Example of an Activity Chart - Benchmarking study

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Week Activities Develop a broad plan Get approval Identify team Train Team Develop detailed plan Conduct preliminary research Identify key practices Identify benchmark partners Shedule visits to partners Analyze data Identify current state Develop benchmark questions Visit benchmark partners Develop new process Finalize new process Get approval 1 2 3 4 5 6 7 8 9 10