BC Fieldvisit 8
BC Fieldvisit 8
Project:: Toms Creek Wood Frame DB Contractor: Structures Date: 12/1/11 Report Number: 8 Day: Su M T W Th F S
Work Performed:
No work was being performed on site while visiting. Outside of the building was a stack of prefab trusses. It seemed that on the outside there was a green sheet being placed which appeared to be insulation. It appeared that the structure was mainly stick build.
Weather
Temp: 37 Degrees F Wind: None Condition: Sunny Humidity: None