Bai Tap Qtda
Bai Tap Qtda
Bi 1. Cho 1 d n v Qun l Phng khm Nha khoa t nhn vi cc thng tin sau:
- S Data FP: 172 (FP)
S Transaction FP: 278 (FP)
- VAF: 95%
S liu lch s gm:
- 2 d n P1 v P2 tng t lm trc :
o D n P1 c Sched1=3, P1=1.25
o D n P2 c Sched2=4.5, t2=2600 (m-hrs) (m-hrs l man-hour, gi cng lm vic)
Yu cu:
- Tnh AFP, t, PM, gi s Productivity = 12 (m-hrs/FP), PM (m-months)= 173 (m-hrs) (trong mmonths l man-month, thng cng lm vic)
- Tnh b, gi s chi ph Rate = 15 ($/m-hrs) v khng c thm chi ph pht sinh no khc.
- Tnh TDEV
- Tnh R v Rmax vi Rmax = 125% R
GII
* Tnh AFP, t, PM, b:
UFP = DataFP + TransactionFP = 172 + 278 = 450FP
AFP = UFP * VAF = 450 * 0.95 = 427.5 (FP)
t = AFP * Productivity = 427.5 (FP) * 12 (m-hrs/FP) = 5130 (m-hrs)
PM = t / 173 = 5130 (m-hrs) / 173 (m-hrs/month) = 29.65 (m-months)
b = t * Rate = 5130 (m-hrs) * 15 ($/m-hrs) = 76.950 ($)
Tnh TDEV, R, Rmax
PM2 = t2 / 173 = 2600 (m-hrs) / 173 (m-hrs/month) = 15.02 (m-months)
P2 = Sched2 / (PM2 ^ 0.3) = 4.5 / (15.02 ^ 0.3) = 4.5 / 2.25 = 2
P = (P1+P2)/2 = (1.25+2)/2 = 1.625
TDEV = P * (PM ^ 0.3) = 1.625 * (29.65 ^ 0.3) = 1.625 * 2.76 = 4.49 thng
R = PM / TDEV = 29.65 / 4.49 = 6.63 ngi
Rmax = R * 125% = 8.25 ngi
Bi 2. Tng t nh bi tp 1 nhng VAF=1.1 v c thm d n P3 vi Sched3=2.5, t3=3460hrs.
GII
Thc hin tnh tng t bi tp 1 nhng ch phi tnh P3 v P = (P1+P2+P3)/3
Bi 3. Tng t nh bi tp 1 nhng GSC=32 v chi ph o to l 5$/ngi/gi cho nhm 4 ngi trong 1
tun hc (t th 2 n th 6).
GII
Thc hin tnh tng t bi tp 1 nhng ch phi tnh phn kinh ph o to:
$5 * 4ngi * 5ngy * 8gi/ngy = $800 T cng dn vo phn kinh ph
Ngoi ra, dng GSC tnh VAF
Bi 4. Cho bng m t cng vic sau:
Cng vic S ngy lm
Ph thuc
Cng vic S ngy lm
Ph thuc
V1
2
V5
12
V2
V2
4
V6
4
V4
V3
4
V1, V2
V7
8
V5
V4
1
V3
V8
10
V6
Hy v s mng, xc nh con ng nguy him, vi ngy bt u Start l 1/11/2009
GII
K hiu V{ES,D,EF,LS,S,LF} vi V cng vic, ES early start, D duration, EF early finish, LS late start, S
slack, LF late finish. Ta c
V1(1,2,2,4,3,5)
V3(5,4,8,6,1,9)
V4(9,1,9,10,1,10)
V6(10,4,13,11,1,14)
V8(14,10,23,15,1,24)
V2(1,4,4,1,0,4)
V5(5,12,16,5,0,16)
V7(17,8,24,17,0,24)
Start
1/11
End
24/11