of 20-30cm height, with the ram of
150-200 kg, the fills being made of cohesive soil.
*One computes the geometric volume of the space to be filled (volume computed at article
01.04) .
3
UM01.08 := 100m
hr
NTi01.08 := 10.88
3
100m
V01.08 := V01.04 = 1.5032⋅ hundreds_m3
(
Round_V01.08 := Ceil V01.08 , 0.01hundreds_m3 )
Round_V01.08 = 1.51⋅ hundreds_m3
01.09. Ts D 01 B1
Spreading the soil in uniform layers of 10-30 cm height (using the shovel), including the
cracking of boulders.
*One compute the volume of soil to be spread between the pedestals and we must take into
account the swelling coefficient of 1.28.
3
UM01.09 := 1m
hr
NTi01.09 := 0.31
3
m
3
V01.09 := V01.06⋅ 1.28 = 91.5559⋅ m
Ramming-up the fills done in horizontal layers, having the slope up to 1/4, using the
manual ram, including the wetting of each layer in part, having the height of 20cm, in cohesive
soil.
*One determines the geometric volume of soil spread between the pedestals, by dividing
the soil volume computed at article 01.09 by the swelling coefficient, 1.28.
3
UM01.10 := 1m
hr
NTi01.10 := 0.66
3
m
V01.09
3
V01.10 := = 76.2966⋅ m
1.2
01.11. TRA 01 A 05 P
UM01.11 := 1ton
( )
ton
M01.11 := V01.03 + V01.06 − V01.09 ⋅ 1.9 = 673.6368⋅ ton
3
m
(
Round_M01.11 := Ceil M01.11 , 1ton )
Round_M01.11 = 674⋅ ton
2. FOUNDATION WORKS
02.01.C A 01 B
3
Casting the B50 concrete in continuous foundations of volume over 3m . One computes the
volume of concrete to be poured in the blocks of the continuous foundations.
3
UM02.01 := 1m
hr
NTi02.01 := 3.05
3
m
3
V02.01 := V01.06 = 71.528⋅ m
02.02. C B 10 B
Concrete formworks for bearings, glass foundations and foundations for simple machines
with regular form, including the bracing of reusable panels with plywood of 8mm.
* One determines the surface of the panels to be used for bearings.
2
UM02.02 := 1m
1hr
NTi02.02 :=
2
m
Axis C: SC := SA = 14.295 m2
Axis 3: S3 := S2
Axis 5: S5 := S4 = 5.6808 m2
Axis 6: S6 := S2
Axis 7: S7 := S2
Axis 8: S8 := S1 = 6.4008 m2
2
S02.02 := SA + SB + SC + S1 + S2 + S3 + S4 + S5 + S6 + S7 + S8 = 68.7282⋅ m
02.03. C A 02 C1
Pouring the B150 concrete in construction elements, excluding the ones done in sliding
formworks, in isolated foundations with volume over 3m3 and thickness up to 30cm..
3
UM02.03 := 1m
hr
NTi02.03 := 4.15
3
m
Axis A: VAa := 0.3m⋅ 0.8m( LSGI − 0.6m − 0.3m) + 0.2m⋅ 1.1m⋅ 0.3m⋅ 4 = 6.366⋅ m3
Axis B: VBa := 0.3m⋅ 0.8m( LSGI − 0.6m − 0.3m) + 2⋅ ( 0.7m⋅ 0.35m⋅ 0.3m) ⋅ 4 = 6.69⋅ m3
3
V02.03 := VAa + VBa + VCa + V1a + V4a + V5a + V8a = 28.4132⋅ m
Fixing the reinforcement steel OB37 and PC52 in the continuous foundations.
UM02.04 := 1kg
hr
NTi02.04 := 0.02
kg
kg
M02.04 := V02.03⋅ 60 = 1704.79 kg
3
m
(
Round_M02.04 := Ceil M02.04 , 5kg )
3
Round_M02.04 = 1.705 × 10 kg
02.05. C Z 01 02 G
hr
NTi02.05 := 0.085
3
m
3
V02.05 := V02.01⋅ 1.008 = 72.1002⋅ m
02.06. C Z 01 05 C
Preparing the B150 concrete, with heavy aggregates having the granulometry up to
31mm and prepared with M30 cement in centralized installations.
3
UM02.06 := 1m
hr
NTi02.06 := 0.085
3
m
3
V02.06 := V02.03⋅ 1.008 = 28.6405⋅ m
UM02.07 := 1kg
hr
NTi02.07 := 0.033
kg
M02.07 := M02.04⋅ 0.4⋅ 1.01 = 688.74 kg
(
Round_M02.07 := Ceil M02.07 , 1kg )
Round_M02.07 = 689⋅ kg
02.08. C Z 03 01 B
(
Round_M02.08 := Ceil M02.08 , 1kg )
Round_M02.08 = 1034⋅ kg
02.09. TRA 06 A 05
UM02.09 := 1tonne
ton
M02.09 := V02.05⋅ 2.4 = 156.98⋅ tonne
3
m
(
Round_M02.09 := Ceil M02.09 , 0.1tonne ) Round_M02.09 = 157⋅ tonne
02.10. TRA 06 A 05
Transportation of the B150 concrete with the traveling concrete mixer on a 5 km distance
*One computes the mass of B150 concrete necessary to prepare the continuous
foundations by multiplying the volume of concrete prepare at article 02.06 with the
specific weight of concrete.
UM02.10 := 1tonne
tonne
M02.10 := V02.06⋅ 2.4 = 68.737⋅ tonne
3
m
(
Round_M02.10 := Ceil M02.10 , 0.1tonne ) Round_M02.10 = 68.8⋅ tonne
02.11. TRA 04 A 05
M02.11 :=
( M02.07 + M02.08) = 1.705⋅ tonne
1.01
(
Round_M02.11 := Ceil M02.11 , 0.01tonne )
Round_M02.11 = 1.71⋅ tonne
3. BASEMENT STRUCTURE
03.01. C B 12 I
hr
NTi03.01 := 0.88
2
m
Hb := 1.93m + 0.1m = 2.03 m height of the basement
twb := 20cm thickness of basement wall
Axis A: SAb := 2( LSGI − 0.6m − 0.6m) ⋅ Hb = 102.0075⋅ m2
S03.01 := SAb + SBb + SCb + S1b + S2b + S3b + S4b + S5b + S6b + S7b + S8b
2
S03.01 = 518.0293 m
Formworks in black metal sheet, for creating the voids in concrete walls. One determines
the voids' surface in the walls.
2
UM03.02 := 1m
hr
NTi03.02 := 0.45
2
m
2
S03.02 := 2⋅ 0.9m⋅ 1.54m + 9⋅ 0.9m⋅ 1.33m = 13.545 m
03.03. C A 02 G
Pouring the reinforced concrete in construction elements, excluding the ones executed in
sliding formworks,mark B200, at construction with the height up to 35m,including the walls and
diaphragms with thickness up to 30cm .
* One compute the volume of concrete to be poured in diaphragms and walls, taking into
acount the existing voids.
3
UM03.03 := 1m
* S03.01 3
hr V03.05. := − S03.02 ⋅ twb = 49.0939⋅ m
NTi03.03 := 4.04 2
3
m
Axis A:
( )
VAb := LSGI − 0.6m − 0.6m ⋅ Hb⋅ 0.2m = 10.2007⋅ m
3
Axis B:
( )
VBb := LSGI − 0.6m − 0.6m ⋅ Hb⋅ 0.2m − 3⋅ ( 0.9m⋅ 1.33m⋅ 0.2m) = 9.4825⋅ m
3
Axis C:
( )
VCb := LSGI − 0.6m − 0.6m ⋅ Hb⋅ 0.2m − 3⋅ ( 0.9m⋅ 1.33m⋅ 0.2m) = 9.4825⋅ m
3
Axis 4: V4b := 0.2m( lSGI − 2⋅ 0.6m − 2⋅ 0.5m) ⋅ Hb − 0.9m⋅ 0.2m⋅ ( 1.33m⋅ 2) = 4.1772⋅ m3
2
V4b = 4.1772 m⋅ m
V03.03 := VAb + VBb + VCb + V1b + V2b + V3b + V4b + V5b + V6b + V7b + V8b
3
V03.03 = 51.7327⋅ m
03.04. C C 02 B
UM03.04 := 1kg
hr
NTi03.04 := 0.048
kg
kg
M03.04 := V03.03⋅ 50 = 2586.64 kg
3
m
(
Round_M03.04 := Ceil M03.04 , 5kg )
Round_M03.04 = 2590 kg
03.05.C C 02 B
Fixing the PC52 reinforcement bars. having the diametere of 10-12 mm in construction
elements, excluding the ones casted in sliding formworks, with polymer spacers. It results a
consumption up to 30kg of reinforcement to each cubic meter poured in diaphragms and walls.
UM03.05 := 1kg
hr
NTi03.05 := 0.41
3
m
kg 3
M03.05 := V03.03⋅ 30 = 1.552 × 10 kg
3
m
(
Round_M03.05 := Ceil M03.05 , 0.1kg )
Round_M03.05 = 1552⋅ kg
03.06. C A 02 J
2 piece := 1
UM03.06 := 1m
hr
NTi03.06 := 3.54
2
m
V03.06 := [ 2⋅ 0.13m⋅ ( 10.5m⋅ 5.494m + 10.5m⋅ 5.574m) + 0.13m⋅ 4.9m⋅ ( 5.494m + 5.574m) ] ...
+ 4⋅ 0.5m⋅ 0.25m⋅ ( 5.574m − 0.805m) + 4⋅ 0.5m⋅ 0.25m⋅ ( 5.494m − 0.2m − 0.605m) ...
+ 2⋅ 0.13m⋅ 0.15m⋅ ( 26.7m + 11.47m)
3
V03.06 = 43.4836⋅ m
hr
NTi03.07 := 0.85
2
m
2
S03.07 = 393.2031 m
03.08. C B 45 B
Metalic extensible trusses to sustain,for pouring the monolite beams, slabs and plates with
total amount of 500daN/m^2, at the construction having up to 20m height. In each cell will be put
3 beams sustained with extensible props and for each concrete beam will be put a metalic one
also sustained with 2 extensible props.
UM03.08 := 1⋅ piece
hr
NTi03.08 := 2.31
piece
(
Round_N03.08 := Ceil N03.08 , 1piece )
Round_N03.08 = 90⋅ piece
03.09. C C 02 C
Fixing the OB37 reinforcement bars having the diameter up to 10 mm in slabs and up to 18
mm in beams and columns, excluding the ones cast in sliding formworks, with polymeric spacers.
An amount of 50 kg of reinforcement is included in each cubic meter of concrete.
UM03.09 := 1kg
hr
NTi03.09 := 0.033
kg
kg
M03.09 := V03.06⋅ 50 = 2174.18 kg
3
m
(
Round_M03.09 := Ceil M03.09 , 1kg )
Round_M03.09 = 2175⋅ kg
03.10. C C 02 D1
Fixing the OB37 reinforcement bars having the diameter up to 10 mm in slabs and up to
18 mm in beams and columns, excluding the ones cast in sliding formworks, with polymeric
spacers. An amount of 50 kg of reinforcement is included in each cubic meter of concrete.
UM03.10 := 1kg
hr
NTi03.10 := 0.033
kg
kg
M03.10 := V03.06⋅ 50 = 2174.18 kg
3
m
(
Round_M03.10 := Ceil M03.10 , 1kg )
Round_M03.10 = 2175⋅ kg
03.11. C G 32 C1
Fillings compacted layers, done with crushed rocks and sand, compacted with manual
methods. We compute yhe geometric volume of the drainage layer with thickness of 10 cm,
under the basement floor.
3
UM03.11 := 1m
hr
NT03.11 := 0.92
3
m
V03.11 := 2⋅ 0.1m⋅ [ 9.9m⋅ ( 5.574m − 0.6m) − 2⋅ 0.35m⋅ 0.6m − 2⋅ 0.2m⋅ 1.1m] ...
+ 2⋅ 0.1m⋅ [ 9.9m⋅ ( 5.574m − 0.6m) − 2⋅ 0.35m⋅ 0.6m − 2⋅ 0.2m⋅ 1.1m] ...
+ 0.1m⋅ 4.3m⋅ ( 4.974m + 4.894m)
3
V03.11 = 23.5963⋅ m
03.12. C Z 01 06 A
Concrete floors,cast on site, slightly reinforced, mark B100, having the thickness of 10 cm
in continuous field, with cement wash of 2 mm, directly executed on fresh cast concrete.
2
UM03.12 := 1m
hr
NT03.12 := 0.69
2
m
S03.12 := 2( 10.5m⋅ 5.574m − 0.2m⋅ 0.3m − 2⋅ 0.2m⋅ 0.5m − 0.2m⋅ 0.15m − 2⋅ 0.3m⋅ 0.605m) ...
+ 2⋅ ( 10.5m⋅ 5.494m − 0.25m⋅ 0.084m − 2⋅ 0.2m⋅ 0.5m − 0.2m⋅ 0.15m − 2⋅ 0.3m⋅ 0.605m) ...
+ ( 4.9m⋅ 5.574m − 2⋅ 0.2m⋅ 0.15m) + ( 4.9m⋅ 5.494m − 2⋅ 0.15m⋅ 0.084m)
2
S03.12 = 284.042 m
Preparing the concrete mark B100 with heavy aggregates having the granulometry up to
31mm, for reinforced concrete in elements with reduced section, with cement F25 in centralized
installations.
*One compute the volume of flooring, considering the thickness of 10 cm.
3
UM03.13 := 1m
hr
NT03.13 := 0.085
3
m
3
V03.13 := S03.12⋅ 0.1m⋅ 1.008 = 28.6314⋅ m
03.133. C C 02 F
hr
NTi03.133 := 0.031
kg
kg
M03.133 := S03.12⋅ 3 = 852.126 kg
2
m
(
Round_M03.133 := Ceil M03.133 , 1kg ) Round_M03.133 = 853 kg
03.14. C Z 01 06 A
Preparing the concrete mark B200 with heavy aggregates having the granulometry up to
16mm, for reinforced concrete in elements with reduced section, with cement M30 in centralized
installations.
3
UM03.14 := 1m
hr
NTi := 0.085
3
m
( )
V03.14 := V03.03 + V03.06 ⋅ 1.008 = 95.978⋅ m
3
Preparing OB37 reinforcement having the diameter 6-8 mm, for concrete in construction
elements cast in formworks, excluding the ones executed in sliding formworks. We take into
account the reinforcement quantities to be placed in the volumes of concrete computed at
articles 03.05 and 03.10.
UM03.15 := 1kg
hr
NTi03.15 := 0.036
kg
( )
M03.15 := M03.04 + M03.10 ⋅ 1.01 = 4808.42 kg
(
Round_M03.15 := Ceil M03.15 , 5kg )
Round_M03.15 = 4810⋅ kg
03.16. C Z 03 02 F
Preparing PC52 reinforcement having the diameter 10-16 mm, for concrete in
construction elements cast in formworks, excluding the ones executed in sliding formworks. We
take into account the reinforcement quantities to be placed in the volumes of concrete computed
at articles 03.05 and 03.010.
UM03.16 := 1kg
hr
NTi03.16 := 0.025
kg
( )
M03.16 := M03.05 + M03.10 ⋅ 1.01 = 3763.42 kg
(
Round_M03.16 := Ceil M03.16 , 5kg )
Round_M03.16 = 3765⋅ kg
03.17. TRA 01 A 05
Transport of B100 concrete with traveling concrete mixers on a distance less of 5 km.
UM03.17 := 1tonne
tonne
M03.17 := V03.11⋅ 2.4 = 56.6311⋅ tonne
3
m
(
Round_M03.17 := Ceil M03.17 , 0.1tonne ) Round_M03.17 = 56.7⋅ tonne
03.18. TRA 06 A 05
UM03.18 := 1tonne
tonne
M03.18 := V03.14⋅ 2.4 = 230.3472⋅ tonne
3
m
(
Round_M03.18 := Ceil M03.15 , 0.1tonne )
Round_M03.18 = 4.9⋅ tonne
03.19. TRA 04 A 05
UM03.19 := 1kg
( )
1
M03.19 := M03.04 + M03.05 + M03.09 + M03.10 + M03.133 ⋅ = 9.2466⋅ tonne
1.01
(
Round_M03.19 := Ceil M03.19 , 0.1tonne )
Round_M03.19 = 9.3⋅ tonne
4. SUPERSTRUCTURE
04.01.C B 12 I
Casting the concrete in construction elements, excluding the ones executed in formworks,
marc B200 at the constructuins with height up to 35m, in walls with 30cm height.
We compute the concrete to be poured in slabs, walls, taking into account the existing voids.
2
UM04.01 := 1m
hr
NTi04.01 := 0.88
2
m
Hs := 2.85m storey height SAB = 5.6 m
hp := 13cm slab thickness
hw := Hs − hp = 2.72 m wall height
Ground floor:
3
Axis 2: V2s := hw⋅ 0.4m⋅ 0.3m⋅ 2 + 2⋅ 0.625m⋅ 0.3m⋅ hw = 1.6728⋅ m
3
Axis 3: V3s := V2s = 1.6728⋅ m
( )
+ 2⋅ SAB − 2⋅ 0.3m + 2⋅ 0.166m − 0.6m − 0.16m hw⋅ 0.16m − 0.9m⋅ 2.09m⋅ 0.16m⋅ 2
3
V4s = 4.6083⋅ m
3
Axis 5: V5s := 2⋅ 1.74m⋅ 0.125m⋅ hw + V4s = 5.7915⋅ m
3
Axis 6: V6s := V2s = 1.6728⋅ m
3
Axis 7: V7s := V2s = 1.6728⋅ m
3
Axis 8: V8s := V1s = 5.1157⋅ m
3
Axis B: VBs := ( 24.78m + 1.6m) ⋅ 0.16m⋅ hw − 2.09m⋅ 0.9m⋅ 2⋅ 0.16m = 10.8787⋅ m
3
Vfloor := V1s + V2s + V3s + V4s + V5s + V6s + V7s + V8s + VBs = 38.201⋅ m
3
V04.01 := Vfloor⋅ 5 = 191.0051⋅ m
3
Round_V04.01 := 200.03m
04.02. C B 12 II
Reinforced concrete formworks for walls and slabs, including the bracings, from
reusable plywood pannels with 15 mm thickness at construction having up to 20m.
We compute the surface of formworks for walls and slabs.
UM=1sqm
Nti=0.88hours/sqm
Axis 1: ( )
S1s := 2⋅ SAB − 2⋅ 0.3m + 2⋅ 0.166m ⋅ hw⋅ 2 ... = 58.0301 m
2
Axis 4: ( )
S4s := hw⋅ 0.48m⋅ 4 + 2⋅ SAB − 2⋅ 0.3m + 2⋅ 0.166m − 0.6m − 0.16m ⋅ hw⋅ 2 ...
+ −0.9m⋅ 2.09m⋅ 4
2
S4s = 53.0341 m
2
Axis 5: S5s := 4⋅ 1.74m⋅ hw + S4s = 71.9653 m
2
Axis 6: S6s := S2s = 11.152 m
2
Axis 7: S7s := S2s = 11.152 m
2
Axis 8: S8s := S1s + 4⋅ 0.6m⋅ 0.6m = 59.4701 m
2
Axis B: SBs := 2( 24.78m + 1.6m)hw − 2.09m⋅ 0.9m⋅ 4 = 135.9832 m
2
Sfloor := S1s + S2s + S3s + S4s + S5s + S6s + S7s + S8s + SBs = 423.0907 m
3 2
S04.02 := Sfloor⋅ 5 = 2.1155 × 10 m 2
sqm := 1m
Round_S04.02 := 2223sqm
04.02.C B 23 D1
Frame-formworks in black metal sheet for creating the voids in concrete walls.
We determine the voids' surface in walls.
2
UM04.02 := 1m
hr
NTi04.02 := 0.53
2
m
2
S04.03 := ( 6⋅ 0.9m⋅ 2.09m + 2⋅ 0.6m⋅ 0.6m) = 12.006 m
Mounting the OB37 reinforcement bars, having the diameter up to 8 mm in walls and
slabs, excluding the ones casted in glissant formworks, with polymeric spacers.
Following the bar list results an amount of 30kg of reinforcement at each cubic meter of concrete
in the walls and slabs.
UM=1kg
Nti=0.048hours/mp 3
V04.01 = 191.0051⋅ m
kg
M04.04 := V04.01⋅ 30 = 5730.15 kg
3
m
(
Round_M04.04 := Ceil M04.04 , 1kg ) Round_M04.04 = 5731 kg
04.05.C C 02 B1
Mounting the PC52 reinforcement bars, having the diameter of 10-12 mm in walls and
diaphragms, excluding the ones cast in glissant formworks, with polymeric spacers.
Following the bar list results an amount of 50kg of reinforcement at each cubic meter of
UM=1kg
Nti=0.041hours/mp
kg
M04.05 := V04.01⋅ 50 = 9550.25 kg
3
m
(
Round_M04.05 := Ceil M04.05 , 1kg )
Round_M04.05 = 9551 kg
04.06. C C 02 J1
3
V04.06 := 5V03.06 = 217.4179⋅ m
Formworks for reinforced concrete for slabs, beams and columns, excluding the bracings
from reusable plywood pannelshaving the thickness equal with 15 mm at the constructions
having up to 20m height, including the slabs and beams.
We compute the surface of formworks for slabs, adding the surface of the formworks for
balconies.
UM=1sqm
Nti=3.54hours/sqm
( ) 3 2
S04.07 := 5S03.07 + 2⋅ 5⋅ Hs − hp + 0.8m ⋅ 1m + 2⋅ 5⋅ 1m⋅ ( 7.25m + 0.8m) ... = 2.0828 × 10 m
+ 8⋅ 1⋅ m⋅ 0.13m
04.08. C B 45 B1
Metallic extensible beams to sustain, for pouring the monolith beams, slabs and plates with
total amount of 500 daN/m2, at the construction having up to 20 m height.
In each cell will put 3 beams sustained with 2 extensible columns and for each concrete beam will
put a metallic one also sustained with 2 extensibles columns.
UM=1piece
Nti=2.31h/piece
UM04.08 := piece
hr
NTi04.08 := 2.31
piece
N04.08 := 5⋅ ( 3⋅ 2⋅ 14 + 2⋅ 8) = 500
(
Round_N04.08 := Ceil N04.08 , 1piece ) Round_N04.08 = 500⋅ piece
04.09. C C 02 A1
Mounting the OB37 reinforcement bars having the diameter of 8 mm in slabs and beams,
excluding the ones cast in glissant formworks, with polymeric spacers.
Following the bar list results an amount of 30kg of reinforcement at each cubic meter of concrete
in the slabs and beams.
UM=1kg
Nti=0.048hours/kg
kg 3
M04.09 := V04.06⋅ 30 = 6.5225 × 10 kg
3
m
(
Round_M04.09 := Ceil M04.09 , 5kg )
Round_M04.09 = 6525⋅ kg
04.10. C C 02 D1
Mounting the PC52 reinforcement bars having the diameter of 18 mm in beams and
columns and 12 mm in slabs, excluding the ones casted in glissant formworks, with polimers
spacers.
Following the bar list results an amount of 50kg of reinforcement at each cubic meter of concrete
in the slabs and beams.
UM=1kg
Nti=0.028hours/kg
kg 4
M04.10 := V04.06⋅ 50 = 1.0871 × 10 kg
3
m
(
Round_M04.10 := Ceil M04.10 , 5kg )
Round_M04.10 = 10875⋅ kg
04.11. C Z 01.06 A1
Preparing the concrete mark B200 with heavy aggregates having the granulometry up to 16
mm, for reinforced concrete in elements with reduced section, with cement M30 in centralised
installations.
We determine the volume of the concrete prepared for pouring of the walls and of the slabs.
(art. 04.01 and 04.06)
UM=1cm
Nti=0.085hours/cm
( )
V04.11 := V04.01 + V04.06 ⋅ 1.008 = 411.6904⋅ m
3
04.12. C Z 03 02 A1
Preparing OB37 reinforcement having the diameter 6-8 mm, for concrete in construction
elements casted in formworks, excluding the ones executed in glissant formworks.
We take into account the reinforcement quantities computed at articles 04.04 and 04.09.
UM=1kg
Nti=0.036hours/kg
( )
M04.12 := M04.04 + M04.09 ⋅ 1.01 = 12375.22 kg
(
Round_M04.12 := Ceil M04.12 , 5kg )
Round_M04.12 = 12380⋅ kg
04.13. C Z 03 02 B1
Preparing PC52 reinforcement having the diameter 10-16 mm, for concrete in
construction elements casted in formworks, excluding the ones executed in glissant formworks.
We take into account the reinforcement quantities computed at articles 04.05 and 04.10.
UM=1kg
Nti=0.020hours/kg
( )
M04.13 := M04.05 + M04.10 ⋅ 1.01 = 20625.36 kg
(
Round_M04.13 := Ceil M04.13 , 5kg )
Round_M04.13 = 20630⋅ kg
04.14. TRA 06 A 05
kg
M04.14 := V04.11⋅ 2.4 = 988.057⋅ kg
3
m
(
Round_M04.14 := Ceil M04.14 , 1kg )
Round_M04.14 = 989⋅ kg
04.15. TRA 04 A 05
( )
M04.15 := M04.04 + M04.05 + M04.09 + M04.10 = 3.2674 × 10 kg
4
(
Round_M04.15 := Ceil M04.15 , 0.1tonne ) Round_M04.15 = 32.7⋅ tonne
5. MASONRY
05.01. C D 07 C
Cellular concrete masonry with M25 mortar in 30 cm thick walls, for constructions up to
35 m height, included with GBN bloks.
3 3
CSI_M25 := 0.065m M25 / 1m wall
3 3
CSBCA := 0.975m BCA / 1m wall
Hb := 0.47m beam height
Swindows := 4( 10⋅ 1.5m⋅ 1.2m + 4⋅ 1.2m⋅ 1.2m + 2⋅ 0.6m⋅ 0.6m + 0.6m⋅ 0.9m) ...
+ 9⋅ 1.5m⋅ 1.2m + 4⋅ 1.2m⋅ 1.2m + 2⋅ 0.6m⋅ 0.6m
2
Swindows = 122.76 m
( ) ( )
V05.01 := 2⋅ 26.7m⋅ Hs − Hb ⋅ 0.3m⋅ 5 − Swindows + Sdoors ⋅ 0.3m ...
( )
+ 11.686m⋅ Hs − Hb ⋅ 0.3m⋅ 5
3
V05.01 = 183.6401⋅ m
05.02. C P 15 C
( )
S05.02 := 54( 3.415 − 0.9) + 4( 2 − 0.7) + 8( 5.62 − 0.166 − 0.625 − 0.9) ... m⋅ Hs − Hb ...
+ 2( 2.795 − 0.8) + 2⋅ ( 2.795 − 0.9) + 1.645 + ( 2.405 − 0.8) ...
+ ( 1.95 − 0.7) + 5.12
(
+ 4[ 0.96 + ( 1.95 − 0.7) ]m⋅ Hs − Hb )
2
S05.02 = 783.734 m
M100-T cement mortar prepared with M30 cement in special installations without lime
admixture.
UM=1mc
Nti=0.86hours/mc
3
CSI_M100T := 0.0018m
CSI_M100T
3
V05.03 := 2S05.02⋅ = 2.8214⋅ m
2
m
05.04. C Z 02.02 C
M25Z cement mortar prepared with F25 cement in non-centralized installations, with lime
admixture.
UM=1cm
Nti=0.86hours/cm
CSI_M25 3
V05.04 := V05.01⋅ = 11.9366⋅ m
3
m
05.05. TRA 01 A 05
( )
tonne
M05.05 := V05.01 + S05.02⋅ 0.125m ⋅ 2.0 = 563.2137⋅ tonne
3
m
(
Round_M05.05 := Ceil M05.05 , 0.1tonne )
Round_M05.05 = 563.3⋅ tonne
05.06. TRA 01 A 05
( )
tonne
M05.06 := V05.03 + V05.04 ⋅ 2.1 = 30.9919⋅ tonne
3
m
(
Round_M05.06 := Ceil M05.06 , 0.1tonne ) Round_M05.06 = 31⋅ tonne
6. CARPENTRY WORKS
06.01. C K 01 A
Wooden windows, simple, double or coupled, with regular or interior opening direction,
with one or more leaves, for social, cultural or industrial buildings, including thermal and hydro
insulation, in buildings up to 35 m high, for windows with a surface frame up to 1 m2,
inclusively.
2
UM06.01 := 1m
hr
NTi06.01 := 2.69
2
m
2
S06.01 := ( 2⋅ 0.6m⋅ 0.6m) ⋅ 5 + ( 0.6m⋅ 0.9m) ⋅ 4 = 5.76 m
06.02. C K 01 B
Wooden windows, simple, double or coupled, with regular or interior opening direction,
with one or more leaves, for social, cultural or industrial buildings, including thermal and hydro
insulation, in buildings up to 35 m high, for windows with a surface frame up to 1 m2,
inclusively.
2
UM06.02 := 1m
hr
NTi06.02 := 1.25
2
m
2
S06.02 := ( 10⋅ 1.5m⋅ 1.2m) ⋅ 5 + ( 4⋅ 1.2m⋅ 1.2m) ⋅ 5 + 2.4m⋅ 0.6m⋅ 4 = 124.56 m
06.03. C K 04 A
Wooden doors for balconies (exterior), with regular or interior opening direction, with one
or two leaves, made of lumber, for social, cultural buidings, including thermal and hydro-
insulation of the frames, for buildings up to 35 m high.
2
UM06.03 := 1m
hr
NTi06.03 := 1.48
2
m
2
S06.03 := ( 4⋅ 0.9m⋅ 2.00m) ⋅ 4 + ( 5⋅ 0.9m⋅ 2.00m) = 37.8 m
06.04. C K 03 F
Wooden doors, interior or exterior, simple, including waterproofing and thermal insulation
of the door frame, mounted on interior, existing, wooden dowels, type CIL, finished by the
producer, with one leaf, on door frame and timber plankings.
2
UM06.04 := 1m
hr
NTi06.04 := 1.31
2
m
2
S06.04 := ( 4⋅ 0.70⋅ 2.09 + 14⋅ 0.90⋅ 2.09 + 4⋅ 0.80⋅ 2.59 + 6⋅ 0.90⋅ 2.59)m ⋅ 5 ...
2
+ 9⋅ 0.7⋅ 2.59m
2
S06.04 = 288.617 m
06.05. C K 09 B
Wooden boards, sills and rods for doors, sills and rods up to 20 mm thickness and 100
mm width, mounted on doors.
UM06.05 := 1m
hr
NTi06.05 := 0.07
m
L06.05 := 54( 2⋅ 2.09m + 0.7m) + 14( 2⋅ 2.09m + 0.9m) + 4⋅ ( 2⋅ 2.59m + 0.8m) ... ...
+ 6⋅ ( 2⋅ 2.59m + 0.9m) + 9⋅ ( 2⋅ 2.59m + 0.7m)
+ 21⋅ ( 2⋅ 2m + 0.9m) + ( 1m + 2⋅ 1.945m) + ( 1.565m + 2⋅ 1.945m)
L06.05 = 1133.045 m
(
Round_L06.05 := Ceil L06.05 , 1m ) Round_L06.05 = 1134⋅ m
06.06. C K 09 A
(
Round_L06.07 := Ceil L06.06 , 1m )
Round_L06.07 = 119⋅ m
06.07. C M 02 B
Glass of 2-3 mm thickness, with wooden frames, polished, fixed with lute and nails, in
holes over 0.25 m2. It is considered that the glass' surface represents approximately 80% from
the windows' and balcony doors' surface.
2
UM06.07 := 1m
hr
NTi06.07 := 0.45
m
( )
S06.07 := S06.01 + S06.02 + S06.03 ⋅ 2⋅ 0.8 = 268.992 m
2
06.08. C K 14 J
Metallic doors made of rolled steel profiles or corrugated sheet of cold formed steel
profiles or aluminium profiles, including reinforcement and fittings (accessories) needed for door
placing in any type of masonry, aluminum doors for constructions up to 10 m height with frame
surface between 5-7 m2, inclusively.
2
UM06.08 := 1m
hr
NTi06.08 := 1.31
2
m
2 2
S06.08 := 1.945( 1 + 1.565) m = 4.9889 m
07.01. C F 01 C
Manual interior plastering for walls and columns on concrete surfaces, small concrete
blocks or cellular concrete blocks with lime mortar, M10-T cement grade, of 2 cm average
thickness, including scafoldings.
2
UM07.01 := 1m
07.02. C F 03 A
Manual interior plastering for ceilings made of cast in place concrete or prefabricated
elements, hand made with lime mortar, M10-T cement grade, of 2 cm average thickness,
including scafoldings.
2
UM07.02 := 1m
hr
NTi07.02 := 1.03
2
m
3 2
CSI_M25T := 0.020m M25-T/ m
2
S07.02 := S04.07 = 2082.7553 m
07.03. C F 10 C
Floated plastering on the concrete elements' surface, columns and ceilings, hand made
with plastering paste.
2
UM07.03 := 1m
hr
NTi07.03 := 0.38
2
m
* S
09.03_cl. := 4[ 2( 2m + 2.10m − 0.7m) ⋅ 3.37m] + 2[ 2⋅ ( 2.795m + 3.07m − 0.8m) ⋅ 3.37m] ...
+ 2⋅ [ 2( 2.405m + 3.515m − 0.8m) ⋅ 3.37m]
2
S07.03 := S07.01 + S07.02 + S05.02⋅ 2 − S09.03. = 4748.953 m
07.04. C Z 02.06 A
Lime mortar, M10-T cement grade, made with F25 cement and plastering paste in
centralized installations.
3
UM07.04 := 1m
hr
NTi07.04 := 0.52
3
m
3
m 3
V07.04 := S07.01⋅ 0.018 = 40.4307⋅ m
2
m
07.05. C Z 02.07 A
Lime mortar, M25-T cement grade, made with F25 cement and plastering paste in
centralized installations.
3
UM07.05 := 1m
hr
NTi07.05 := 0.52
3
m
3
m 3
V07.05 := S07.02⋅ 0.020 = 41.6551⋅ m
2
m
tonne tonne
M07.06 := V07.04⋅ 1.9 + V07.05⋅ 2.1 = 164.294⋅ tonne
3 3
m m
(
Round_M07.06 := Ceil M07.06 , 1tonne )
Round_M07.06 = 165⋅ tonne
8. FLOORING
08.01. C G 01 D
Supporting layer for floors made of 3 cm thickness cement mortar, grade M100-T.
2
UM08.01 := 1m
hr
NTi08.01 := 0.46
2
m
3 2
CSI_M100T. := 0.031m M100-T/ m
2 2 2 2
S08.01 := 11.95m ⋅ 4⋅ 5 + 24.9m ⋅ 4⋅ 5 + ( 2.55⋅ 2.795)m ⋅ 2⋅ 5 ... = 864.31 m
2
+ ( 2.005⋅ 2.795)m ⋅ 2⋅ 5
08.02. C G 03 E
PVC plastic floorings including sills, cleaned and waxed in rooms with surface up to 20
m2, with wooden sill.
2
UM08.02 := 1m
hr
NTi08.02 := 0.73
2
m
2
S08.02 := S08.01 = 864.3123 m
Mosaic plinth cast in place, without pigments, including 3 cm supporting layer with
cement mortar, grade M100-T, including cleaning and washing, 10 cm height.
2
UM08.03 := 1m
hr
NTi08.03 := 2.23
2
m
2 2 2 2 2
S08.03 := 8.30m ⋅ 2⋅ 5 + 8.20m ⋅ 5 + 8.40m ⋅ 5 + 4.20m ⋅ 4⋅ 5 ... = 520.603 m
+ ( 2.405m + 2.41m) ⋅ 5.62m⋅ 5 + 4.815m⋅ 5.62m⋅ 5
08.04. C G 07 B
Mosaic plinth cast in palce, without pigments, including support layer of mortar M100-T
cement grade, including scrubbing and washing horizontal plinth or 10 cm height for walls made
of marble.
UM08.04 := 1m
hr
NTi08.4 := 1.2
m
(
Round_L08.04 := Ceil L08.04 , 5m ) Round_L08.04 = 1540⋅ m
08.05. C Z 02.09 A
Cement mortar for plastering M100-T with M30 cement grade, prepared in centralized
installations, without lime admixture.
3
UM08.05 := 1m
hr
NTi08.05 := 0.52
3
m
3
CSI_M100T. = 0.031⋅ m
CSI_M100T.
3
V08.05 := S08.01⋅ = 26.7937⋅ m
2
m
08.06. TRA 06 A 08
tonne
M08.06 := V08.05⋅ 2.2 = 58.9461⋅ tonne
3
m
(
Round_M08.06 := Ceil M08.06 , 0.1tonne )
Round_M08.06 = 59⋅ tonne
09.01. C N 02 B
hr
NTi09.01 := 0.31
2
m
S09.01 := S07.03
2
Round_S09.01 = 4749⋅ m
09.02. C N 09 B
3 ply interior painting for doors and windows on wood framings, using oil colours.
2
UM09.02 := 1m
hr
NTi09.02 := 1.14
2
m
( )
S09.02 := S06.01 + S06.02 + S06.03 ⋅ 3 + S06.04⋅ 2.9 = 1341.3493 m
2
09.03. C I 06 S
Mounting faience on walls and columns, including the plating of lintels using the same
colour and format plates, using M100-T cement grade, using lime admixture of 2 cm thickness,
in rooms less than 10 m2.
2
UM09.03 := 1m
hr
NTi09.03 := 2.72
2
m
S09.03_cl := 4[ 2( 2m + 2.10m − 0.7m) ⋅ 4.27m] + 2[ 2⋅ ( 2.795m + 3.07m − 0.8m) ⋅ 4.27m] ...
+ 2⋅ [ 2( 2.405m + 3.515m − 0.8m) ⋅ 4.27m]
S09.03_gl := 4[ 2( 2m + 2.10m − 0.7m) ⋅ 4.27m] + 2[ 2⋅ ( 2.795m + 3.07m − 0.8m) ⋅ 4.27m] ...
+ [ 2( 2.405m + 3.515m − 0.8m) ⋅ 4.27m] + [ 2( 2.795m + 3.515m − 0.8m) ⋅ 4.27m]
2
S09.03 := 4S09.03_cl + S09.03_gl = 1453.8496 m
10.01. C B 48 A
hr
NTi10.01 := 0.28
2
m
Hattic := 0.9m
Hpedestal := 1.1m
( )
S10.01 := 5 Hs + Hattic + Hpedestal 2⋅ ( 27.2m + 11m) = 1241.5 m
2
Exterior plastering in artficial stone for facade hand-made, using M100-T cement grade
mortar, with lime admixture of 1.5 average thickness, with visible layer of M100-T cement
mortar with the superior layer's thickness of 0.5-0.8 cm.
2
UM10.02 := 1m
hr
NTi10.02 := 2.21
2
m
( ) 2
S10.02 := S10.01 − S06.01 + S06.02 + S06.03 ⋅ 1.10 = 1180.718 m
Round_S10.02 := Ceil S10.02 , 1m
2
Round_S10.02 = 1181⋅ m
2
10.03. C Z 02.09 D
Cement mortar for plastering M100-T with M30 cement in non-centralized installations,
without lime admixture.
3
UM10.03 := 1m
hr
NTi10.03 := 0.52
3
m
3
m 3
V10.03 := S10.02⋅ 0.017 = 20.0722⋅ m
2
m