You are on page 1of 2

Item No.

RCC [M25]
1 Considering 1Cum Cum

Sr No Description of the Material Unit Quantity Rate Amount Wastage

A Material Cost
1 Cement [Approx 360 kgs/Cum] Bags 7.25 220.00 1595.00 3%
2 Sand Cum 0.55 1100.00 605.00 3%
3 12mm size aggregate cum 0.24 750.00 180.00 3%
4 18mm-20mm size aggregate Cum 0.65 900.00 585.00 3%
5 Shuttering Material Sqm 8.30 210.00 1743.00

B Labour Cost
6 Labour for concreting Cum 1.00 350.00 350.00
Labour For Shuttering @ Rs
7 Cum 8.30 110.00 913.00
110/SQM

8 Curing Rs. 50.00


9 Hacking Rs. 0.00

Total A+ B =

C Over heads & Profit


10 T/P Etc Charges % age 1.50 On Total A+B
11 Water Charges % age 1.00 On Total A+B
12 Electricity Charges % age 1.00 On Total A+B

13 Over head & Profit % age 15.00 On Total A+B

Total A + B + C =
Total
Loading
Amount

1642.85
623.15
185.40
602.55
1743.00

350.00

913.00

50.00
0.00

Total A+ B = 6156.30

92.34
61.56
61.56

923.45

Total A + B + C = 7295.22