CATEDRATICO:
Juan Bautista Nieto, PhD
INTEGRANTES:
Licien Yesenia Moncada
20061003548
20061000937
20070000177
20051010713
20070000338
Seccion 701
Materiales:
Madera
0.25m*3.28*1.0m*3.28*1*2 = 5.38 P.T.
0.20m*3.28*3/12*1*2.5*2 = 0.82 P.T.
0.25m*3.28*3/12*1*3.33 =
0.68 P.T.
0.30m*3.28*3/12*1*3.33*2 = 1.64 P.T.
Total
8.52 P.T.
Para entrar en la ficha: 8.52/4 =2.13 P.T.
Clavos
4lb -----------100 P.T.
X-------------8.52 P.T.
X= 0.34 lb
Alambre Dulce
-
0.30m*4 = 1.2m
1.2m/120m/lb= 0.01lb
Acero
Grava : 3/3 = 1 m3
Arena : 2/3= 0.67 m3
Cemento : 1/3 = 0.33m^3x (3.28ft)^3 = 11.65ft^3 = 11.65 bolsas
Agua : Relacin Agua-Cemento igual a 0.50
A/C=0.50 = A/0.33=0.50
A= 0.165 m3
Mano de obra
Encofrado
Calificada
Capataz = 6673*1.4*1.5
= 14013.3 Lps.
Por Jornada = 14013.3/30
= 467.11 Lps.
Suponiendo :
Encofrado = 35 Minutos.
Colado =
15 Minutos.
Total =
50 Minutos.
Tiempo: 50 Minutos x
1 hora__ x _1 Jnd._
50 Minutos
8 Horas
= 0.125 Jnd
No calificada
Pen = 6673*1.4
= 9342.2 Lps.
1 hora__ x _1 Jnd._
50 Minutos
8 Horas
Batido de concreto
1 mezclador de 1 bolsa: 20 batidas/hora
11.65 ______________ X
20 Batidas__________1h
X = 0.58 h
Por Jornada:
0.58h = 0.07 x 2 peones = 0.14 Jnd
8 horas
Equipo
Hormigonera:
Costo de Posesin:
D = 29,102.51-0.01 (29,102.51) = 11.52 Lps/hora
5 aos x 500 h/ao
I = 29,102.51 x (5+1) (0.12) =
2
5(500)
4.19 Lps/hora
1.73 Lps/hora
Sub Total
Costos de Mantenimiento:
1.10 (11.52)
Sub Total
12.67 Lps/hora
12.67 Lps/hora
Costos de Operacin:
Combustible: 0.06x9.0x94 =
50.76 Lps/hora
12.69 Lps/hora
Operador: 58.39x48x52
291.48 Lps/hora
Sub Total
354.93 Lps/hora
TOTAL
385.04 Lps/hora
Tiempo: 15 Minutos x
8 Horas