Professional Documents
Culture Documents
Presented By:
LAURA WILDMAN, PE
Director, New England Regional Office Director, New England Regional Office Ecological Restoration & Fisheries Engineer Ecological Restoration & Fisheries Engineer
Dam Removal Demystified: Workshop hosted by American Rivers June 14, 2011 Chapel Hill, NC
Talk Outline
History of the Dam
Construction Sequencing Reverse Engineering
Technical Specifications Expect the Unexpected Access Dewatering Water Control Infrastructure Retrofits Remove Dam & Assoc. Structures Site Restoration Site Protection/Safety Construction Oversight Lessons Learned Monitoring
Dam Types
Earth Gravity Earth and Rock Timber/Rock Fill Variable Radius Arch Hydraulic Fill Constant Radius Arch Flashboard & Buttress Multiple Arch Reinforced Concrete Tank Slab and Buttress Inflatable Rubber Crib Other (sheetpile, tailings, etc)
CONSTRUCTING A DAM
Build primary portion of dam Redirect water Fill dam notch Remove equipment & water controls Fill with water
REMOVING A DAM
Divert water
Notch dam Divert water through notch Remove primary portion of dam Redirect water Removed water controls Free flowing river
Princeton Hydro
Princeton Hydro
The New Water Power of the Hartford Electric Company written in 1900 three waste pipes were capable of carrying normal flow(later) permanently sealed with 12 x 12 in. southern pine old surface of the rock was taken off by squib blasting..surfaces of rock were made to slope upstream
Wiley-Russell Dam, MA
Legacy Dam
Tree Stumps
Dunkard Creek Dam, PA - Turn of the century cooling systems for a gas pumping station
TECHNICAL SPECIFICATIONS
Princeton Hydro Princeton Hydro
Sediment moves daily plan to dig it only once Take precautions for unknown contaminants Working in a river plan for variable flows emergency high flows Unknown reinforcing plan for worst case Double check quality & quantities during construction
High flow Mean Flow
Princeton Hydro
Unexpected reinforcing
Princeton Hydro
Easy
Access
Hard
Access from crest of dam
Dam Hard
Reservoir Drawdown
Reservoir Drawdown
Time for Vegetation to Reestablish
Can make equipment access easier Can reduce the amount of sediment transported
During drawdown
Reservoir Drawdown
partial breach / notch low level outlets siphons bypass pipe or channel riser with outlet
Source: PA Fish & Game
Source: NH DES
Water Control
Princeton Hydro
Diversion Systems
Pumps, siphons Excavated channel Excavated channel w/ liner Pipe bypass Box culvert, tunnel,
Cofferdam Systems
Earthen cofferdams Sheetpile cofferdams Tilt-up panels Water bubble dam
Water Control
Lessons Learned:
Water control & S&E are never as pretty as on the plans Have good inspectors Take care when inviting spectators or press to site Dont rely too heavily on water control measures Working in the wet is preferred (in & out faster) Design/Plan for a potential blow out
Source: NH DES
Methods of Removal
Extent & Timing of Removal Staged (timing, Full
delta migration, % remaining)
Partial
(height or width)
Bypass Dam
Source: Wildman
Amount of original delta eroded by different channel positions under the single and triple notch scenarios
80 70 Percentage eroded 60 50
Image courtesy of National Park Service
Methods of Removal
Bypass Dam
California Coastal Conservancy, NMFS, Planning & Conservation League Foundation, and Cal Am
Methods of Removal
Embankment and Timber Demolition Excavator w/ Bucket Grapples/Splitters/Thumb Crane and Dragline Dozer
Concrete Demolition Mechanical impact methods Expansive grout methods Sawcutting methods Blasting methods
Princeton Hydro
Princeton Hydro
Princeton Hydro
Grapples
Princeton Hydro
Splitter
Franklin Dam removal Sheboygan River, Wis. 2001 Orienta Dam, Iron River, Wis. Removed, 2001
Princeton Hydro
Princeton Hydro
Blasting Methods
Waddel Dam - AZ
Princeton Hydro
Site Protection
Protection of equipment Protection of plantings Site safety (spectators & boaters)
Historic Restoration
Creative ways to incorporate historic preservation in a dam removal.
Source: Wildman
Only lowered the dam. Left the dam sill in, now river dynamics & fish passage are not restored.
Source: Wildman
Leaving the Dam Sill in Place Means Leaving the Dam in Place
Dam Removal in PA
Dam Removal in MA
Dam Removal in CT
Removing a Structure Only to Install More Structures Weirs, J-Hooks, Ramps, Etc.
Construction Oversight
Engineering designer should help to supervise construction
Most familiar with the site Ensure that dam is removed in a manner consistent with plans, permits and vision for the site Link design quality & responsibility to the design firm
Listen & learn from the contractor Determining level of oversight needed Document/photograph/video Historic (reuse of material) and Ecological oversight
Think in terms of constructability Check quantities twice (3 times, etc..) Have sediment testing results and arrange for a disposal site, & onsite staging/stockpile sites Get contractors advice on creative/cost saving approaches Show actual proposed elevations/grades Show dam material/construction/quantity Fish timing and turbidity restrictions Installing useless E&S controls Strength of concrete underwater or cured under water
Use photographs if necessary to explain odd/unique requests (i.e. rootwad placements, etc.) Dont try to shift all the risk & liability to them
Billington Dam Military Readiness Initiative (great, lots of equipment, no restoration); Asbestos tiles
Source: American Rivers
wanted
tons of weirs; mucky soil (difficult construction); left a sill; wetland wars
http://www.gulfofmaine.org/streambarrierremoval/
High bids!
Changed plans from big to small but original bids based on big Too many people at mandatory prebid meeting Bid during wrong time of year Non-typical items on plans (rootwads) Difficult soil conditions
When a contractor feels like they are taking on risk the price goes up!
Source: American Rivers
Made project seem like a big deal (risky, press, sensitive, lg. bid package)
FLO W
Time and materials delays by contractor, but emergency permit sped things up
FLO W
Upstream pipe exposed provide for flexibility in permit applications Removing sediment twice
Primary Project Lead: City of Waterbury & CT DEP Engineering: Milone & MacBroom
Sheetpile core Poor contractor with rented equipment Water control extras