GOVERNMENT OF GOA ELECTRICITY DEPARTMENT OFFICE OF THE SUB-DIVISIONAL, ENGINEER SUB-DIVISION-III, VALPOI No.

AE/SD-III/(O&M)/Tech-8/12-13/ Date:- /08/2012 To, The Executive Engineer, Elect. Div- VIII (MRT), Electricity Department, Margao Goa. Sub:- Testing of Metering Installation for releasing of 800KVA load to M/s Goa Formulation Pvt. Ltd., Honda IDC,Honda, Sattari- Goa. Sir, With reference to the above you are requested to inspect the HT metering installation for releasing of service connection to M/s Goa Formulation Pvt. Ltd., Honda IDC, Honda, Sattari- Goa & convey your approval for the same. The details of the installation are as follows: 1. Name of the HT consumer : M/s Swanson Plastics Pvt. Ltd. 2. Location 3. Contract demand : Bhuipal, Honda, Sattari-Goa. : 1000KVA

4. Proposed date of energization of HT installation : 28/03/2012 5. i) Details of 33KV CT unit: Make:- Kalpa Electrical Ratio :- 50/5 Sr.N. :- 94282/08,94286/08 & 94310/08 ii) Details of 33KV PT unit: Make:- Instrans Ratio:- 33Kv/110V Sr. No. :- Z/5552, Z/5553 & Z/5554 6. Details of Trivector meter : Make:- L&T Sr. No. :- 11064195 Pulse rate :-10000/unit Current rating:-3x-/5A Voltage :- 3x-/110V

7. Details of consumer transformer : Make :- Prolec, Sr.No.- IT-45303 Capacity:-2500KVA, Ratio:-33/0.433Kv 8. Details of HT Check meter : Make :- L&T Sr.No.:- 7922361 Current rating :- -/5A Pulse rate :- 10000/unit 9. i) Details of 33KV CT unit (Check meter): Make:- Kalpa Electrical Ratio :- 50/5 Sr.N:78762/11, 78763 & 78764/11 ii) Details of 33KV PT unit (Check meter) : Make:- Kalpa electrical Ratio:- 33Kv/110V Sr. No. :-78765/11,78766/11 & 78767/11 10. Approval from the State Electrical Inspector, Panjim-Goa. SAT/ELECT/INSPT/APPRL/1959/888 Dt: 23/02/2012 (enclosed) This is for your further needful.

Yours faithfully, Assistant Exe.Engineer, Elect. SD-III (O&M), Valpoi-Goa

Encl:- As above. Copy to:- The Executive Engineer, Elect. Div-V (O&M), ------ For kind information please. Bicholim-Goa.