You are on page 1of 8

Code No: R05321502 Set No.

1
III B.Tech Supplimentary Examinations, Aug/Sep 2008
MATHEMATICAL MODELING AND SIMULATION
(Computer Science & Systems Engineering)
Time: 3 hours Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
⋆⋆⋆⋆⋆

1. (a) What is the role of decision variables in linear programming model?


(b) What is the standard form of linear programming model and explain.
(c) What is the use of functional constraints in linear programming model?[4+6+6]

2. Discuss the streamlined simplex method for the transportation Problem. [16]

3. (a) Discuss stochastic multi period model with batch orders and no setup cost.
(b) Draw the graph for the above. [12+4]

4. (a) A company purchases three items A,B,C Their annual demand and prices are
given in the following table.

Items Annual Demand Unit Price


A 1,00,000 3
B 80,000 2
C 600 96
If the company wants to place 40 orders per year for all the three items, what
is the optimal number of orders for each item?
(b) The following thirty numbers represent the annual value in thousand of rupees
of some thirty items of materials selected at random. Carry out an ABC
analysis and list out the values of ‘A’ items only. [6+10]

1 2 4 9 75 4
3 6 13 2 4 12
100 2 7 40 15 55
1 11 25 15 8 10
1 20 30 1 3 5

5. (a) Explain the meaning of a ‘Queue’ with suitable examples.


(b) Customers arrive at a box office window being manned by a single individual
according to a Poisson input process with a mean rate of 30 per hour. The
time required to serve a customer has an exponential distribution with a mean
of 90 seconds. Find average waiting time of a customer. Also determine the
average number of customers in the system and average queue length. [7+9]

1 of 2
Code No: R05321502 Set No. 1
6. A company manufacturing plant and equipment for chemical processing is in the
process of quoting a tender called by a public sector undertaking. Delivery data
once promised is crucial and penalty clause is applicable. Project manager has
listed down the activities in the project as under:

Activity Immediate Activity Time (weeh)


Predecessor Optimistic Most Likely Pessimistic
A - 1 3 5
B - 2 4 6
C A 3 5 7
D A 5 6 7
E C 5 7 9
F D 6 8 10
G B 7 9 11
H E,F,G 2 3 4

Using PERT:

(a) find out the delivery week from the date of commencement of the project, and
(b) total float and free float for each of the non-critical activities. [16]

7. A sample of 100 arrivals of customers at a retail sales depot is according to the


following distribution:

Time between arrivals (minutes) 0.5 1 15 2 2.5 3 3.5 4 4.5 5


Frequency 2 6 10 25 20 14 10 7 4 2
A study of the time required to service customers by adding up the bills, receiving
payments, placing packages, etc. yields the following distribution.

Service time (minutes) I: 0.5 1 1.5 2 2.5 3


Frequency 12 21 36 19 7 5
Estimate the average percentage of customer waiting time and average percentage
idle time of the server by simulation for the next 10 arrivals. Assume any suitable
random numbers. [16]

8. Distinguish verification and validation of simulation models with appropriate ex-


amples. [16]

⋆⋆⋆⋆⋆

2 of 2
Code No: R05321502 Set No. 2
III B.Tech Supplimentary Examinations, Aug/Sep 2008
MATHEMATICAL MODELING AND SIMULATION
(Computer Science & Systems Engineering)
Time: 3 hours Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
⋆⋆⋆⋆⋆

1. A television company has three major departments for the manufacture of its two
models A and B. The monthly capacities are given as follows: [16]
Per unit Hours available this month
time
requirement (hours)
Model A Model B
Dept - I 4.0 2.0 1600
Dept - II 2.5 1.0 1200
Dept - III 4.5 1.5 1600
The marginal profit per unit from of model A is Rs 400 and that of model B
us Rs100. Assuming that the company can sell any quantity of either product
to do favorable market conditions, Determine the optimum output for both the
models, the highest possible profit for this month and the slack time in the three
departments.

2. A pure Binary Integer Programming example with the constraint, 2x1 +3x2 ≤ 4,
was used to illustrate the procedure for tightening constraints. Show that applying
the procedure for generating cutting planes to this constraint yields the same new
constraint, x1 +x2 ≤ 1. [16]

3. (a) Describe the basic characteristics of an inventory system?


(b) Explain with suitable examples. [8+8]

4. (a) “Purchase manager should shoulder special responsibility for A-items and the
‘A’ items should not be handled on any routine procurement policy.” Discuss.
(b) Determine the Re-order level with uncertain demand. [10+6]

5. (a) Discuss the fields of application for queuing theory?


(b) Telephone users arrive at a booth following a poison distribution with an av-
erage time of 5 min between one arrival and the next. The time taken for
telephone call is on an average 3 min. and it follows an exponential distribu-
tion. What is the probability that the booth is busy? How many more booths
should be established to reduce the waiting time to less than equal to half of
the present waiting time? [6+10]

6. A company has decided to market a new product for the consumer market. The
problems of how to plan and control the various phases of this project-sales promo-
tion, training of salespeople, pricing, packaging, advertising, and manufacturing-are

1 of 2
Code No: R05321502 Set No. 2
obvious to the management of this firm. They have asked you to guide then through
this difficult venture using CPM, since time is of the essence. The first firm to mar-
ket this type of product will reap substantial profits and will enhance its image by
marketing such a revolutionary product. A list of the activities, with the expected
time duration for each, is given in the table in terms of weeks:

Activity Precedents Time(weeks)


A -- 1
B A 1
C B 3
D C 3
E B 3
F B 8
G E 2
H G 4
I P 1
J F 0
K D,J,H,I,T 3
L K 7
M B,S 2
N M 4
O N 5
P O 1
Q K,S 2
R Q 3
S B 2
T S 3
Draw network diagram, identify tthe critical part and determine its length. [16]

7. Discuss in detail various applications of simulations in real life with examples. [16]

8. Discuss need and scope of mathematical modeling with illustrations. [16]

⋆⋆⋆⋆⋆

2 of 2
Code No: R05321502 Set No. 3
III B.Tech Supplimentary Examinations, Aug/Sep 2008
MATHEMATICAL MODELING AND SIMULATION
(Computer Science & Systems Engineering)
Time: 3 hours Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
⋆⋆⋆⋆⋆

1. A farmer has 1000 acres of land on which he can grow corn, wheat or soyabeans.
Each acre of corn costs Rs100 for preparation, requires 7 men/day of work and yields
a profit of Rs30. An acre of wheat costs Rs120 to prepare, require 10 men/day of
work and yields a profit of Rs20. If the former has Rs1,00,000 for preparation and
can count on 8000 men/day of work, determine how many acres should be allocated
to each crop to max’m profits. [16]

2. (a) What is Initial solution in transportation problem.


(b) Discuss the following methods for binding initial solution.
i. North-west corner method
ii. Least cost Method
iii. VAM. [4+4+4+4]

3. Discuss the basic EOQ model in deterministic continuous review models. [16]

4. Draw the graph for ABC classification of inventory items and discuss the steps in
ABC analysis with example. [16]

5. Arrival rate of telephone calls at a telephone booth is according to Poisson distri-


bution, with an average time of 9 minutes between the consecutive arrivals. The
length of telephone call is assumed to be exponentially distributed with mean 3
minutes.

(a) Determine the probability that a person arriving at the booth will have to
wait.
(b) Find the average queue length that forms time to time.
(c) The telephone company will install a second booth when convinced that an
arrival would expect to have to wait at least four minutes for the phone.
(d) What is the probability that an arrival will have to wait for more than 10
minutes before the phone is free?
(e) What is the probability that he will have to wait for more than 10 minutes
before the phone is available and the call is also complete?
(f) Find the fraction of a day that the phone will be in use. [16]

6. Listed in the table are the activities and sequencing requirements necessary for the
completion of a research report.

1 of 2
Code No: R05321502 Set No. 3
Activity Description Precedence
Duration (weeks)
A Literature search - 6
B Formulation of hypothesis - 5
C Preliminary feasibility study B 2
D Formal proposal C 2
E Field analysis A,D 2
F Progress report D 1
G Formal research A, D 6
H Data collection E 5
I Data analysis G,H 6
J Conclusions I 2
K Rough draft G 4
L Final copy J,K 3
M Preparation of oral presentation L 1

(a) Draw a network diagram for this project.


(b) Find the critical path. What is its length?
(c) Find the total float and the free float for each non-critical activity. [16]

7. A certain maintenance facility is responsible for the upkeep of five machines. The
machines, which fail frequently, must be repaired as soon as possible to maintain
as high a productive capacity of the production system as possible. Management is
concerned about the average down time per machine and is considering an increase
in the capacity of maintenance facility. The following distributions have been de-
veloped from historical data:

Time between breakdown (days) Probability Repair time Probability


2 0.05 1 0.4
3 0.10 2 0.5
4 0.15 3 0.1
5 0040 4 0.2
6 0.20 5 0.3
7 0.10 6 0.6
Simulate the failure and repair of 10 machines. Begin by determining the time of
the first breakdown by each of the 5 machines. Sequence the machines through the
repair facility on first come first served basis. If there is more than one machine
waiting to be repaired, arbitrarily choose one to repair the next. After a machine
has been repaired, determine its next time of break down and continue until you
have repaired 10. Assume any suitable random numbers. [16]

8. Discuss various definitions of modeling mentioning its appropriate applications.[16]

⋆⋆⋆⋆⋆

2 of 2
Code No: R05321502 Set No. 4
III B.Tech Supplimentary Examinations, Aug/Sep 2008
MATHEMATICAL MODELING AND SIMULATION
(Computer Science & Systems Engineering)
Time: 3 hours Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
⋆⋆⋆⋆⋆

1. (a) Explain about the levels of abstraction in model development?


(b) Discuss the simplex method procedure for solving on Linear Programming
Problem? [4+12]
2. (a) What is assignment problem? Discuss in detail.
(b) Discuss the assignment problem solution procedure. [8+8]
3. (a) Purchase manager has decided to place order to a minimum quantity of 500
member of a particular item in order to get a discount of 10%. Form the past
records it was found out that in the last year, 8 orders each of size 200 units
were placed. Given the ordering cost is Rs.500 per order, inventory carrying
cost of 40% of the inventory value and the price of the item of Rs.400 per
unit. Is the purchase manager justified in his decision? What is the effect of
his decision to the company?
(b) The annual demand for a product is 64,000 units (or 1280 units per week).
The buying cost per order is Rs.10 and the estimated cost of carrying one unit
in stock for a year is 20%. The normal price of the product is Rs.10 per unit.
however, the supplier offer a quantity discount of 2% on an order of at least
1000 units of a time, and a discount of 5% if the order is for at least 5,000
units. Suggest the most economic purchase quantity per order. [8+8]
4. (a) Classify the material in A,B,C classification for the following information. This
information is known about a group of items.

Model Number Annual Consumption pieces Unit Price


(in paise)
501 30,000 10
502 2,80,000 15
503 3,000 10
504 1,10,000 5
505 4,000 5
506 2,20,000 10
507 15,000 5
508 80,000 5
509 60,000 15
510 8,000 10
(b) Draw the graph for cumulative % of items (q) and cumulative % of usage value
for the above table. [10+6]

1 of 2
Code No: R05321502 Set No. 4
5. (a) State and prove Markovian Property of inter arrival times.
(b) A repair shop attended by a single mechanic has an average of four customers
an hour who bring small appliances for repair. The mechanic inspects them
for defects and takes six minutes on an average. Arrivals are Poisson and
service rate has the exponential distribution. You are required to
i. Find the proportion of time during which there is no customer in the shop.
ii. Find the probability of finding at least one customer in the shop.
iii. What is the average number of customers in the system?
iv. Find the average time spent by a customer in the shop including service.
[6+10]

6. A company manufacturing plant and equipment for chemical processing is in the


process of quoting a tender called by a public sector undertaking. Delivery data
once promised is crucial and penalty clause is applicable. Project manager has
listed down the activities in the project as under:

Activity Immediate Activity Time (weeh)


Predecessor Optimistic Most Likely Pessimistic
A - 1 3 5
B - 2 4 6
C A 3 5 7
D A 5 6 7
E C 5 7 9
F D 6 8 10
G B 7 9 11
H E,F,G 2 3 4

Using PERT:

(a) find out the delivery week from the date of commencement of the project, and
(b) total float and free float for each of the non-critical activities. [16]

7. Why would an analyst prefer a general purpose language such as FORTRAN or


BASIC in simulation? Explain anyone application area of simulation with illustra-
tion.
[16]

8. Why would an analyst ever prefer a general purpose language such as FORTRAN or
BASIC in a simulation when there are advantages of using special purpose languages
such as GPSS or SIMSCRIPT? Illustrate with examples. [16]

⋆⋆⋆⋆⋆

2 of 2

You might also like